Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
OPERATION-2024 OPERATION-2023 OPERATION-2022 OPERATION-2021 OPERATION-2020 OPERATION-2019 SASE1-2018 SASE1-2017 Experiment data
  OPERATION-2023 logbook, Contact: F.Wolff-Fabris, A.Galler, L.Samoylova, H.Sinn  Not logged in ELOG logo
Message ID: 439     Entry time: 05 Nov 2023, 12:47
Author: Jan Gruenert 
Group: PRC 
Subject: Issue 

North branch down : another e-beam magnets problem

RC informs 12h45 that the linac and the south branch are back in operation and performance is as before the issues with the A21 quadrupole.
However, during the access to XTL, additional manget problems occurred in the T4 and SA3 section.
Several magnet power supplies failed several times, MPS is working on this issue.
Additionally the SA3 burn-through radiation safety monitor was triggered which requires an onsite intervention by D3.
The downtime for SA1/SA3 is expected to last at least one hour.

ELOG V3.1.4-7c3fd00