8h05 Beam is switched back on in SASE2. HED ready for taking beam.
8h45 BKR is having problems to turn on SA2 beam. Not due to any
Beam actually went down in all beamlines today at 7:02 (for the records).
9h00: Electricity comes back to SASE3.
We can see SCS-XGM crate coming back on (that's how we can tell that power is back).
9h15 BKR struggles with SA2
9h20: Info from TS-OCD: Problem with USV at SASE3, all needs to be switched
9h30 BKR is working on making beam in SA1/3. SA1 beam on IMGFEL, switching to FXE conditions (5.6 keV).
9h08 FXE info:
D3 has reset the alarms for SA1 beamstop monitor 9.1 (burnthrough monitor) and SA3. FXE is ready to receive beam.
9h04 EEE-OCD informs:
Power has been restored to the LA3 PPL PLC
9h08 DOC info:
restoring settings for LA3 PPL as of before today's power cut.
|