Message ID: 326     Entry time: 26 Aug 2023, 18:02
Author: Naresh Kujala 
Group: PRC 
Subject: Status 

Dear All,

Two important machine updates.

1) Still, the forecasted time for the start-up of the machine will be tomorrow morning.

2) After discussion with machine RC, it is confirmed that beam delivery is extended by 24 hr, so the beam is available till 7 am Tuesday morning for instruments.

Just want to point out, that this is a very exceptional case that it is extended by 24 hours as there will be a blue week(in wk 35).

The below programs have been canceled keeping in view of the user program and beam delivery is important for instruments. Sorry for this.

153339 - Euler MDL calibration for SASE2 mirrors M1, M2, M3: Antje 

158376 - Beamtime for Safety tests (HED Preabsorber): Eric

156699 - SASE3_XTD10 Virtual Spectrometer: Joakim

157789 - Chirp-dispersion short pulses study (further decoupling from SASE1): Svitozar

 

Stay tuned to the public display tomorrow morning for the machine's status.

thanks

Naresh

PRC wk 34

 