120
|
07 Apr 2017, 19:13 |
wajid ehsan | XTD2 | Information | Acceptance test IMAGERS (FRIDAY 07-04-2017) |
SA1_XTD2_IMGPII45:
1)
MOTOR/SCREEN(DONE)
2) |
|
358
|
08 Aug 2017, 13:10 |
wajid ehsan | General | Information | KARABO 2.1.13 | As previously announced we will deploy
KARABO 2.1.13 in tunnel under topic
SA1. The system will go down in 10 mins. |
|
359
|
08 Aug 2017, 15:25 |
wajid ehsan | General | Information | KARABO 2.1.13 | The system is up and running.
Regards,
Wajid |
|
320
|
07 Jul 2017, 08:24 |
Wolfgang Freund | General | Information | Karabo K-Mono-scenes | I am working this morning on following
projects:
SA1_KMONO_SYSTEM |
|
324
|
10 Jul 2017, 14:35 |
Wolfgang Freund | XTD2 | Information | K-Mono control | During the first K-Mono test with Karabo
on Friday the first goniometer THETA1 (Elmo
controller) moved beyond the CW limit switch |
|
185
|
27 Apr 2017, 17:41 |
Valerii Bondar | General | Information | Motion Loop is up | Dear all,
motion loop is up and all Karabo
devices in it are running. |
|
232
|
12 May 2017, 15:58 |
Valerii Bondar | General | Information | CAS OCD from today to Monday | Dear all,
CAS phone numbers for OCD:
Friday: Alessandro (98054), |
|
506
|
13 Apr 2018, 09:05 |
Torsten Schoen | XHEXP | Information | SASE3 E.21 and E.22 electrical power distribution | changes according to the racklist on the
electrical power distribution cabinets for
rackrooms E.21 and E.22 are done. Power supply |
|
512
|
17 Apr 2018, 14:23 |
Torsten Schoen | XHEXP | Information | SPB emergency power off tests | Dear all,
the emergency power off test
has been successfully performed in SPB. |
|
78
|
16 Mar 2017, 13:34 |
Torben Falk | General | Feedback | Wiring status | Wiring status SASE 1:
Wiring progress:
Internal wiring of the |
|
1
|
26 Oct 2016, 13:55 |
Tobias Haas | General | Information | Start of Logbook | Dear Colleagues,
in the future we would like to use
this mechanism to record and exchange information |
|
2
|
26 Oct 2016, 14:26 |
Tobias Haas | General | Information | Minutes of last week's meeting | http://tinyurl.com/gvvv392 |
|
9
|
09 Nov 2016, 15:36 |
Tobias Haas | General | Information | Update of Component list | I have included the status columns provided
by Alessandro and Sandor in the component
list. Please find it in the usual location |
|
10
|
11 Nov 2016, 15:43 |
Tobias Haas | General | Information | Mandate for the Extension of the Vacuum Controls Commissioning Task Force | The Vacuum Controls Commissioning Task
Force initially helped to get the vacuum
components extending from the gate valve |
|
22
|
24 Jan 2017, 08:17 |
Tobias Haas | XTD2 | Information | STATUS UPDATE: XTD2 Differential Pumping Modules running under interlock control | Post on behalf of Raul
Villanueva:
|
|
23
|
24 Jan 2017, 08:21 |
Tobias Haas | General | Information | Karabo Names in Vacuum component list | Post on behalf of Harald Sinn:
for
the non-vacuum part of WP73 we have the following |
|
24
|
24 Jan 2017, 08:23 |
Tobias Haas | General | Information | Karabo Names in Vacuum component list | Post on behalf of Alessandro
Silenzi:
|
|
27
|
26 Jan 2017, 17:02 |
Tobias Haas | XTD2 | Problem | XGM at XTD2 / issue with in-vacuum-resistor | Post on behalf
of Jan Grünert: |
|
28
|
27 Jan 2017, 09:25 |
Tobias Haas | General | Information | Software Report | Post on behalf of S. Brockhauser
|
|
33
|
02 Feb 2017, 16:56 |
Tobias Haas | General | Information | Installation List Update | Updates as of 2 Feb 16:30 |
|