Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 4 of 30  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown
  122   10 Apr 2017, 10:09 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

The Vacuum loop is running again, now with XGM XTD9 included. We will be testing interlocks in XGM XTD2, so could be needed another upload.

Thank you,

  125   10 Apr 2017, 18:13 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

Right now both XGMs are into the loop and would be running. The loop must run continuously, in case you should do any work, just let me know in advanced.

Thank you,

  128   11 Apr 2017, 11:48 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

Vacuum loop is up and running, we would wait till Raul check the interlock of the "OK" signal for the Vacuum and then, if everything is correct, we would put again the XGM controlled by the Vacuum PLC.

Thank you!

  170   26 Apr 2017, 09:10 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

We need to update the Vacuum loop in order to correct and add some configuration to the interlock conditions.

It would be running in few minutes again.

Thank you!

  215   10 May 2017, 11:06 NEREA JARDONGeneralInformationVacuum Loop

Sorry for disturbing you, but I will have to wait till WP74 group finish a training in order to be able to put the XGM up again .

  216   10 May 2017, 12:34 NEREA JARDONGeneralInformationVacuum Loop

Vacuum is up and running again.

Thank you

  242   17 May 2017, 13:57 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

The Vacuum Loop will be updated now. You will be able to connect to it again in few minutes.

Thank you,

  266   30 May 2017, 10:56 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

It is needed to add two digital input terminals in Rack 1.17 and 1.18 in XTD9 for the vacuum loop, and Denis will do it in the next minutes. Therefore you will loose communication for those motion racks.

Thank you

 

  267   30 May 2017, 11:08 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

Sorry, my last message was not correct. We will do the hardware changes when we have prepared the Vacuum update also.

Thank you

  268   30 May 2017, 15:52 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

We will run the update of the Vacuum loop in the next half hour.

Thank you!

  270   30 May 2017, 18:32 NEREA JARDONGeneralInformationVacuum Loop

We will run again an update in the Vacuum loop, just to fix small bug detected.

Thank you

  272   30 May 2017, 20:42 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

We have detected with Karabo guys that there was a problem in the IonPumps in SASE1. The IonPumps are working, Raúl went to the Tunnel to check the controllers in XTD9 to confirm that.

According with Raúl and CAS people, we have arranged to do the next Vacuum update tomorrow early in the morning. I will post a new entry to let you know and I will contact now WP74 people in order to be quickly with the loop update tomorrow.

Thank you and sorry for the disturbing.

  273   31 May 2017, 10:45 NEREA JARDONGeneralInformationVacuum Loop

Dear all, we will proceed with the update of the Vacuum loop.

Thank you!

  318   06 Jul 2017, 12:49 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

Sorry for the short notice, but we have to do an update of the Vacuum loop in order to get the neecssary interlock for the experiments done. I will contact know WP74 and Vacuum group so they can be awared about their equipments.

Thank you,

  319   06 Jul 2017, 15:03 NEREA JARDONGeneralInformationVacuum Loop

Vacuum Loop is running again.

Thank you!

NEREA JARDON wrote:

Dear all,

Sorry for the short notice, but we have to do an update of the Vacuum loop in order to get the neecssary interlock for the experiments done. I will contact know WP74 and Vacuum group so they can be awared about their equipments.

Thank you,

 

  21   09 Jan 2017, 10:47 Sabine CunisXTD2InformationVCTF-list updated

The VCTF-components-list  has been updated. Labels on components, as far as visible, are in accordance with names in list.

... please, check for consistency, when naming and labeling XGM components!

  145   13 Apr 2017, 16:21 Tobias FreyermuthGeneralFeedbackVAC loop up and running agian

The first EtherCAT coupler in 1.7 VAC was broken and is replaced now. The loop is up and running again.

Cheers,

    Tobias

  208   05 May 2017, 09:44 Tobias FreyermuthGeneralInformationVAC loop up and running again

The vacuum loop is up and running again, with the version 1.11.4.

Denis Finze will connect the shutter signals of the XS3 shutter to the vacuum loop in rack 1.7.

 

  230   12 May 2017, 13:59 Harald SinnGeneralInformationV0 open!

V0 is open now!

Janni opened this morning at 11:00 the V0 valve towards the accelerator vacuum.

We removed the B4C absorber in front of the valve and now the spontaneous radiation can enter the Schenefeld vacuum. 

The interlock conditions for Vacuum loop and EPS loops towards the DESY MPS were tested and they are now enabled. 

This means that rebooting SA1 VACUUM  or EPS loop will stop the beam during the reboot (therefore call 4500 before you do it).

 

IMG_4609.jpg 

  81   17 Mar 2017, 12:11 Thomas TschentscherGeneralInformationUpdated Tunnel component status list
Updated list of tunnel high priority components after SASE1 Readiness mtg this morning. The list has also been sent for comments/clarifications to the involved Groups/People.
Attachment 1: 170317-Tunnel-Components-Priority-list.xlsx