ID |
Date |
Author |
Location |
Severity |
Subject |
Text |
|
478
|
20 Nov 2023, 15:02 |
Moritz Peter | General | Information | Transport Uetersen | Montagehilfe für Cryofan #47620 von
Uetersen nach XFEL transportiert und in den
Laserraum über HED mit dem Stapler gehoben. |
|
55
|
06 Oct 2022, 08:21 |
Michael Luedeke | General | Information | SQS Laserboard Regal 2 | 5.10.2022 ---> Rose Krieger Profile
gesägt und montiert |
|
56
|
06 Oct 2022, 08:23 |
Michael Luedeke | General | Information | SQS Hutch Kühlwasser | 29.9.22 ---> SQS Kühlwasser an
einer Vacuumpumpe installiert |
|
57
|
06 Oct 2022, 08:25 |
Michael Luedeke | General | Information | SQS Hutch 19" Gerät montiert | 28.09.22 ---> 19" Gerät montiert,
dazu Rose Krieger Winkel angepasst |
|
62
|
10 Oct 2022, 11:04 |
Michael Luedeke | General | Information | Lasertisch bei SQS Kranen | SQS Lasertisch von Beamline Position F1
zu F2 Kranen.
(Email Auftrag vom 9.10.22 ---> |
|
63
|
10 Oct 2022, 12:44 |
Michael Luedeke | General | Information | Kranarbeit FXE | 10.10.2022 ---> Kranarbeit bei FXE wie
besprochen durchgeführt |
|
64
|
11 Oct 2022, 15:03 |
Michael Luedeke | General | Information | SQS Gestell befestigen | 11.10.22 ---> SQS Hutch, Doppelkreuz
Rahmengestell am Boden befestigen, 4 Bohrungen |
|
65
|
12 Oct 2022, 13:09 |
Michael Luedeke | General | Information | Abstützung für SQS Laserboard | 12.10.22: Abstützung für SQS
Laserboard montiert, da der Lasertisch ohne
Abstützung schwingt. Die Abstützung |
|
92
|
17 Nov 2022, 14:30 |
Michael Luedeke | XHEXP | Information | SCS Kammer verschieben | 17.11.2022: Email von Jan Torben - SCS
Kammer verschieben. Wurde heute Morgen erledigt. |
|
100
|
29 Nov 2022, 15:09 |
Michael Luedeke | General | Information | SCS Installation for Cleantent 22_11_29 | |
|
101
|
30 Nov 2022, 14:49 |
Michael Luedeke | General | Information | SCS Cleantent Day 2 22-11-30 | |
|
102
|
07 Dec 2022, 08:15 |
Michael Luedeke | General | Information | SCS clean tent installation 6.12.2022 | Installation C-Profile
Moving Chamber 1
Moving Chamber 2 |
8x |
107
|
08 Dec 2022, 07:51 |
Michael Luedeke | General | Information | SCS clean tent 7.12.2022 | Preparation top plate part 1 (drilling,
cutting, mounting) |
|
110
|
09 Dec 2022, 07:55 |
Michael Luedeke | General | Information | SCS clean tent installation 8.12.2022 | The big aluminium plate is mounted
The frame of the clean tent is
well moving |
|
118
|
16 Dec 2022, 11:51 |
Michael Luedeke | General | Information | SQS start installation frame for exhaust | |
|
120
|
21 Dec 2022, 07:48 |
Michael Luedeke | General | Information | SQS Frame Installation for exaust air 20.12.2022 | |
|
162
|
27 Jan 2023, 12:51 |
Michael Luedeke | General | Information | 4 Abstandshalter für SQS Nils gefertigt | |
|
181
|
15 Feb 2023, 08:30 |
Michael Luedeke | General | Information | 14.02.2023 - SQS Como Frame vom Experiment abbauen | Siehe Task 156
Como Frame vom Experiment entfernt
und Rollen montiert. |
|
184
|
16 Feb 2023, 14:56 |
Michael Luedeke | General | Information | Parts for SCS | Die gestern mit Sascha angefangen Teile
für SCS sind jetzt fertig. |
|
914
|
07 Nov 2024, 12:41 |
Kai-Erik Pfeiffer | XHEXP | Information | Transport to XHE1 | Transported two aluminum Boxes for SPB/SFX
and 2 Granite Blocks for SQS from XHEXP to
XHE1. |
|