Group Selection Page HELP Controls Group Data Analysis Group ITDM WP76 DET Vacuum EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Operation PSPO XO TS Migrated2Zulip
OPERATION-2025 OPERATION-2024 OPERATION-2023 OPERATION-2022 OPERATION-2021 OPERATION-2020 OPERATION-2019 SASE1-2018 SASE1-2017 Experiment data
  OPERATION-2023 logbook, Contact: F.Wolff-Fabris, A.Galler, L.Samoylova, H.Sinn  Not logged in ELOG logo
Message ID: 226     Entry time: 05 Jun 2023, 08:28
Author: Naresh Kujala 
Group: PRC 
Subject: Status 

- SA2 photon beamline

Today morning found the CRL1: 5 and 6 arm and Pop-in 45-I are still IN. I have retracted them.

Attachment 1: SA2_Main-Status_05-06-23.PNG  675 kB  Uploaded 05 Jun 2023, 09:30  | Hide | Hide all
SA2_Main-Status_05-06-23.PNG
ELOG V3.1.4-7c3fd00