77
|
15 Mar 2017, 17:00 |
NEREA JARDON | General | Information | Vacuum and Motion |
Vacumm and Motion are running again after the hardware changes. |
76
|
15 Mar 2017, 11:31 |
NEREA JARDON | General | Information | Vacuum and Motion |
Today Denis has to make some changes in the Vacuum and Motion hardware loop, therefore they would be down some time.
At least, we would try to keep the Vacuum loop up again for 3pm, therefore Valerii and Raul could use it with Karaboo. |
75
|
15 Mar 2017, 08:13 |
Andreas Koch | XTD2 | Information | XTD2 Imagers |
XTD2, IMAG.2694.T9, Pop-In II-45: Acceptance test of motor control under Karabo, done. Camera device needs further explanations and testing. |
74
|
14 Mar 2017, 13:55 |
NEREA JARDON | General | Information | Vacuum and Motion down |
Dear all,
Finally today the Vacuum and Motion will still running the hole day and I would have to stop them tomorrow morning. Before doing this operation, I will post an entry in the ELOG. |
73
|
13 Mar 2017, 15:47 |
NEREA JARDON | General | Information | Vacuum and Motion down |
Tomorrow, 14th of March, Vacuum and Motion loop will be down at least during morning due to technical reasons .
I will notify you when the works are finished. |
72
|
10 Mar 2017, 16:56 |
Tobias Haas | General | Information | Tunnel Commissioning Schedule for Week 11 |
Day |
Motion |
Vacuum |
EPS |
Other |
Monday |
Loop is up. AE continues tests on MC2 lib |
Loop up. AE investigates problem with ion pump controller |
Loop inactive |
|
Tuesday |
Loop is up. AE continues tests on MC2 lib |
Loop down. AE implements fix for ion pump controller |
Loop inactive |
|
Wednesday |
Loop down. AE adds ELMO and TECHNOSOFT |
Loop up for testing |
AE brings up loop |
|
Thursday |
Loop down. AE adds ELMO and TECHNOSOFT |
Loop up for testing |
AE brings up loop |
|
Friday |
Loop up for testing |
Loop up for testing |
Loop up for testing |
|
In addition it should be tried to have a so called "Happy Hour" every day from 0800 - 1000. During this time loops should be up if possible. Meaning that in the evening before leaving, developers bring loops back up. |
71
|
10 Mar 2017, 14:56 |
Lewis Batchelor | XTD2 | Information | CRL |
The XTD2 CRL is now aligned and cabled.
Motor cabling is complete and ready for local testing. Encoder and PT100 cabling at rack to be completed by the middle of week 11. |
70
|
10 Mar 2017, 12:53 |
Tobias Haas | General | Information | Update of Tunnel Component Priority List after SASE1 Readiness Meeting |
Note that due to a bug in the elog the name appeared wrongly in my previous message. In general: Avoid underscores in the file names! |
Attachment 1: 170310-Tunnel-Components-Priority-list.xlsx
|
69
|
10 Mar 2017, 11:34 |
Alessandro Silenzi | General | Information | Link to the redmin list of Tasks. |
https://in.xfel.eu/redmine/projects/control-support/issues
Short Instructions:
- Add your task
- Select your work package
- Do NOT set the assignee
- Do NOT set the priority
|
68
|
10 Mar 2017, 11:18 |
Tobias Haas | XHEXP | Information | Instrument Component Priority List update after SASE1 Readiness Meeting |
|
Attachment 1: 170310_Instrument_Components-Priority-list.xlsx
|
67
|
10 Mar 2017, 11:15 |
Tobias Haas | General | Information | Update of Tunnel Component Priority List after SASE1 Readiness Meeting |
|
Attachment 1: Components-Priority-list.xlsx
|
66
|
08 Mar 2017, 18:26 |
Alessandro Silenzi | General | Information | Karabo Deployment Documentation link |
Url to the readthedocs documentation:
https://goo.gl/vsz9hu |
65
|
08 Mar 2017, 16:18 |
Andreas Koch | XTD2 | Information | Karabo testing |
Here the link to the detailed list of issues: https://docs.xfel.eu/share/page/site/xfelwp74/document-details?nodeRef=workspace://SpacesStore/1733b825-e62e-47af-abba-fdef1ff9485d |
64
|
08 Mar 2017, 16:08 |
Andreas Koch | XTD2 | Problem | Karabo testing |
End switch testing: the in-position end switch stopped devices working, also stopped gateway connection. Stroke of motor is not correct, parameter list to be checked. More details in "Improvements / bug list". |
63
|
08 Mar 2017, 13:11 |
NEREA JARDON | XTD9 | Information | Interlock tests DPS |
The interlock test in XTD9-DPS has been done. The Vacuum PLC is again available for Karaboo. |
62
|
07 Mar 2017, 11:09 |
Andreas Koch | XTD2 | Information | Karabo testing on Wednesday |
As discussed with Wajid, I am availalbe tomorrow Wednesday the whole day to continue testing Karabo, motion loop. Wajid checked with Narea. I understand that there may be interruptions and that I have not first priority. Thanks, Andreas |
61
|
07 Mar 2017, 10:21 |
NEREA JARDON | XTD9 | Information | XTD9-DPS |
Dear all,
Tomorrow morning, 08th of March at 09.30h. I will be in the tunnel doing interlock tests in the DPS-XTD9 with Raúl.
Therefore I will need the connection of the TCP_Client in the Vacuum loop (just to let know Karaboo people).
I will post again when the PLC is available for Karaboo.
Thank you! |
60
|
06 Mar 2017, 18:14 |
Andreas Koch | XTD2 | Information | Pop-In II-45 Karabo test |
6.3.2017, Karabo tests in XTD2 with Wajid, Andreas
1. Karabo all devices, all scenes working, with restrictions.
2. Power supply, motor, LED working.
3. Scenes tested: Motor scene and camera scene need additional parameters. AK will edit a list of suggestions, improvements and bugs.
4. Bugs, observations, details in improvement list.:
- Homing not working, tried also old parameter set from prototype crate.
- Encoder position not correct, dragging behind.
- Parameter for braking switch missing “ALowSpeed”.
|
59
|
03 Mar 2017, 16:46 |
Tobias Haas | General | Information | Minutes of weekly SASE1 Readiness Meeting |
Here is the link to the minutes Minutes |
58
|
03 Mar 2017, 16:40 |
Tobias Haas | General | Information | Update of Component Priority list after weekly meeting |
|
Attachment 1: 170303_Components-Priority-list.xlsx
|