  262  
 | 
19 Jun 2023, 09:37 | 
Jan Gruenert | XPD | Shift start | Rampdown day activities
 
 
The main focus is as usual on checking 
all tunnel components and to identify any | 
   |  | 
  347  
 | 
19 Sep 2023, 18:58 | 
Jan Gruenert | PRC | SA1 status | Concerning SASE1:
 
 
Please note that for this week 
the "remote power limit" was set | 
   |  | 
  350  
 | 
21 Sep 2023, 09:24 | 
Jan Gruenert | PRC | SA1 status | Info by R.Kammering (mail 20.9.23 18h25), 
related to the SA1 intensity drops 
during large wavelength scans: | 
   |  | 
  351  
 | 
22 Sep 2023, 00:56 | 
Jan Gruenert | PRC | SA1 status | As agreed beforehand, PRC and SPB/SFX re-assessed 
the SA1 EPS power limit based on actual performance, 
required number of pulses and rep rate, at | 
   |  | 
  354  
 | 
22 Sep 2023, 17:46 | 
Jan Gruenert | PRC | Status | SASE3 gas supply alarm
 
 
SCS 
called the PRC at 17h04 due to a loud audible 
alarm in XHEXP1 and contacted also TS-OCD. | 
   |  | 
  356  
 | 
23 Sep 2023, 07:31 | 
Jan Gruenert | PRC | Issue | 7:23: RC info:
 
an electrical power glitch interrupted 
beam operation, machine down. DESY has power | 
   |  | 
  359  
 | 
23 Sep 2023, 08:50 | 
Jan Gruenert | PRC | Issue | Updates on power glitch
 
 
8h50 No feedback from TS-OCD (still 
not arrived at SASE3 / SCS ?). Phone is busy. | 
      |  | 
  360  
 | 
23 Sep 2023, 14:49 | 
Jan Gruenert | PRC | Status | Update of power outage aftermath
 
 
Achieved 
by now / status
 
 
 
	SASE1
 
	
 
		beam | 
   |  | 
  361  
 | 
23 Sep 2023, 15:35 | 
Jan Gruenert | PRC | Issue | SASE2 :
 
The unavailability of karabo and possibly 
missing cooling water is a problem for | 
   |  | 
  363  
 | 
24 Sep 2023, 07:19 | 
Jan Gruenert | PRC | Attention | Again: power outage !
 
 
As yesterday, at around 7am, power 
was lost in Schendfeld at SASE3. No beam | 
   |  | 
  365  
 | 
24 Sep 2023, 08:05 | 
Jan Gruenert | PRC | Status | 8h05 Beam is switched back on in SASE2. 
HED ready for taking beam.
 
 
8h45 BKR is having problems to | 
   |  | 
  425  
 | 
30 Oct 2023, 14:36 | 
Jan Gruenert | PRC | Issue | The EPD reading system at the turnstiles 
of XTD10 entrance were not working this morning.
 
A necessary ZZ access to XTD10 | 
   |  | 
  426  
 | 
30 Oct 2023, 23:18 | 
Jan Gruenert | PRC | Status | At the end of the MON late shift, the tuning 
status and obtained lasing pulse energies 
(ATT#1) are as follows: | 
    |  | 
  431  
 | 
02 Nov 2023, 19:37 | 
Jan Gruenert | PRC | Status | Typical delivery status during daytime 
during the week:
 
 
 
	SA1 at 19 keV : 841 uJ +/- | 
    |  | 
  435  
 | 
04 Nov 2023, 08:15 | 
Jan Gruenert | PRC | Issue | Beam down for SASE1/3: SASE1 XTD2 
vacuum issue
 
 
Vacuum interlock of the SA1 / XTD2 | 
    |  | 
  436  
 | 
04 Nov 2023, 13:49 | 
Jan Gruenert | PRC | Issue | (Temporary) solution for the vacuum 
incident in SA1
 
 
This morning at 7h18 the vacuum | 
   |  | 
  438  
 | 
05 Nov 2023, 12:18 | 
Jan Gruenert | PRC | Issue | Accelerator down 9h23 - 12h
 
 
RC / BKR informs (10am), that due 
to a quadrupole power supply failure in A21 | 
   |  | 
  439  
 | 
05 Nov 2023, 12:47 | 
Jan Gruenert | PRC | Issue | North branch down : another e-beam 
magnets problem
 
 
RC informs 12h45 that the linac | 
   |  | 
  440  
 | 
05 Nov 2023, 16:14 | 
Jan Gruenert | PRC | Status | Finally, we're completely back in operation,
 
and the performance is recovered in 
all beamlines. | 
   |  | 
  443  
 | 
10 Nov 2023, 17:39 | 
Jan Gruenert | XPD | SA2 status | End of 30 keV study
 
 
The machine finished their attemps 
for 30 keV tuning while using NEPAL injector | 
    |   
 |