ID |
Date |
Author |
Location |
Severity |
Subject |
122
|
10 Apr 2017, 10:09 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
The Vacuum loop is running again, now with XGM XTD9 included. We will be testing interlocks in XGM XTD2, so could be needed another upload.
Thank you, |
125
|
10 Apr 2017, 18:13 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
Right now both XGMs are into the loop and would be running. The loop must run continuously, in case you should do any work, just let me know in advanced.
Thank you, |
128
|
11 Apr 2017, 11:48 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
Vacuum loop is up and running, we would wait till Raul check the interlock of the "OK" signal for the Vacuum and then, if everything is correct, we would put again the XGM controlled by the Vacuum PLC.
Thank you! |
170
|
26 Apr 2017, 09:10 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
We need to update the Vacuum loop in order to correct and add some configuration to the interlock conditions.
It would be running in few minutes again.
Thank you! |
215
|
10 May 2017, 11:06 |
NEREA JARDON | General | Information | Vacuum Loop | Sorry for disturbing you, but I will have to wait till WP74 group finish a training in order to be able to put the XGM up again . |
216
|
10 May 2017, 12:34 |
NEREA JARDON | General | Information | Vacuum Loop | Vacuum is up and running again.
Thank you |
242
|
17 May 2017, 13:57 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
The Vacuum Loop will be updated now. You will be able to connect to it again in few minutes.
Thank you, |
266
|
30 May 2017, 10:56 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
It is needed to add two digital input terminals in Rack 1.17 and 1.18 in XTD9 for the vacuum loop, and Denis will do it in the next minutes. Therefore you will loose communication for those motion racks.
Thank you
|
267
|
30 May 2017, 11:08 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
Sorry, my last message was not correct. We will do the hardware changes when we have prepared the Vacuum update also.
Thank you |
268
|
30 May 2017, 15:52 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
We will run the update of the Vacuum loop in the next half hour.
Thank you! |
270
|
30 May 2017, 18:32 |
NEREA JARDON | General | Information | Vacuum Loop | We will run again an update in the Vacuum loop, just to fix small bug detected.
Thank you |
272
|
30 May 2017, 20:42 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
We have detected with Karabo guys that there was a problem in the IonPumps in SASE1. The IonPumps are working, Raúl went to the Tunnel to check the controllers in XTD9 to confirm that.
According with Raúl and CAS people, we have arranged to do the next Vacuum update tomorrow early in the morning. I will post a new entry to let you know and I will contact now WP74 people in order to be quickly with the loop update tomorrow.
Thank you and sorry for the disturbing. |
273
|
31 May 2017, 10:45 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all, we will proceed with the update of the Vacuum loop.
Thank you! |
318
|
06 Jul 2017, 12:49 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
Sorry for the short notice, but we have to do an update of the Vacuum loop in order to get the neecssary interlock for the experiments done. I will contact know WP74 and Vacuum group so they can be awared about their equipments.
Thank you, |
319
|
06 Jul 2017, 15:03 |
NEREA JARDON | General | Information | Vacuum Loop | Vacuum Loop is running again.
Thank you!
NEREA JARDON wrote: |
Dear all,
Sorry for the short notice, but we have to do an update of the Vacuum loop in order to get the neecssary interlock for the experiments done. I will contact know WP74 and Vacuum group so they can be awared about their equipments.
Thank you,
|
|
21
|
09 Jan 2017, 10:47 |
Sabine Cunis | XTD2 | Information | VCTF-list updated | The VCTF-components-list has been updated. Labels on components, as far as visible, are in accordance with names in list.
... please, check for consistency, when naming and labeling XGM components! |
145
|
13 Apr 2017, 16:21 |
Tobias Freyermuth | General | Feedback | VAC loop up and running agian | The first EtherCAT coupler in 1.7 VAC was broken and is replaced now. The loop is up and running again.
Cheers,
Tobias |
208
|
05 May 2017, 09:44 |
Tobias Freyermuth | General | Information | VAC loop up and running again | The vacuum loop is up and running again, with the version 1.11.4.
Denis Finze will connect the shutter signals of the XS3 shutter to the vacuum loop in rack 1.7.
|
230
|
12 May 2017, 13:59 |
Harald Sinn | General | Information | V0 open! | V0 is open now!
Janni opened this morning at 11:00 the V0 valve towards the accelerator vacuum.
We removed the B4C absorber in front of the valve and now the spontaneous radiation can enter the Schenefeld vacuum.
The interlock conditions for Vacuum loop and EPS loops towards the DESY MPS were tested and they are now enabled.
This means that rebooting SA1 VACUUM or EPS loop will stop the beam during the reboot (therefore call 4500 before you do it).
|
81
|
17 Mar 2017, 12:11 |
Thomas Tschentscher | General | Information | Updated Tunnel component status list | Updated list of tunnel high priority components after SASE1 Readiness mtg this morning. The list has also been sent for comments/clarifications to the involved Groups/People. |
Attachment 1: 170317-Tunnel-Components-Priority-list.xlsx
|
|