  84  
 | 
20 Apr 2024, 23:37 | 
Juncheng E | SPB | Shift summary | Staff: JK, SB, JE, AS, RW, FK
 
 
**X-ray delivery:**
 
- 21 keV, ~500 uJ | 
   |  | 
  83  
 | 
18 Apr 2024, 19:31 | 
Jan Gruenert | PRC | Status | The intra-bunchtrain feedback (IBFB) was 
not active until today afternoon.
 
Although not strictly required or | 
   |  | 
  82  
 | 
13 Apr 2024, 23:03 | 
Peter Zalden | FXE | Shift summary | Measurements to check the impact of bunch 
compression on FXE mono transmission were 
successful. We could change the peak current | 
   |  | 
  81  
 | 
11 Apr 2024, 21:54 | 
Antje Trapp | XRO | SASE1 MIRROR MOTORS CALIBRATED | Dear all,
 
 
we calibrated the mirror vertical 
motors to their geometrically neutral. | 
    |  | 
  80  
 | 
10 Apr 2024, 17:03 | 
Kelin Tasca | XRO | M3 calibration | - M3 TX moved to 0 in steps of 1 mm and 
beam on FXE Pop-In corrected with M3 RY (+) 
and M2 RY | 
      |  | 
  79  
 | 
10 Apr 2024, 16:35 | 
Antje Trapp | XRO | start of shift - status | Starting shift with mirror motor calibration:
 
 
- beam is centered on FEL imager
 
 
- pblm in XTD9 is inserted | 
       |  | 
  78  
 | 
10 Apr 2024, 16:35 | 
Antje Trapp | XRO | start of shift - status | Starting shift with mirror motor calibration:
 
 
- found solid attenuator 0.5mm 
silicon inserted | 
       |  | 
  77  
 | 
10 Apr 2024, 11:55 | 
Harald Sinn | PRC | Status | Yesterday two motors of the SASE2 seeding 
mono were damaged. The mono was exchanged 
in the afternoon and pumped down. Currently, | 
   |  | 
  76  
 | 
08 Apr 2024, 06:37 | 
Marcin Sikorski | SPB | Shift end | In-house/commissioning beam time summary 
night 5
 
 
X-ray delivery: | 
   |  | 
  75  
 | 
07 Apr 2024, 07:04 | 
Raphael de Wijn | SPB | Shift summary | In-house/commissioning beam time summary 
night 4
 
 
X-ray delivery: | 
   |  | 
  74  
 | 
06 Apr 2024, 07:06 | 
Raphael de Wijn | SPB | Shift summary | Staff: MS, RB, PS, RdW
 
 
In-house/commissioning beam time 
summary night 3 | 
   |  | 
  73  
 | 
05 Apr 2024, 07:14 | 
Raphael de Wijn | SPB | Shift summary | In-house/commissioning beam time summary 
night 2
 
 
X-ray delivery: | 
   |  | 
  72  
 | 
04 Apr 2024, 06:48 | 
Raphael de Wijn | SPB | Shift summary | In-house/commissioning beam time summary 
night 1
 
 
X-ray delivery: | 
   |  | 
  71  
 | 
31 Mar 2024, 23:20 | 
Adam Round | SPB | Shift end | X-ray delivery
 
 
 
	12.72 keV, 10Hz, ~1.4 mJ/pulse, 
some beam drift in the horizontal direction | 
   |  | 
  70  
 | 
30 Mar 2024, 22:50 | 
Chan Kim | SPB | Shift summary | X-ray delivery
 
 
- 12.72 keV, 10Hz, ~1.4 mJ/pulse, 
continuous beam drift in the horizontal direction | 
   |  | 
  69  
 | 
30 Mar 2024, 22:02 | 
Chan Kim | SPB | Issue | Continuous pointing drift in horizontal 
direction.
 
 
It may trigger a vacuum spike at | 
     |  | 
  67  
 | 
30 Mar 2024, 06:59 | 
Romain Letrun | SPB | Issue | DOOCS panels are again incorrectly reporting 
the FXE shutter as opened when it is in fact 
closed. This had been fixed after it was | 
    |  | 
  68  
 | 
30 Mar 2024, 00:17 | 
Björn Senfftleben |   | (Resolved) Issues with DAQ | We had some trouble with the DAQ. It was 
not able to start runs properly.
 
 
We got the following error messages: | 
   |  | 
  66  
 | 
29 Mar 2024, 22:38 | 
Chan Kim | SPB | Shift summary | X-ray delivery
 
- 12.72 keV, 10Hz, ~1.4 mJ/pulse, 
stable delivery  | 
   |  | 
  65  
 | 
28 Mar 2024, 14:56 | 
Chan Kim | SPB | Issue | Pulse energy fluctuation observed after 
full train operation in SA2 starts. | 
    |   
 |