Entry   Motion loop, posted by NEREA JARDON on 22 Mar 2017, 16:28 

Dear all,

tomorrow morning at 10h am, we will need the Motion PLC for roughly half hour to do some tests. During this time the PLC will be stop.

 

Entry   Motion Loop, posted by NEREA JARDON on 22 Mar 2017, 15:05 

FYI. The Motion loop is again up and running.

Entry   Loop status schedule for KW12, posted by Adriano Violante on 17 Mar 2017, 15:21 

Dear all,

find here the foreseen loop status for KW12. The schedule could change. All changes will be notified by entries in the logbook.

 

Day Motion Vacuum EPS Other 
Monday Loop is up.  Loop up.  Loop up  
Tuesday Loop is up.  Loop down. AE updates loop (maybe short ) Loop up  
Wednesday Loop down. AE updates loop Loop up  Loop up  
Thursday Loop up Loop up  Loop up  
Friday Loop up  Loop up  Loop up  

 

 

Entry   Updated Tunnel component status list, posted by Thomas Tschentscher on 17 Mar 2017, 12:11 170317-Tunnel-Components-Priority-list.xlsx
Updated list of tunnel high priority components after SASE1 Readiness mtg this morning. The list has also been sent for comments/clarifications to the involved Groups/People.
Entry   Loops up, posted by NEREA JARDON on 17 Mar 2017, 10:49 

Dear all, Vacuum and Motion loops are running again.

Thank you,

Entry   Fuses replacement, posted by NEREA JARDON on 16 Mar 2017, 16:54 

Dear all,

Tomorrow in the morning is needed to add some fuses in the PLCs crate, therefore Vacuum and Motion would be down for more or less one hour from 9am. I will notify you when the PLCs are available to work again.

Thank you,

Entry   Wiring status, posted by Torben Falk on 16 Mar 2017, 13:34 

Wiring status SASE 1:

Wiring progress:

  • Internal wiring of the XGM in XTD 9 is done.
  • Vacuum part wiring of the XGM in XTD 9 is done (ready for local Beckhoff test).
  • Gas Panel wiring of the XGM in XTD 9 is done.
  • Crate wiring (ADAM & Femto crate) of the XGM in XTD 9 is done.

Upcoming work XTD 2:

  • Serial connection from Beckhoff to TCP 350.
  • Change cold plug cables into halogenfree cables.

Upcoming work XTD 9:

  • INHIBIT connection Iseg HV crate.
  • Serial connection from MTCA to RVC 300.

Upcoming work XTD 10:

  • Vacuum part wiring of XGM.
  • Gas Panel wiring of XGM.
  • Internal wiring of XGM.
  • Installing ADAM & Femto crate.
  • Measure cable lengths for Imager and prepare cables.
Entry   Vacuum and Motion, posted by NEREA JARDON on 15 Mar 2017, 17:00 

Vacumm and Motion are running again after the hardware changes.

Entry   Vacuum and Motion, posted by NEREA JARDON on 15 Mar 2017, 11:31 

Today Denis has to make some changes in the Vacuum and Motion hardware loop, therefore they would be down some time.

At least, we would try to keep the Vacuum loop up again for 3pm, therefore Valerii and Raul could use it with Karaboo.

Entry   XTD2 Imagers, posted by Andreas Koch on 15 Mar 2017, 08:13 

XTD2, IMAG.2694.T9, Pop-In II-45: Acceptance test of motor control under Karabo, done. Camera device needs further explanations and testing.

Entry   Vacuum and Motion down, posted by NEREA JARDON on 14 Mar 2017, 13:55 

Dear all,

Finally today the Vacuum and Motion will still running the hole day and I would have to stop them tomorrow morning. Before doing this operation, I will post an entry in the ELOG.

Entry   Vacuum and Motion down, posted by NEREA JARDON on 13 Mar 2017, 15:47 

Tomorrow, 14th of March, Vacuum and Motion loop will be down at least during morning due to technical reasons .

I will notify you when the works are finished.

Entry   Tunnel Commissioning Schedule for Week 11, posted by Tobias Haas on 10 Mar 2017, 16:56 
Day Motion Vacuum EPS Other 
Monday Loop is up. AE continues tests on MC2 lib Loop up. AE investigates problem with ion pump controller Loop inactive  
Tuesday Loop is up. AE continues tests on MC2 lib Loop down. AE implements fix for ion pump controller Loop inactive  
Wednesday Loop down. AE adds ELMO and TECHNOSOFT Loop up for testing AE brings up loop  
Thursday Loop down. AE adds ELMO and TECHNOSOFT Loop up for testing AE brings up loop  
Friday Loop up for testing Loop up for testing Loop up for testing  

 

In addition it should be tried to have a so called "Happy Hour" every day from 0800 - 1000. During this time loops should be up if possible. Meaning that in the evening before leaving, developers bring loops back up.

Entry   CRL, posted by Lewis Batchelor on 10 Mar 2017, 14:56 

The XTD2 CRL is now aligned and cabled.

Motor cabling is complete and ready for local testing. Encoder and PT100 cabling at rack to be completed by the middle of week 11.

Entry   Update of Tunnel Component Priority List after SASE1 Readiness Meeting, posted by Tobias Haas on 10 Mar 2017, 12:53 170310-Tunnel-Components-Priority-list.xlsx

Note that due to a bug in the elog the name appeared wrongly in my previous message. In general: Avoid underscores in the file names! 

Entry   Link to the redmin list of Tasks., posted by Alessandro Silenzi on 10 Mar 2017, 11:34 

https://in.xfel.eu/redmine/projects/control-support/issues

Short Instructions:

- Add your task

- Select your work package

- Do NOT set the assignee

- Do NOT set the priority

 

Entry   Instrument Component Priority List update after SASE1 Readiness Meeting, posted by Tobias Haas on 10 Mar 2017, 11:18 170310_Instrument_Components-Priority-list.xlsx
 
Entry   Update of Tunnel Component Priority List after SASE1 Readiness Meeting, posted by Tobias Haas on 10 Mar 2017, 11:15 Components-Priority-list.xlsx
 
Entry   Karabo Deployment Documentation link, posted by Alessandro Silenzi on 08 Mar 2017, 18:26 

Url to the readthedocs documentation:

https://goo.gl/vsz9hu

Entry   Karabo testing, posted by Andreas Koch on 08 Mar 2017, 16:18 

Here the link to the detailed list of issues: https://docs.xfel.eu/share/page/site/xfelwp74/document-details?nodeRef=workspace://SpacesStore/1733b825-e62e-47af-abba-fdef1ff9485d