  1   16 Jan 2023, 11:33 Theophilos MaltezopoulosXPDStatus

I started the upstream XGMs in XTD2, XTD1, and XTD10.

  7   23 Jan 2023, 10:43 Jan GruenertPRCStatus

Status of machine SASE tuning (just before switching off for monday maintenance):

11.5 GeV operation SASE1 SASE2 SASE3
Photon energy 7 keV 7 keV 700 eV
Max. obtained average pulse energy 3.25 mJ 1.35 mJ 5.8 mJ
FEL pointing confirmed on IMGFEL handover cross ?   YES  

 

Attachment 1: JG_2023-01-23_um_10.04.56.png
JG_2023-01-23_um_10.04.56.png
  26   11 Feb 2023, 13:55 Andreas GallerPRCStatus

Gun Modulator Problems

Gun Trip at 11:23 and since then the Modulator trips after each restart.
Accelerator Shift Crews and On Call personnel working on fixing the issue.

  100   23 Mar 2023, 13:07 Naresh KujalaXPDStatus

Update for elog 99:

Now Gotthard timing is changed to new setting for 0.5 MHz.

attached screenshot with gothard timing setting

Machine changed from 0.5 MHz to 1.1MHz new screenshot attached2

 

Attachment 1: Screenshot_from_2023-03-23_13-04-58.png
Screenshot_from_2023-03-23_13-04-58.png
Attachment 2: Screenshot_from_2023-03-23_13-17-05.png
Screenshot_from_2023-03-23_13-17-05.png
  101   23 Mar 2023, 14:31 Romain LetrunSPBStatus

After SASE1 HIREX GOTTHARD reconfiguration, we now get a single pulse per frame. This was verified by comparing data from HIREX recorded with 564 kHz and 1.13 MHz X-ray repetition rates. Both intensity and number of peaks is comparable for the two repetition rates.

Attachment 1: 20230323_HIREX_integral2.png
20230323_HIREX_integral2.png
Attachment 2: 20230323_HIREX_mean_spectrum2.png
20230323_HIREX_mean_spectrum2.png
Attachment 3: 20230323_HIREX_peaks2.png
20230323_HIREX_peaks2.png
  104   24 Mar 2023, 19:42 Naresh KujalaPRCStatus

Reply to elog103:

Spoke with Machine RC Thomas Wamsat and SQS.

Machine RC has some ideas to try. SQS have agreed that they can give 30 min for the machine to optimize the intensity.

SA1 has no impact while the machine trying to improve the power for SA3.

 

Update at 21.17hr

Machine RC has optimized for higher pulse intensity for SQS from 900uJ to 1600uJ. But still, the problem reported in elog103 exists, However, SQS can work now and overnight.

Thanks to Thomas Wamsat for his effort to support.

 

 

  109   26 Mar 2023, 13:26 Naresh KujalaPRCStatus

Machine RC Raimond informed PRC that there is an issue with the A4 module that needs to fix to have a continuous operation. To fix this they need 20 min.

Agreed with all instruments (SPB, SQS, and HED) that at 13:30hr machine will take over the beam for 20 min.

Update: 13:55hr

Machine finished fixing the issue for the A4 module and beam handover to all beamlines.

 

 

  169   03 May 2023, 13:01 Jan GruenertPRCStatus

The machine tuning over the night had not yet accomplished fully satisfactory beam conditions mainly at the high photon energies for SA1 and SA2,
therefore tuning continued during WED morning.
Beam was handed over to SCS (SASE3) at 9h with about 2.4mJ at 2.5 keV.
Beam was handed over to FXE (SASE1) at 13h with about 530uJ at 19.5 keV.
Tuning for MID (SASE2) at 23 keV is agreed to continue until 14h, currently at a level of 120 uJ. 

Attachment 1: JG_2023-05-03_um_13.10.33.png
JG_2023-05-03_um_13.10.33.png
  226   05 Jun 2023, 08:28 Naresh KujalaPRCStatus

- SA2 photon beamline

Today morning found the CRL1: 5 and 6 arm and Pop-in 45-I are still IN. I have retracted them.

Attachment 1: SA2_Main-Status_05-06-23.PNG
SA2_Main-Status_05-06-23.PNG
  227   06 Jun 2023, 08:28 Naresh KujalaXPDStatus

SA2 photon beamline

- SRA position were 7 mm x 7 mm, MID reported they see the hallow of beam shadow at MID Popin

- I have closed the SRA to 3.5 mm x 3.5 mm

 

Attachment 1: SRA-Before_changing_1.PNG
SRA-Before_changing_1.PNG
Attachment 2: SRA-after_changing.PNG
SRA-after_changing.PNG
  242   10 Jun 2023, 21:52 Jan GruenertPRCStatus

The Cryo team solved the problems, beam is back.
Downtime from 17h59 until 21h03.

