Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 14 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Locationdown Severity Subject Text Attachments
  206   04 May 2017, 12:14 Sandor BrockhauserGeneralInformationCAS support during the afternoon: 9-6776Dear All,
 
During the afternoon CAS has a group
  
  207   04 May 2017, 19:40 Jan GrünertGeneralProblemSlow loading in karabo GUIThe current slow response times in the
karabo GUI are the following (some measured
times for reference):
  
  208   05 May 2017, 09:44 Tobias FreyermuthGeneralInformationVAC loop up and running againThe vacuum loop is up and running again,
with the version 1.11.4.
Denis Finze will connect the shutter
  
  209   05 May 2017, 14:35 Nicola CoppolaGeneralInformationAE OCD Mai 5 -- Mai 8AE on call service:
    Contact person:
       
  
  210   06 May 2017, 14:50 Jan GrünertGeneralInformationWP74 OCD contacts for this weekendWP74   OCD  for the 
weekend 6.5.-7.5.2017:
Saturday: Jan, jan.gruenert@xfel.eu,
  
  211   08 May 2017, 15:18 Adriano ViolanteGeneralInformationStatus after the 9.30 Meeting Vacuum (M. Dommach):   
  212   09 May 2017, 16:43 NEREA JARDONGeneralInformationEPS loopDear all,
I will make an update on the EPS
loop, it will take only a moment.
  
  213   09 May 2017, 17:04 NEREA JARDONGeneralInformationEPS loopEPS loop in SASE1 is running again   
  214   10 May 2017, 10:59 NEREA JARDONGeneralInformationVacuum loopDear all,
The update of the Vacuum loop will
take place in the next few minutes, later
  
  215   10 May 2017, 11:06 NEREA JARDONGeneralInformationVacuum LoopSorry for disturbing you, but I will have
to wait till WP74 group finish a training
in order to be able to put the XGM up again
  
  216   10 May 2017, 12:34 NEREA JARDONGeneralInformationVacuum LoopVacuum is up and running again.
Thank you
  
  219   10 May 2017, 18:52 Gero FluckeGeneralInformationCAS OCDCAS on call service for the night:
Gero Flucke: 9-8053
 
  
  220   11 May 2017, 12:43 Alessandro SilenziGeneralInformationNew Deployment of Karabo for the SASE1 control machines.I will ramp down the system and bring it
back up during the lunch break after installing
the 
 download.sh 
  221   11 May 2017, 15:08 Alessandro SilenziGeneralInformationNew Deployment of Karabo for the SASE1 control machines.


   
        
            
  
  222   11 May 2017, 16:41 NEREA JARDONGeneralInformationMotion loopDear all,
I will update the Motion loop to
include the mc2 motors, it will be running
  
  224   11 May 2017, 19:12 Jan GrünertGeneralInformationWP74 OCD contactsPlan of WP74 OCD contacts for May.
Assignments are subject to change.
Initially availability is 10h-18h
 WP74-OCD-5-2017.xlsx 
  225   12 May 2017, 08:21 Harald SinnGeneralInformationRestart vacuum loop now We are in the BRK and corrected the
vacuum interlock condition.
We will restart the SA1 vacuum loop
  
  227   12 May 2017, 12:26 Monica ArestéGeneralInformationUpdate of Instrument component priority list Find attached the Instrument Component
priority list discussed this morning.
Regards,
 170512_Instrument_Components-Priority-list.xlsx 
  228   12 May 2017, 13:19 Alessandro SilenziGeneralInformationNew Deployment of Karabo for the SASE1 control machines.

    

       
            
  
  229   12 May 2017, 13:33 Tobias HaasGeneralInformationStatus and plans after SASE1 Readiness MeetingFocus of meeting is on SASE1 Instruments,
Laser and Detectors
SPB (B. Weinhausen)
 AttendanceS1R120517.pdf 
ELOG V3.1.4-7c3fd00