Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
OPERATION-2024 OPERATION-2023 OPERATION-2022 OPERATION-2021 OPERATION-2020 OPERATION-2019 SASE1-2018 SASE1-2017 Experiment data
  OPERATION-2024 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn, Page 7 of 11  Not logged in ELOG logo
IDdown Date Author Group Subject Text Attachments
  86   22 Apr 2024, 00:06 Raphael de WijnSPBShift summary
User
beamtime 5157 day 5

X-ray delivery:
  
  85   20 Apr 2024, 23:58 Jan GruenertPRCSA2 status20.4.2024 / 22h51:
DOC informed PRC that the SASE2 topic
broker had to be restarted.
  
  84   20 Apr 2024, 23:37 Juncheng ESPBShift summaryStaff: JK, SB, JE, AS, RW, FK

**X-ray delivery:**
- 21 keV, ~500 uJ
  
  83   18 Apr 2024, 19:31 Jan GruenertPRCStatusThe intra-bunchtrain feedback (IBFB) was
not active until today afternoon.
Although not strictly required or
  
  82   13 Apr 2024, 23:03 Peter ZaldenFXEShift summaryMeasurements to check the impact of bunch
compression on FXE mono transmission were
successful. We could change the peak current
  
  81   11 Apr 2024, 21:54 Antje TrappXROSASE1 MIRROR MOTORS CALIBRATEDDear all,

we calibrated the mirror vertical
motors to their geometrically neutral.
 XRO_optics-setpoints_2024-04-11_22-05-08.png 
  80   10 Apr 2024, 17:03 Kelin TascaXROM3 calibration- M3 TX moved to 0 in steps of 1 mm and
beam on FXE Pop-In corrected with M3 RY (+)
and M2 RY
 SA1_M1_calibration.odsM3_at_nominal_2024-04-10_21-16-39.pngM3_calibrated_2024-04-10_21-20-34.png 
  79   10 Apr 2024, 16:35 Antje TrappXROstart of shift - statusStarting shift with mirror motor calibration:

- beam is centered on FEL imager

- pblm in XTD9 is inserted
 Init_2024-04-10_16-34-30.pngstatus_2024-04-10_16-46-01.pngFEL_imag_2024-04-10_16-40-29.pngpblm_2024-04-10_16-52-34.png 
  78   10 Apr 2024, 16:35 Antje TrappXROstart of shift - statusStarting shift with mirror motor calibration:

- found solid attenuator 0.5mm
silicon inserted
 Init_2024-04-10_16-34-30.pngstatus_2024-04-10_16-46-01.pngFEL_imag_2024-04-10_16-40-29.pngpblm_2024-04-10_16-52-34.png 
  77   10 Apr 2024, 11:55 Harald SinnPRCStatusYesterday two motors of the SASE2 seeding
mono were damaged. The mono was exchanged
in the afternoon and pumped down. Currently,
  
  76   08 Apr 2024, 06:37 Marcin SikorskiSPBShift endIn-house/commissioning beam time summary
night 5

X-ray delivery:
  
  75   07 Apr 2024, 07:04 Raphael de WijnSPBShift summaryIn-house/commissioning beam time summary
night 4

X-ray delivery:
  
  74   06 Apr 2024, 07:06 Raphael de WijnSPBShift summaryStaff: MS, RB, PS, RdW

In-house/commissioning beam time
summary night 3
  
  73   05 Apr 2024, 07:14 Raphael de WijnSPBShift summaryIn-house/commissioning beam time summary
night 2

X-ray delivery:
  
  72   04 Apr 2024, 06:48 Raphael de WijnSPBShift summaryIn-house/commissioning beam time summary
night 1

X-ray delivery:
  
  71   31 Mar 2024, 23:20 Adam RoundSPBShift endX-ray delivery


12.72 keV, 10Hz, ~1.4 mJ/pulse,
some beam drift in the horizontal direction
  
  70   30 Mar 2024, 22:50 Chan KimSPBShift summaryX-ray delivery

- 12.72 keV, 10Hz, ~1.4 mJ/pulse,
continuous beam drift in the horizontal direction
  
  69   30 Mar 2024, 22:02 Chan KimSPBIssueContinuous pointing drift in horizontal
direction.

It may trigger a vacuum spike at
 Screenshot_from_2024-03-30_21-59-03.pngScreenshot_from_2024-03-30_21-09-11.png 
  68   30 Mar 2024, 00:17 Björn Senfftleben (Resolved) Issues with DAQWe had some trouble with the DAQ. It was
not able to start runs properly.

We got the following error messages:
  
  67   30 Mar 2024, 06:59 Romain LetrunSPBIssueDOOCS panels are again incorrectly reporting
the FXE shutter as opened when it is in fact
closed. This had been fixed after it was
 Screenshot_from_2024-03-30_06-58-42.png 
ELOG V3.1.4-7c3fd00