Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 27 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Datedown Author Location Severity Subject Text Attachments
  77   15 Mar 2017, 17:00 NEREA JARDONGeneralInformationVacuum and MotionVacumm and Motion are running again after
the hardware changes.
  
  76   15 Mar 2017, 11:31 NEREA JARDONGeneralInformationVacuum and MotionToday Denis has to make some changes in
the Vacuum and Motion hardware loop, therefore
they would be down some time. 
  
  75   15 Mar 2017, 08:13 Andreas KochXTD2InformationXTD2 ImagersXTD2, IMAG.2694.T9, Pop-In II-45: Acceptance
test of motor control under Karabo, done.
Camera device needs further explanations
  
  74   14 Mar 2017, 13:55 NEREA JARDONGeneralInformationVacuum and Motion downDear all,
Finally today the Vacuum and Motion
will still running the hole day and I would
  
  73   13 Mar 2017, 15:47 NEREA JARDONGeneralInformationVacuum and Motion downTomorrow, 14th of March, Vacuum and Motion
loop will be down at least during morning
due to technical reasons .
  
  72   10 Mar 2017, 16:56 Tobias HaasGeneralInformationTunnel Commissioning Schedule for Week 11
    
        

           Day
  
  71   10 Mar 2017, 14:56 Lewis BatchelorXTD2InformationCRLThe XTD2 CRL is now aligned and cabled.
Motor cabling is complete and ready
for local testing. Encoder and PT100 cabling
  
  70   10 Mar 2017, 12:53 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness MeetingNote that due to a bug in the elog the
name appeared wrongly in my previous message.
In general: Avoid underscores in the file
 170310-Tunnel-Components-Priority-list.xlsx 
  69   10 Mar 2017, 11:34 Alessandro SilenziGeneralInformationLink to the redmin list of Tasks.https://in.xfel.eu/redmine/projects/control-support/issues
Short Instructions:
- Add your task
  
  68   10 Mar 2017, 11:18 Tobias HaasXHEXPInformationInstrument Component Priority List update after SASE1 Readiness Meeting   170310_Instrument_Components-Priority-list.xlsx 
  67   10 Mar 2017, 11:15 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness Meeting   Components-Priority-list.xlsx 
  66   08 Mar 2017, 18:26 Alessandro SilenziGeneralInformationKarabo Deployment Documentation linkUrl to the readthedocs documentation:
  
  65   08 Mar 2017, 16:18 Andreas KochXTD2InformationKarabo testingHere the link to the detailed list of issues:
https://docs.xfel.eu/share/page/site/xfelwp74/document-details?nodeRef=workspace://SpacesStore/1733b825-e62e-47af-abba-fdef1ff9485d
  
  64   08 Mar 2017, 16:08 Andreas KochXTD2ProblemKarabo testingEnd switch testing: the in-position end
switch stopped devices working, also stopped
gateway connection. Stroke of motor is not
  
  63   08 Mar 2017, 13:11 NEREA JARDONXTD9InformationInterlock tests DPSThe interlock test in XTD9-DPS has been
done. The Vacuum PLC is again available for
Karaboo.
  
  62   07 Mar 2017, 11:09 Andreas KochXTD2InformationKarabo testing on WednesdayAs discussed with Wajid, I am availalbe
tomorrow Wednesday the whole day to continue
testing Karabo, motion loop. Wajid checked
  
  61   07 Mar 2017, 10:21 NEREA JARDONXTD9InformationXTD9-DPSDear all,
Tomorrow morning, 08th of March at
09.30h. I will be in the tunnel doing interlock
  
  60   06 Mar 2017, 18:14 Andreas KochXTD2InformationPop-In II-45 Karabo test






Normal
0
  
  59   03 Mar 2017, 16:46 Tobias HaasGeneralInformationMinutes of weekly SASE1 Readiness Meeting Here is the link to the minutes Minutes   
  58   03 Mar 2017, 16:40 Tobias HaasGeneralInformationUpdate of Component Priority list after weekly meeting   170303_Components-Priority-list.xlsx 