ID |
Date |
Author |
Group |
Subject |
Text |
|
147
|
12 Aug 2024, 02:07 |
Wonhyuk Jo | MID | Shift summary | Found spatial overlap at Suna microscope
with Zyla cam.
The splitting ratio was obtained about |
|
149
|
13 Aug 2024, 02:04 |
Wonhyuk Jo | MID | Shift summary | Found the interference fringe at Suna microscope
with Zyla cam from MID split-and-delay line.
The fringe patterns were recorded |
|
164
|
13 Sep 2024, 02:16 |
Wonhyuk Jo | MID | Shift summary | - DAQ was crashed after taking darks of
AGIPD. It was solved by DOC and OCD.
- Laser could not switched from |
|
167
|
14 Sep 2024, 02:23 |
Wonhyuk Jo | MID | Shift summary | - The seeding optimization result: Total
450 uJ (Seeding of 150 uJ + SASE of
300 uJ). BKR will be able to start |
|
169
|
15 Sep 2024, 02:16 |
Wonhyuk Jo | MID | Shift summary | - The seeding optimization is ongoing,
which was not successful. Now we have a total
of 170 uJ including SASE and seeding. |
|
171
|
16 Sep 2024, 02:21 |
Wonhyuk Jo | MID | Shift summary | - Pump-probe experiments are being conducted
using PuMa and PP laser.
- The user program is ongoing over |
|
177
|
26 Sep 2024, 01:46 |
Jörg Hallmann | MID | Shift summary | Started the day with vacuum & detector
issues
real start of the experiments only |
|
179
|
27 Sep 2024, 01:51 |
Jörg Hallmann | MID | Shift summary | started initial alignment for the ptycho
experiment
Continued with XPCS measurement using |
|
182
|
28 Sep 2024, 01:31 |
Jörg Hallmann | MID | Shift summary |
started
with data acquisition for the ptycho experiment |
|
183
|
28 Sep 2024, 23:42 |
Jörg Hallmann | MID | Shift summary | continued with the evaluation of the XPCS
analysis packages
investigated the effect of alignment |
|
189
|
30 Sep 2024, 01:50 |
Jörg Hallmann | MID | Shift summary | 01:49
|
|
196
|
31 Oct 2024, 02:43 |
Ulrike Boesenberg | MID | Shift summary | 12.389keV, HXRSS, 1-400+ bunches, 450uJ
Seeding alignment
Beamline
alignment (Mirror + foccussing)
Measured |
|
215
|
05 Dec 2024, 00:06 |
Jörg Hallmann | MID | Shift summary |
machine
runs at 17 keV with about 1.2 mJ
|
|
9
|
02 Feb 2024, 12:40 |
Konopkova Zuzana | HED | Shift summary | beam parametes: 8.5-9 kev, 1.2
mJ, 1-2 pulses
HED trajectory |
|
25
|
13 Feb 2024, 08:55 |
Konopkova Zuzana | HED | Experiment summary | *Achievements :
- Generally rather successful with
very high quality beam parameters |
|
32
|
24 Feb 2024, 11:58 |
Motoaki Nakatsutsumi | HED | Shift summary | Shift summary 2024-02-23 07:00 - 2024-02-24 10:00
We got self-seeding at 8.5 keV
very quickly after changeover from 10.5 keV |
|
34
|
25 Feb 2024, 14:47 |
Motoaki Nakatsutsumi | HED | Shift summary | Shift summary for 2024-02-24 from 07:00
to 2024-02-25 at 14:00:
Self-seeding at 8.5 keV, with approximately |
|
36
|
26 Feb 2024, 14:32 |
Motoaki Nakatsutsumi | HED | Shift summary | Shift summary for 2024-02-25 from
11:00 to 2024-02-25 at 14:00:
Self-seeding at 8.5 keV, with approximately |
|
95
|
05 May 2024, 00:25 |
Konopkova Zuzana | HED | Experiment summary |
proposal 5700 finished on 04.05.
The experiment used 352 pulses at
4.5 MHz and 18 keV to X-ray heat |
|
114
|
27 May 2024, 06:41 |
Konopkova Zuzana | HED | Shift summary | beam parameters: 2 colors
at around 6.5 keV, 1 pulse
achievements: |
|
|