Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 29 of 29  Not logged in ELOG logo
Entry   overview of required racks, posted by Sabine Cunis on 03 Nov 2016, 17:00 VCCT_Rack_1p06_b.jpgVCCT_Rack_1p07_b.jpg
just for reference ... here are pictures and schematics of the racks which are involved in the current commissioning.
Entry   Current PLC-Karabo Conflict, posted by Alessandro Silenzi on 03 Nov 2016, 12:58 
Tobias Freyermuth and me worked on the system and as of 
Entry   Minutes of last week's meeting, posted by Tobias Haas on 26 Oct 2016, 14:26 
 http://tinyurl.com/gvvv392
Entry   Start of Logbook, posted by Tobias Haas on 26 Oct 2016, 13:55 
Dear Colleagues,
in the future we would like to use this mechanism to record and exchange information that concerns the work done within the context of this task
force. Please use this generously. We shall also put a link to the minutes after each weekly meeting.
ELOG V3.1.4-7c3fd00