ID |
Date |
Author |
Location |
Severity |
Subject |
Text |
|
474
|
18 Feb 2018, 17:20 |
Jan Grünert | General | Information | CAS OCD | Here is a information from Sandor on CAS
OCD Numbers
(this info is copied from the SASE1 |
|
494
|
27 Mar 2018, 14:18 |
Jan Gruenert | General | Information | XTD1 open | Info from BKR: the southern tunnels
were opened, thus XTD1 can be accessed now. |
|
464
|
31 Jan 2018, 10:06 |
ITDM Admin | General | Information | exflgateway migration | Today late in the evening (~22:00), the
exflgateway will be migrated to a new hardware.
All users will be logged out before migration |
|
466
|
31 Jan 2018, 22:34 |
ITDM Admin | General | Information | Re: exflgateway migration | The migration has finished, to avoid temporary
problem with ssh you can use
ssh exflgateway -o StrictHostKeyChecking=no |
|
190
|
28 Apr 2017, 14:43 |
Hugo Silva Santos | General | Information | CAS - On-Call Duty Planning - Valerii, Gabriele and Wajid | Dear All,
I would like to share the CAS members
on the OCD from 29/04 to 01/05: |
|
193
|
29 Apr 2017, 10:04 |
Hugo Silva Santos | General | Information | ERRATA: CAS - On-Call Duty Planning - Valerii, Gabriele and Wajid | Dear All,
Still in time, I would like to correct
out schedule. |
|
237
|
16 May 2017, 14:55 |
Hugo Silva Santos | General | Information | CAS On-Call Duty Planning (Until 11/06) | Dear All, |
|
366
|
22 Aug 2017, 09:48 |
Hugo Silva Santos | General | Problem | Karabo down in tunnel | Dear All,
We have a issue on the control
servers and we are already working on it... |
|
367
|
22 Aug 2017, 10:24 |
Hugo Silva Santos | General | Problem | Karabo down in tunnel | Dear All,
We solved the incident and the
services are running normally. We are still |
|
368
|
22 Aug 2017, 10:53 |
Hugo Silva Santos | General | Information | Karabo 2.1.15 in Test | Dear All,
I would like to report that we
started today to test (internally in CAS) |
|
442
|
10 Jan 2018, 14:53 |
Hugo Silva Santos | General | Information | Re: Status and plans after Readiness meeting | Dear Monica,
Just one small correction at "Karabo
2.2.0 being deploy today for FXE." |
|
496
|
29 Mar 2018, 09:48 |
Hugo Silva Santos | General | Information | Re: Status report after dispatch meeting 09.30 | Update regarding Digitizer:
----- Forwarded Message -----
From: "hamed sotoudi namin" |
|
534
|
13 Jun 2018, 11:07 |
Hugo Silva Santos | General | Information | Re: Status report after dispatch meeting 09.30 | Hi All,
Just adding more info:
CAS |
|
537
|
25 Jun 2018, 09:45 |
Hugo Silva Santos | General | Information | Karabo 2.2.4 released (mainly for ITDM, AE and DET) + Deployment dates | Dear All,
I would like to inform that we
released last Friday (22.06) the Karabo 2.2.4 |
|
544
|
10 Jul 2018, 11:23 |
Hugo Silva Santos | General | Information | Re: Karabo 2.2.4 released (mainly for ITDM, AE and DET) + Deployment dates | Dear All,
Please, see below the updates regarding
Karabo 2.2.4.1 deployment: |
|
195
|
02 May 2017, 10:56 |
Harald Sinn | XTD9 | Information | Status of Vacuum System | XTD2: All gate valves are now OK (not interlocked)
after re-instantiating and re-setting the
XGM_DP_OK. |
|
223
|
11 May 2017, 18:26 |
Harald Sinn | XTD10 | Information | XTD10 not open on Monday | Dear all,
contrary to the rumor that I spread
last Tuesday in the PBS meeting, the magnet |
|
225
|
12 May 2017, 08:21 |
Harald Sinn | General | Information | Restart vacuum loop now | We are in the BRK and corrected the
vacuum interlock condition.
We will restart the SA1 vacuum loop |
|
230
|
12 May 2017, 13:59 |
Harald Sinn | General | Information | V0 open! | V0 is open now!
Janni opened this morning at 11:00
the V0 valve towards the accelerator vacuum. |
|
264
|
27 May 2017, 16:31 |
Harald Sinn | General | Information | Status of beam commissioning | We got the beam to the end of XTD9 onto
the SPB screen and FXE Pop-in (the SPB pop-in
does not work). |
|