Group Selection Page HELP Controls Group Data Analysis Group ITDM WP76 DET Vacuum EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Operation PSPO XO TS Migrated2Zulip
OPERATION-2025 OPERATION-2024 OPERATION-2023 OPERATION-2022 OPERATION-2021 OPERATION-2020 OPERATION-2019 SASE1-2018 SASE1-2017 Experiment data
  OPERATION-2024 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn, Page 9 of 12  Not logged in ELOG logo
ID Date Author Group Subjectdown Text Attachments
  165   13 Sep 2024, 23:17 Adam RoundSPBShift endOn Shift: TS,
FT, CK, AR, PS

X-ray
  
  203   23 Nov 2024, 07:09 Raphael de WijnSPBShift endEnd of in-house
8496

X-ray
  
  128   22 Jul 2024, 15:27 Antje TrappXROSASE3 end of shift summarythis morning, ZZ was done together with
Sylvia Huynh (EEE) to solve softmono pre-mirror
motor issue https://redmine.xfel.eu/issues/177392
  
  129   22 Jul 2024, 15:20 Antje TrappXROSASE2 end of shift summaryBeam is now aligned back to HED for hand-over
to Naresh (see picture)

points achieved:
 HED_beam__2024-07-22_15-19-15.png 
  81   11 Apr 2024, 21:54 Antje TrappXROSASE1 MIRROR MOTORS CALIBRATEDDear all,

we calibrated the mirror vertical
motors to their geometrically neutral.
 XRO_optics-setpoints_2024-04-11_22-05-08.png 
  85   20 Apr 2024, 23:58 Jan GruenertPRCSA2 status20.4.2024 / 22h51:
DOC informed PRC that the SASE2 topic
broker had to be restarted.
  
  198   04 Nov 2024, 15:07 Frederik Wolff-FabrisXOSA2 statusDear MID colleagues, Svitozar (PRC), Bolko
and Shan (RCs),
This morning we faced the situation
  
  4   31 Jan 2024, 11:24 Frederik Wolff-FabrisPRCSA1 statusA ZZ is taking place today, 31.01 at
11:30, in XTD9 to verify and fix the M3 Pop-in
screen which is currently blocking the
  
  39   28 Feb 2024, 08:57 Peter ZaldenFXESA1 status5.61 keV setpoint in SA1 was confirmed
to correspond to 5.660 keV (+/- 0.003 keV),
see attached.
 2024-02-28-081608_626485769_exflqr51474.png 
  172   21 Sep 2024, 09:50 Peter ZaldenFXESA1 statusThe xray beam drifted significantly on
wednesday and thursday (18. and 19.) but
then was not drifting on friday (20.), see
 2024-09-21-094858_073864177_exflqr51474.png 
  195   28 Oct 2024, 09:58 Peter ZaldenFXESA1 statusThis is to report some findings during
operation that should be looked into (mostly
to avoid in the future, because both negatively
 2024-10-28-095823_156722903_exflqr37199.png2024-10-28-100227_584317851_exflqr37199.pngScreenshot_2024-11-08_093316.png 
  210   26 Nov 2024, 09:47 Andreas KochXPDSA1 statusConcerning
damage of the SA1 FEL imager, Operation-2024
eLog #206
 SA1_FEL_imager_-_damaged_spot_at_YAG_-_original_screen_position.pngSA1_FEL_imager_-_damaged_spot_at_YAG_-_new_screen_position.png 
  80   10 Apr 2024, 17:03 Kelin TascaXROM3 calibration- M3 TX moved to 0 in steps of 1 mm and
beam on FXE Pop-In corrected with M3 RY (+)
and M2 RY
 SA1_M1_calibration.odsM3_at_nominal_2024-04-10_21-16-39.pngM3_calibrated_2024-04-10_21-20-34.png 
  157   30 Aug 2024, 13:02 Antje TrappXROM1 Rz damaged - DO NOT MOVE!!!What has happened:
During euler motion calibration of
M1, we were driving the vertical motors by
 6x 
  108   19 May 2024, 14:49 Antje TrappXROM1 - M2 - M3 euler fine tuning geometriy parametersWe fine tuned geometry parameters for linear
effects on X motion (parallel offset) for
all three mirrors.
 Screenshot_from_2024-05-19_15-18-51.png 
  1   28 Jan 2024, 13:50 Jan GruenertPRCIssueRC / BKR informs : Beam is down
(since 12h10), all beamlines affected

The reason is failure of a quadrupole
  
  7   01 Feb 2024, 21:56 Romain LetrunSPBIssueAt 21:29:20 today, the number of bunches
in SASE1 was increased from 1 to 352 without
intervention of the SPB/SFX shift crew. 30
 Screenshot_from_2024-02-01_21-52-15.pngScreenshot_from_2024-02-01_21-31-53.png 
  24   13 Feb 2024, 08:52 Romain LetrunSPBIssueLike after the previous winter maintenance
period, the shutter of FXE appears as opened
in DOOCS panels even though it is closed
 Screenshot_from_2024-02-13_08-51-02.png 
  27   17 Feb 2024, 08:15 Tommaso MazzaSQSIssueThe cross on the FEL imager, which we use
as a reference for BKR crew, is not centred
on the GATT aperture. when was this changed,
 Screenshot_from_2024-02-17_08-12-43.pngScreenshot_from_2024-02-17_08-17-03.pngScreenshot_from_2024-02-03_16-06-39.png 
  37   27 Feb 2024, 09:56 Romain LetrunSPBIssueThe status of the XTD2 attenuators has
been checked during the experiment last week
and many were found to cause disturbances
 8x 
ELOG V3.1.4-7c3fd00