59
|
03 Mar 2017, 16:46 |
Tobias Haas | General | Information | Minutes of weekly SASE1 Readiness Meeting | Here is the link to the minutes Minutes |
|
60
|
06 Mar 2017, 18:14 |
Andreas Koch | XTD2 | Information | Pop-In II-45 Karabo test |
Normal
0
|
|
61
|
07 Mar 2017, 10:21 |
NEREA JARDON | XTD9 | Information | XTD9-DPS | Dear all,
Tomorrow morning, 08th of March at
09.30h. I will be in the tunnel doing interlock |
|
62
|
07 Mar 2017, 11:09 |
Andreas Koch | XTD2 | Information | Karabo testing on Wednesday | As discussed with Wajid, I am availalbe
tomorrow Wednesday the whole day to continue
testing Karabo, motion loop. Wajid checked |
|
63
|
08 Mar 2017, 13:11 |
NEREA JARDON | XTD9 | Information | Interlock tests DPS | The interlock test in XTD9-DPS has been
done. The Vacuum PLC is again available for
Karaboo. |
|
65
|
08 Mar 2017, 16:18 |
Andreas Koch | XTD2 | Information | Karabo testing | Here the link to the detailed list of issues:
https://docs.xfel.eu/share/page/site/xfelwp74/document-details?nodeRef=workspace://SpacesStore/1733b825-e62e-47af-abba-fdef1ff9485d |
|
66
|
08 Mar 2017, 18:26 |
Alessandro Silenzi | General | Information | Karabo Deployment Documentation link | Url to the readthedocs documentation:
|
|
67
|
10 Mar 2017, 11:15 |
Tobias Haas | General | Information | Update of Tunnel Component Priority List after SASE1 Readiness Meeting | |
|
68
|
10 Mar 2017, 11:18 |
Tobias Haas | XHEXP | Information | Instrument Component Priority List update after SASE1 Readiness Meeting | |
|
69
|
10 Mar 2017, 11:34 |
Alessandro Silenzi | General | Information | Link to the redmin list of Tasks. | https://in.xfel.eu/redmine/projects/control-support/issues
Short Instructions:
- Add your task |
|
70
|
10 Mar 2017, 12:53 |
Tobias Haas | General | Information | Update of Tunnel Component Priority List after SASE1 Readiness Meeting | Note that due to a bug in the elog the
name appeared wrongly in my previous message.
In general: Avoid underscores in the file |
|
71
|
10 Mar 2017, 14:56 |
Lewis Batchelor | XTD2 | Information | CRL | The XTD2 CRL is now aligned and cabled.
Motor cabling is complete and ready
for local testing. Encoder and PT100 cabling |
|
72
|
10 Mar 2017, 16:56 |
Tobias Haas | General | Information | Tunnel Commissioning Schedule for Week 11 |
Day
|
|
73
|
13 Mar 2017, 15:47 |
NEREA JARDON | General | Information | Vacuum and Motion down | Tomorrow, 14th of March, Vacuum and Motion
loop will be down at least during morning
due to technical reasons . |
|
74
|
14 Mar 2017, 13:55 |
NEREA JARDON | General | Information | Vacuum and Motion down | Dear all,
Finally today the Vacuum and Motion
will still running the hole day and I would |
|
75
|
15 Mar 2017, 08:13 |
Andreas Koch | XTD2 | Information | XTD2 Imagers | XTD2, IMAG.2694.T9, Pop-In II-45: Acceptance
test of motor control under Karabo, done.
Camera device needs further explanations |
|
76
|
15 Mar 2017, 11:31 |
NEREA JARDON | General | Information | Vacuum and Motion | Today Denis has to make some changes in
the Vacuum and Motion hardware loop, therefore
they would be down some time. |
|
77
|
15 Mar 2017, 17:00 |
NEREA JARDON | General | Information | Vacuum and Motion | Vacumm and Motion are running again after
the hardware changes. |
|
79
|
16 Mar 2017, 16:54 |
NEREA JARDON | General | Information | Fuses replacement | Dear all,
Tomorrow in the morning is needed
to add some fuses in the PLCs crate, therefore |
|
80
|
17 Mar 2017, 10:49 |
NEREA JARDON | General | Information | Loops up | Dear all, Vacuum and Motion loops are running
again.
Thank you, |
|