Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 23 of 30  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown
  246   18 May 2017, 12:18 NEREA JARDONGeneralInformationMotion loop

Dear all,

The motion loop will be updated in 5 minutes. The IMGs are already in safe state, please do not operate nothing. I have already contacted the control room and Harald Sinn as representative of the commissioning team.

Thank you!

  247   18 May 2017, 13:38 NEREA JARDONGeneralInformationMotion loop

The Motion loop is again up and running.

Thank you

  250   18 May 2017, 16:36 NEREA JARDONGeneralInformationMotion loop

Dear all,

I have already contacted Andreas Koch, and Alessandro has contacted the BKR in order to do a new update of the motion loop because of one small bug detected.

I will do the update in the next few minutes.

Thank you,

  269   30 May 2017, 18:14 NEREA JARDONGeneralInformationMotion loop

Dear all,

I will make an update of the Motion loop in the next minutes, all the systems are in safe state.

Thank you

  271   30 May 2017, 19:43 NEREA JARDONGeneralInformationMotion loop

Dear all, we will run another update in the Motion loop.

Thank you

  311   04 Jul 2017, 09:41 NEREA JARDONXTD9InformationMotion loop

Dear all,

Today we are planning to integrate part of Hirex motors into the Motion loop of SASE1. Therefore, the loop will be break, so you will loose communication with whole XTD9 Motion part. I will back again to you when we are done,

Thank you

  312   04 Jul 2017, 10:12 NEREA JARDONXTD2InformationMotion loop

Dear all,

I have received a request from Konstantin Sukharnikov to break the Motion loop in XTD2 from Rack 1.5 in order to do checks in the CRLs. So you will loose communication with almost the whole Motion loop in SASE1. I will let you know when they are finished.

Thank you,

  313   04 Jul 2017, 11:23 NEREA JARDONXTD2InformationMotion loop

We are finished. One encoder terminal has failed and needs replacing: rack 1.5 EC14

NEREA JARDON wrote:

Dear all,

I have received a request from Konstantin Sukharnikov to break the Motion loop in XTD2 from Rack 1.5 in order to do checks in the CRLs. So you will loose communication with almost the whole Motion loop in SASE1. I will let you know when they are finished.

Thank you,

 

  314   04 Jul 2017, 11:47 NEREA JARDONXTD2InformationMotion loop

It will be replaced today around 1pm.Therefore Motion loop will be broken from this rack position.

NEREA JARDON wrote:

We are finished. One encoder terminal has failed and needs replacing: rack 1.5 EC14

NEREA JARDON wrote:

Dear all,

I have received a request from Konstantin Sukharnikov to break the Motion loop in XTD2 from Rack 1.5 in order to do checks in the CRLs. So you will loose communication with almost the whole Motion loop in SASE1. I will let you know when they are finished.

Thank you,

 

 

  315   04 Jul 2017, 14:07 NEREA JARDONXTD2InformationMotion loop

The encoder terminal in rack 1.5 has been replaced.

NEREA JARDON wrote:

It will be replaced today around 1pm.Therefore Motion loop will be broken from this rack position.

NEREA JARDON wrote:

We are finished. One encoder terminal has failed and needs replacing: rack 1.5 EC14

NEREA JARDON wrote:

Dear all,

I have received a request from Konstantin Sukharnikov to break the Motion loop in XTD2 from Rack 1.5 in order to do checks in the CRLs. So you will loose communication with almost the whole Motion loop in SASE1. I will let you know when they are finished.

Thank you,

 

 

 

  171   26 Apr 2017, 09:14 NEREA JARDONGeneralInformationMotion and Vacuum

Vacuum is running again and Motion also, yesterday I forgot to update you about the Motion PLC.

Sorry and best regards,

  185   27 Apr 2017, 17:41 Valerii BondarGeneralInformationMotion Loop is up

Dear all,
motion loop is up and all Karabo devices in it are running.

Thank you.

  83   22 Mar 2017, 15:05 NEREA JARDONGeneralInformationMotion Loop

FYI. The Motion loop is again up and running.

  130   11 Apr 2017, 13:24 NEREA JARDONGeneralInformationMotion Loop

Dear all,

Motion loop is running again with the last update (names for PSLIT and LVDT have been changed).

Thank you,

  25   24 Jan 2017, 18:36 Alessandro SilenziGeneralInformationMore items in the master equipment list

Master Component list is being updated.

https://docs.xfel.eu/share/proxy/alfresco/api/node/content/workspace/SpacesStore/1c6c10cd-d741-410d-bd05-bb00944514dc/MasterEquipmentList.xlsx?a=true

Best regards

Alessandro

  26   26 Jan 2017, 13:10 Tobias FreyermuthXTD2InformationModification of the vacuum PLC loop

The PLC program was modified and downloaded to the PLC, due to allow work on the XGM crate in rack 1.3.

The PLC vacuum loop includes now all vacuum crates in the racks from rack 1.1 to rack 1.7 except rack 1.3 (XGM)

  59   03 Mar 2017, 16:46 Tobias HaasGeneralInformationMinutes of weekly SASE1 Readiness Meeting

 Here is the link to the minutes Minutes

  5   04 Nov 2016, 08:03 Frederike WittmaackGeneralInformationMinutes of last weeks meeting (Oct 28, 2016)
http://tinyurl.com/jy5rsbx
  2   26 Oct 2016, 14:26 Tobias HaasGeneralInformationMinutes of last week's meeting

 http://tinyurl.com/gvvv392

  6   04 Nov 2016, 14:22 Frederike WittmaackGeneralInformationMinutes - Meeting November 4, 2016
http://tinyurl.com/jbog6tz