| ID | Date | Author | Group | Subject | Text |  |  | 449 | 18 Nov 2023, 06:42 | Tokushi Sato | SPB | Shift summary | X-ray delivery 
 
 1.3-1.7 mJ, 10.7 keV, 1-100
 pulses, stable delivery
 
 
 Optical
 |  |  | 448 | 17 Nov 2023, 06:55 | Tokushi Sato | SPB | Shift summary | X-ray delivery 
 
 1.3-1.7 mJ, 10.7 keV, 1-100
 pulses, stable delivery
 
 
 Optical
 |  |  | 447 | 16 Nov 2023, 06:56 | Tokushi Sato | SPB | Shift summary | X-ray delivery 
 
 1.3-1.7 mJ, 10.7 keV, 1-100
 pulses, stable delivery
 
 
 Optical
 |  |  | 446 | 15 Nov 2023, 07:10 | Jayanath Koliyadu | SPB | Shift end | X-ray delivery 
 
 1.3-1.7 mJ, 1-30 pulses,
 stable delivery
 
 
 Optical
 |  |  | 445 | 13 Nov 2023, 07:16 | Loic Le Guyader | SCS | shift summary | # Shift Summary 
 Achievements
 - Measured elastic line with
 |  |  | 444 | 12 Nov 2023, 07:24 | Benjamin van Kuiken | SCS | Night shift summary | # Shift Summary 
 Achievements
 - Found RIXS signal from CuO
 |   |  | 443 | 10 Nov 2023, 17:39 | Jan Gruenert | XPD | SA2 status | End of 30 keV study 
 The machine finished their attemps
 for 30 keV tuning while using NEPAL injector
 |   |  | 442 | 10 Nov 2023, 14:10 | Antje Trapp | XRO | Euler MDL bugfix - motor velocities restored after stop | The Euler MDL was updated, so that velocities are restored to standard values also after
 the stop button was hit before motion was
 |  |  | 441 | 07 Nov 2023, 15:57 | Janni Eidam |  | KW44 - Leak in Solid Attenuator | There was a leak in the Solid Attenuator that increased on Saturday morning when SPB
 moved the arm number 4 (see last
 |      |  | 440 | 05 Nov 2023, 16:14 | Jan Gruenert | PRC | Status | Finally, we're completely back in operation, and the performance is recovered in
 all beamlines.
 |  |  | 439 | 05 Nov 2023, 12:47 | Jan Gruenert | PRC | Issue | North branch down : another e-beam magnets problem
 
 RC informs 12h45 that the linac
 |  |  | 438 | 05 Nov 2023, 12:18 | Jan Gruenert | PRC | Issue | Accelerator down 9h23 - 12h 
 RC / BKR informs (10am), that due
 to a quadrupole power supply failure in A21
 |  |  | 437 | 05 Nov 2023, 04:08 | Angel Rodriguez Fernandez | MID | Shift summary | stable SASE beam delivery with
 1mJ pulse energy
 we took data
 for different optical laser excitation fluences
 |  |  | 436 | 04 Nov 2023, 13:49 | Jan Gruenert | PRC | Issue | (Temporary) solution for the vacuum incident in SA1
 
 This morning at 7h18 the vacuum
 |  |  | 435 | 04 Nov 2023, 08:15 | Jan Gruenert | PRC | Issue | Beam down for SASE1/3: SASE1 XTD2 vacuum issue
 
 Vacuum interlock of the SA1 / XTD2
 |   |  | 434 | 04 Nov 2023, 02:29 | Johannes Moeller | MID | Shift summary | Stable delivery of SASE at 18 keV.
 The intensity dropped slightly from 1mJ to
 0.88mJ during the evening, but everything
 |  |  | 433 | 03 Nov 2023, 02:08 | Johannes Moeller | HED | Shift summary | stable 18 keV SASE delivery
 measurement
 of siemens star in the morning
 alignment
 of phase plate for the nano focussing lenses
 testing
 |  |  | 432 | 02 Nov 2023, 23:25 | Chan Kim | SPB | Shift summary | X-ray delivery 
 
 19 keV, ~0.9 mJ/pulse,
 stable delivery
 
 
 Optical
 |  |  | 431 | 02 Nov 2023, 19:37 | Jan Gruenert | PRC | Status | Typical delivery status during daytime during the week:
 
 
 SA1 at 19 keV : 841 uJ +/-
 |   |  | 430 | 02 Nov 2023, 02:28 | Johannes Moeller | MID | Shift summary | stable delivery of 1mJ SASE at
 18keV
 NAFO lens characterization
 with caustic scan
 successful detector
 |  |  |