Transport to XHE1: Preparation, posted by Orkidia Bilani on 04 Oct 2022, 13:15 
|
We prepared and brought the components, which will be transported to XHE1, into the LKW-Schleuse.
The transport will be carried out tomorrow, 05.10.2022, very early in the morning.
|
Manual red Crane, posted by Orkidia Bilani on 04 Oct 2022, 14:29
|
The manual red crane (from HiBEF) was tested and it WORKS!
Nevertheless an external specialist will take care for the Inbetriebnahme/Zulassung very soon (S.Arslan will contact him).
Instruments (FXE, HiBEF, HED) happy about it |
Transport to XHE1: postponed for tomorrow, posted by Orkidia Bilani on 05 Oct 2022, 10:45
|
Unfortunately it did not succeed, because the elevator in XHE1 is out of service.
Technische Notdienst was there, but could not solve the problem. A technician from "Lutz Aufzüge" will look it up tomorrow.
The Anhänger with the components is in XHE1, the transporter is loaded and ready for the transport tomorrow. |
Hall Crew from 10.10 - 23.10.2022, posted by Orkidia Bilani on 07 Oct 2022, 11:04
|
Next week, 10.10 - 14.10.2022 only one Hall Crew member, M.Lüdeke, will be here. S.Menzel will be on vacation.
On 17.10 - 23.10.2022 Hall Crew is not there. M.Lüdeke and S.Menzel will attend a training
O.Bilani will the whole two weeks on vacation, but always verfügbar. |
Update of the Inventory List: Parts stored in XHE1, posted by Orkidia Bilani on 26 Oct 2022, 13:45
|
The latest/updated inventory list of the parts and components stored in the shaft building XHE1 can be found in Alfresco under:
https://docs.xfel.eu/share/page/site/x-ray-operations/document-details?nodeRef=workspace://SpacesStore/502fb8d6-d305-4447-b4f5-fc34f479ca64
|
Weissklima Technik at SA2, posted by Orkidia Bilani on 27 Oct 2022, 07:54
|
An acustic warning singal was triggered at the Weissklima Technik unit (QR 30755) at SA2- On the display: Nicht dringende Störung.
Acustic signal has been muted, TS will check.
|
SCS Support, posted by Orkidia Bilani on 28 Oct 2022, 10:58
|
| Supported J.Schlappa, SCS, with the transport of a big dewar to their exp.hutch. |
SQS support, posted by Orkidia Bilani on 02 Nov 2022, 14:40
|
Discussed by the end of September with T.Mullins and D. Rivas, to remove the laser tables from the exp.hall area, in case they won't be needed anymore.
Today we supported SQS in dismountig and removing these tables (1*2 m²) from the exp.hall.
Coworkers: O.Bilani, S. Menzel, D. Rivas, J. Monotano |
Hall Organization Meeting, posted by Orkidia Bilani on 11 Nov 2022, 07:36
|
Hall Organization Meeting on 10.11.2022:
- Only SPP/SFX and SCS were present.
- FXE didn't have time, but reported via email. |
SQS: Transport from XHE1 to XHEXP1, posted by Orkidia Bilani on 11 Nov 2022, 15:19
|
Y. Ovcharenko wrote a Redmine Ticket to XO Transport:
The DSSC components: QR 47932, QR 47938, QR48494 should be brought back to XHEXP1. Already booked the transporter for Thursday 17.11.2022. |
SQS: "Igel" Kammer, posted by Orkidia Bilani on 15 Nov 2022, 12:58
|
M. Ilchen (with Desy Transport) removed the "Igel" chamber from the exp.hall and brought it to Desy back.
|
Transport from XHEXP1 to XHE1 and back: 17.11.2022, posted by Orkidia Bilani on 16 Nov 2022, 10:02
|
SPB/SFX: Transport of a big optical table from the exp.hall to XHE1. Alreaday craned from XHCrew and S.Arslan and is now in the LKW Schleuse.
HiBEF: J. Hauser wants a component back in the exp.hall. (Will come back today with other parts to be stored in the XHE1, needs support with
XIM). The other components would be transported in another day to XHE1). |
SCS Support, posted by Orkidia Bilani on 24 Nov 2022, 10:38
|
A zoom discussion with A. Reich from SCS.
SCS needs the support of the XHCrew starting from monday afternoon next week, in craning in their hutch the plates for the cleanroom. Also in
building up the clean room in their hutch, our support is asked. |
Pulserraum: HiBEF, posted by Orkidia Bilani on 28 Nov 2022, 11:38
|
C.Bähtz needs a temporary space in the hall, to place the materials (5 palltes and a 4m long frame) which be used during the buildiing up of the
Pulserraum.
Delivery expected latest in January 2023. |
TS, posted by Orkidia Bilani on 29 Nov 2022, 08:06
|
TS (A.Kondraschew, D. Tscherwitschka) contacted for temporarily space in the hall.
They need to place the materials which will be used during the maintanance period. Currently these are located near and under the stairs of the
XHVrew Hutch. |
XHCrew Hutch, posted by Orkidia Bilani on 07 Dec 2022, 11:07
|
| Under the XHallCrew office lights have been installed and are functional. |
HiBEF, posted by Orkidia Bilani on 07 Dec 2022, 11:09
|
HiBEF colleauges (mainly J.Hauser) are cleaning up the spaces from the materials which no longer are needed in the hall.
They are preparing a 1-2 pallets with waste.
Many components will be stored in the shaft building XHE1 (will support them wth Redmine Ticket and QR codes). |
SCS: Transport (XHE1, XHEXP1), posted by Orkidia Bilani on 07 Dec 2022, 11:16
|
Until the end of the year SCS needs back from XHE1 to XHEXP1 the components (QR 44265, QR 49608, QR 49609 and QR 49620).
Further, other components will be stored in the XHE1. Details will follow by next week.
|
SQS, posted by Orkidia Bilani on 07 Dec 2022, 14:07
|
Together with T.Mazza checked the COMO source, which is located in XHE1.
This will be brought back in January in XHEXP1, details will follow in due time.
|
SCS Rack Room, posted by Orkidia Bilani on 08 Dec 2022, 08:32
|
The door of the SCS Rack Room can't open, even when activation with the DACHS card shows a green light. It seems to be stucked.
S.Arslan informed via Redmine Ticket. |