Attachment 1: JG_2023-06-10_um_21.55.46.png
JG_2023-06-10_um_21.55.46.png
  257   16 Jun 2023, 11:42 Abhisakh SarmaSPBStatus

Beam is back at around 11:30 pm

We lost 1 hr 30 min of beam time.(it was promised to get back at around 10:00 am)

If we want to change the pulse number then we need to call BKR.

Attachment 1: Screenshot_from_2023-06-16_11-41-39.png
Screenshot_from_2023-06-16_11-41-39.png
  273   23 Jul 2023, 17:28 Frederik Wolff-FabrisPRCStatus

Photon Activities by XPD colleagues in SA3 are concluded on Sunday 23.07 at 17:00. The photon commissioning activities are concluded for this week.

The PRC agrees with RCs to handle beam back to BKR for further tuning activities while touching common nobs.

  274   25 Jul 2023, 19:18 Harald SinnPRCStatus

After the 12 hour cryo failure last night, it was decided to exchange a faulty window with some reduced transmission at the injector laser today (see email by Andreas to xo-info yesterday). 

This was sucessful and the injector tunnel was closed today 16:40 and restart of the gun is ongoing. Tomorrow ramp up and SASE tuning.

The hope is that the large jitter and the poor SASE performance of last week can be now improved.  Beam delivery to instrument is expected on Thursday. 

  276   28 Jul 2023, 14:46 Harald SinnPRCStatus

As discussed, there will be a beam interuption form 14:45 until probably 15:45 related to jitter studies at A1 that the BKR would like to try out. 

Harald

  278   28 Jul 2023, 15:37 Harald SinnPRCStatus

Good news: The 'jitter'-tests was sucessful and BKR could identify the jitter source related to a wrong software setting around the AH1 module of injector.

This was now fixed and the jitter has disappeared smiley . It is likely that the tuning was compromised by this setting from the beginning of this run (July11).

On Monday morning, a fresh tuning round will be started with hopefully improved SASE performance. Until then photon delivery with what we have.  

  317   22 Aug 2023, 18:15 Naresh KujalaPRCStatus

Photon beam delivery status:

- Machine informed that beam will be handover to instruments SA1 (SPB/SFX) and SA3 (SXP) at 18.30hr

- Machine needs more time for SA2 and the next update will be at 20hr.

This message has been communicated to instruments.

 

  325   26 Aug 2023, 08:23 Naresh KujalaPRCStatus

- Machine updates;

Saturday 1:30 hr Cold compressor failed. The initial estimation of downtime was 20 hr, later in today morning crew gave a new estimation of time of 30 hr. So the machine will be switched on and beam delivery to instruments will be tomorrow morning. Today at 3 pm, I will get more information and a clear picture of the best estimation time for beam delivery.

Naresh

 

 

  326   26 Aug 2023, 18:02 Naresh KujalaPRCStatus

Dear All,

Two important machine updates.

1) Still, the forecasted time for the start-up of the machine will be tomorrow morning.

2) After discussion with machine RC, it is confirmed that beam delivery is extended by 24 hr, so the beam is available till 7 am Tuesday morning for instruments.

Just want to point out, that this is a very exceptional case that it is extended by 24 hours as there will be a blue week(in wk 35).

The below programs have been canceled keeping in view of the user program and beam delivery is important for instruments. Sorry for this.

153339 - Euler MDL calibration for SASE2 mirrors M1, M2, M3: Antje 

158376 - Beamtime for Safety tests (HED Preabsorber): Eric

156699 - SASE3_XTD10 Virtual Spectrometer: Joakim

157789 - Chirp-dispersion short pulses study (further decoupling from SASE1): Svitozar

 

Stay tuned to the public display tomorrow morning for the machine's status.

thanks

Naresh

PRC wk 34

 

  338   09 Sep 2023, 07:54 Naresh KujalaPRCStatus

Info from MRC (Lars)

-----------------------------------------------------------------------------

The cryo crew reports that the cold compressor that failed is, alas!,
the new one with the magnetic bearing. They have to wait for a colleague
who is not on call to help them with the problem. We expect an update on
their further plans around noon and our status panels have been updated
to reflect that.

Cheers,
Lars

-----------------------------------------------------------------------------

 