576
|
01 Mar 2024, 14:05 |
Orkidia Bilani | XHEXP | Information | General | -> Stromkabel @SQS:
The yellow and the orange ones
was/is on the way in the experiment hall, |
  |
582
|
05 Mar 2024, 14:42 |
Orkidia Bilani | XHEXP | Information | Damaged concrete floor in SASE3 and SASE2 | The damages of the concrete floor in SCS
area and SASE3 in general, as well as the
damages in SASE2 under the truck bay were |
|
590
|
08 Mar 2024, 15:37 |
Orkidia Bilani | XHEXP | Information | SXP Support | SXP wanted to buy and place a cabinet under
the stairs in front of their experiment hutch
and asked for advice. Unfortunately it wouldn't |
    |
591
|
11 Mar 2024, 10:26 |
Orkidia Bilani | XHEXP | Information | Not needed consumables | A palett with unneeded consumables was
sent to the warehouse and O. Smith will take
care of that. |
|
597
|
13 Mar 2024, 15:42 |
Orkidia Bilani | XHEXP | Information | SXP: Consumables Storage | V. Vardanyan (SXP) gave a box full of consumables
for the consumables storage. |
|
598
|
13 Mar 2024, 21:09 |
Orkidia Bilani | XHEXP | Information | Consumables Storage | Sorted out a box with screws, nuts, u.Ä.,
which was donated from SXP. |
|
603
|
15 Mar 2024, 10:57 |
Orkidia Bilani | XHEXP | Information | SCS: Consumables Storage | SCS gave a box full
of consumables for the consumables storage. |
|
607
|
18 Mar 2024, 08:03 |
Orkidia Bilani | XHEXP | Information | Waste in the Experiment Hall | Disposed waste from the Experiment Hall. |
|
610
|
19 Mar 2024, 14:32 |
Orkidia Bilani | XHEXP | Information | SCS Transport | Discussed with J.T. Delitz about the transport
of their components. He will label the parts
and where to be transported. We'll find |
|
611
|
20 Mar 2024, 10:55 |
Orkidia Bilani | XHEXP | Information | SCS Support: Transport to Warehouse | SCS: Brought a chiller and a pallet with
boxes with equipment at the warehouse. |
 |
614
|
22 Mar 2024, 13:47 |
Orkidia Bilani | XHEXP | Information | SQS: Emergency craning | Craned for SQS the chain of the manual
crane.
This because the REMI needed to |
|
621
|
25 Mar 2024, 14:22 |
Orkidia Bilani | XHEXP | Problem | Terminal at XHEXP1: TH1 near SQS | The transponder system on the turnstile
near SQS (TH1) doesn't work. Informed
SRP and they are working on it. |
|
623
|
27 Mar 2024, 14:06 |
Orkidia Bilani | XHEXP | Information | Work on the Consumables' Storage | 26.03.2024: Planned and worked on the consumables's
storage.
|
|
629
|
03 Apr 2024, 08:27 |
Orkidia Bilani | XHEXP | Information | HiBEF Waste | Disposed the left over waste from the pulser
(Baureste) out of the Experiment Hall.
Co-workers: B.Näser, O.Bilani |
 |
635
|
10 Apr 2024, 08:16 |
Orkidia Bilani | XHEXP | Information | Waste | Disposed waste (Brandlast) out of the Experiment
Hall. |
|
664
|
26 Apr 2024, 16:19 |
Orkidia Bilani | XHEXP | Information | Consumables' storage | The four pallets with consumables, which
O.Smith gave, have been all placed ordered
in the cabinets of XHCrew consumables' |
 |
679
|
09 May 2024, 14:25 |
Orkidia Bilani | XHEXP | Information | SASE3: Dräger, SCS Empore | T. Mazza (SQS) called to inform about an
alarm at the Dräger gas cabinet.
Went to quit/mute the alarm (yellow |
 |
680
|
11 May 2024, 11:39 |
Orkidia Bilani | XHEXP | Information | SASE3: Dräger, SCS Empore | The battery for the "Notstromausfall"
needs to be exchanged. C.Holz ordered already
new ones and will exchange them as soon |
|
681
|
11 May 2024, 12:24 |
Orkidia Bilani | XHEXP | Information | MID: He 5.0 | Moin Sascha,
wie telefonisch besprochen, am
Montag früh braucht MID He 5.0. Es sind |
|
682
|
11 May 2024, 13:36 |
Orkidia Bilani | XHEXP | Information | SCS: Pumpedisplay | Near the SCS Clean Tent, where the big
chamber is, below, on the pump there is a
control monitor/display. It peeps and perhpas |
 |