| ID | 
Date | 
Author | 
Group | 
Subject | 
Text | 
  |  
| 
  449  
 | 
18 Nov 2023, 06:42 | 
Tokushi Sato | SPB | Shift summary | X-ray delivery
 
 
 
	1.3-1.7 mJ, 10.7 keV, 1-100 
pulses, stable delivery
 
 
 
Optical | 
   |  | 
  448  
 | 
17 Nov 2023, 06:55 | 
Tokushi Sato | SPB | Shift summary | X-ray delivery
 
 
 
	1.3-1.7 mJ, 10.7 keV, 1-100 
pulses, stable delivery
 
 
 
Optical | 
   |  | 
  447  
 | 
16 Nov 2023, 06:56 | 
Tokushi Sato | SPB | Shift summary | X-ray delivery
 
 
 
	1.3-1.7 mJ, 10.7 keV, 1-100 
pulses, stable delivery
 
 
 
Optical | 
   |  | 
  446  
 | 
15 Nov 2023, 07:10 | 
Jayanath Koliyadu | SPB | Shift end | X-ray delivery
 
 
 
	1.3-1.7 mJ, 1-30 pulses, 
stable delivery
 
 
 
Optical | 
   |  | 
  445  
 | 
13 Nov 2023, 07:16 | 
Loic Le Guyader | SCS | shift summary | # Shift Summary
 
 
Achievements
 
 - Measured elastic line with | 
   |  | 
  444  
 | 
12 Nov 2023, 07:24 | 
Benjamin van Kuiken | SCS | Night shift summary | # Shift Summary
 
 
Achievements
 
 - Found RIXS signal from CuO | 
    |  | 
  443  
 | 
10 Nov 2023, 17:39 | 
Jan Gruenert | XPD | SA2 status | End of 30 keV study
 
 
The machine finished their attemps 
for 30 keV tuning while using NEPAL injector | 
    |  | 
  442  
 | 
10 Nov 2023, 14:10 | 
Antje Trapp | XRO | Euler MDL bugfix - motor velocities restored after stop | The Euler MDL was updated, so that velocities 
are restored to standard values also after 
the stop button was hit before motion was | 
   |  | 
  441  
 | 
07 Nov 2023, 15:57 | 
Janni Eidam |   | KW44 - Leak in Solid Attenuator | There was a leak in the Solid Attenuator 
that increased on Saturday morning when SPB 
moved the arm number 4 (see last | 
       |  | 
  440  
 | 
05 Nov 2023, 16:14 | 
Jan Gruenert | PRC | Status | Finally, we're completely back in operation,
 
and the performance is recovered in 
all beamlines. | 
   |  | 
  439  
 | 
05 Nov 2023, 12:47 | 
Jan Gruenert | PRC | Issue | North branch down : another e-beam 
magnets problem
 
 
RC informs 12h45 that the linac | 
   |  | 
  438  
 | 
05 Nov 2023, 12:18 | 
Jan Gruenert | PRC | Issue | Accelerator down 9h23 - 12h
 
 
RC / BKR informs (10am), that due 
to a quadrupole power supply failure in A21 | 
   |  | 
  437  
 | 
05 Nov 2023, 04:08 | 
Angel Rodriguez Fernandez | MID | Shift summary | 
 
	stable SASE beam delivery with 
1mJ pulse energy
 
	we took data 
for different optical laser excitation fluences | 
   |  | 
  436  
 | 
04 Nov 2023, 13:49 | 
Jan Gruenert | PRC | Issue | (Temporary) solution for the vacuum 
incident in SA1
 
 
This morning at 7h18 the vacuum | 
   |  | 
  435  
 | 
04 Nov 2023, 08:15 | 
Jan Gruenert | PRC | Issue | Beam down for SASE1/3: SASE1 XTD2 
vacuum issue
 
 
Vacuum interlock of the SA1 / XTD2 | 
    |  | 
  434  
 | 
04 Nov 2023, 02:29 | 
Johannes Moeller | MID | Shift summary | 
 
	Stable delivery of SASE at 18 keV. 
The intensity dropped slightly from 1mJ to 
0.88mJ during the evening, but everything | 
   |  | 
  433  
 | 
03 Nov 2023, 02:08 | 
Johannes Moeller | HED | Shift summary | 
 
	stable 18 keV SASE delivery
 
	measurement 
of siemens star in the morning
 
	alignment 
of phase plate for the nano focussing lenses
 
	testing | 
   |  | 
  432  
 | 
02 Nov 2023, 23:25 | 
Chan Kim | SPB | Shift summary | X-ray delivery
 
 
 
	19 keV, ~0.9 mJ/pulse, 
stable delivery
 
 
 
Optical | 
   |  | 
  431  
 | 
02 Nov 2023, 19:37 | 
Jan Gruenert | PRC | Status | Typical delivery status during daytime 
during the week:
 
 
 
	SA1 at 19 keV : 841 uJ +/- | 
    |  | 
  430  
 | 
02 Nov 2023, 02:28 | 
Johannes Moeller | MID | Shift summary | 
 
	stable delivery of 1mJ SASE at 
18keV
 
	NAFO lens characterization 
with caustic scan
 
	successful detector | 
   |   
 |