  OPERATION-2024 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn, Page 7 of 11  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
IDdown Date Author Group Subject Text Attachments
  89   25 Apr 2024, 21:11 Frederik Wolff-FabrisPRCStatusV0 valve for SA2 closed as the pump P22090I
at HED branch enters in wrong state. This
closed nearby vacuum valves for HED branch and
 Screenshot_2024-04-25_211325.png 
  88   25 Apr 2024, 01:50 Jörg HallmannMIDShift summaryinstrument alignment including NaFos, DES
spectrometer, diamond detector, PUMA &
test samples
  
  87   22 Apr 2024, 23:26 Raphael de WijnSPBShift summaryEnd of User beamtime 5157


X-ray
delivery:
  
  86   22 Apr 2024, 00:06 Raphael de WijnSPBShift summary
User
beamtime 5157 day 5

X-ray delivery:
  
  85   20 Apr 2024, 23:58 Jan GruenertPRCSA2 status20.4.2024 / 22h51:
DOC informed PRC that the SASE2 topic
broker had to be restarted.
  
  84   20 Apr 2024, 23:37 Juncheng ESPBShift summaryStaff: JK, SB, JE, AS, RW, FK

**X-ray delivery:**
- 21 keV, ~500 uJ
  
  83   18 Apr 2024, 19:31 Jan GruenertPRCStatusThe intra-bunchtrain feedback (IBFB) was
not active until today afternoon.
Although not strictly required or
  
  82   13 Apr 2024, 23:03 Peter ZaldenFXEShift summaryMeasurements to check the impact of bunch
compression on FXE mono transmission were
successful. We could change the peak current
  
  81   11 Apr 2024, 21:54 Antje TrappXROSASE1 MIRROR MOTORS CALIBRATEDDear all,

we calibrated the mirror vertical
motors to their geometrically neutral.
 XRO_optics-setpoints_2024-04-11_22-05-08.png 
  80   10 Apr 2024, 17:03 Kelin TascaXROM3 calibration- M3 TX moved to 0 in steps of 1 mm and
beam on FXE Pop-In corrected with M3 RY (+)
and M2 RY
 SA1_M1_calibration.odsM3_at_nominal_2024-04-10_21-16-39.pngM3_calibrated_2024-04-10_21-20-34.png 
  79   10 Apr 2024, 16:35 Antje TrappXROstart of shift - statusStarting shift with mirror motor calibration:

- beam is centered on FEL imager

- pblm in XTD9 is inserted
 Init_2024-04-10_16-34-30.pngstatus_2024-04-10_16-46-01.pngFEL_imag_2024-04-10_16-40-29.pngpblm_2024-04-10_16-52-34.png 
  78   10 Apr 2024, 16:35 Antje TrappXROstart of shift - statusStarting shift with mirror motor calibration:

- found solid attenuator 0.5mm
silicon inserted
 Init_2024-04-10_16-34-30.pngstatus_2024-04-10_16-46-01.pngFEL_imag_2024-04-10_16-40-29.pngpblm_2024-04-10_16-52-34.png 
  77   10 Apr 2024, 11:55 Harald SinnPRCStatusYesterday two motors of the SASE2 seeding
mono were damaged. The mono was exchanged
in the afternoon and pumped down. Currently,
  
  76   08 Apr 2024, 06:37 Marcin SikorskiSPBShift endIn-house/commissioning beam time summary
night 5

X-ray delivery:
  
  75   07 Apr 2024, 07:04 Raphael de WijnSPBShift summaryIn-house/commissioning beam time summary
night 4

X-ray delivery:
  
  74   06 Apr 2024, 07:06 Raphael de WijnSPBShift summaryStaff: MS, RB, PS, RdW

In-house/commissioning beam time
summary night 3
  
  73   05 Apr 2024, 07:14 Raphael de WijnSPBShift summaryIn-house/commissioning beam time summary
night 2

X-ray delivery:
  
  72   04 Apr 2024, 06:48 Raphael de WijnSPBShift summaryIn-house/commissioning beam time summary
night 1

X-ray delivery:
  
  71   31 Mar 2024, 23:20 Adam RoundSPBShift endX-ray delivery


12.72 keV, 10Hz, ~1.4 mJ/pulse,
some beam drift in the horizontal direction
  
  70   30 Mar 2024, 22:50 Chan KimSPBShift summaryX-ray delivery

- 12.72 keV, 10Hz, ~1.4 mJ/pulse,
continuous beam drift in the horizontal direction
  