Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 27 of 30  Not logged in ELOG logo
ID Date Author Location Severity Subject Text Attachments
  77   15 Mar 2017, 17:00 NEREA JARDONGeneralInformationVacuum and MotionVacumm and Motion are running again after
the hardware changes.
  
  76   15 Mar 2017, 11:31 NEREA JARDONGeneralInformationVacuum and MotionToday Denis has to make some changes in
the Vacuum and Motion hardware loop, therefore
they would be down some time. 
  
  75   15 Mar 2017, 08:13 Andreas KochXTD2InformationXTD2 ImagersXTD2, IMAG.2694.T9, Pop-In II-45: Acceptance
test of motor control under Karabo, done.
Camera device needs further explanations
  
  74   14 Mar 2017, 13:55 NEREA JARDONGeneralInformationVacuum and Motion downDear all,
Finally today the Vacuum and Motion
will still running the hole day and I would
  
  73   13 Mar 2017, 15:47 NEREA JARDONGeneralInformationVacuum and Motion downTomorrow, 14th of March, Vacuum and Motion
loop will be down at least during morning
due to technical reasons .
  
  72   10 Mar 2017, 16:56 Tobias HaasGeneralInformationTunnel Commissioning Schedule for Week 11
    
        

           Day
  
  71   10 Mar 2017, 14:56 Lewis BatchelorXTD2InformationCRLThe XTD2 CRL is now aligned and cabled.
Motor cabling is complete and ready
for local testing. Encoder and PT100 cabling
  
  70   10 Mar 2017, 12:53 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness MeetingNote that due to a bug in the elog the
name appeared wrongly in my previous message.
In general: Avoid underscores in the file
 170310-Tunnel-Components-Priority-list.xlsx 
  69   10 Mar 2017, 11:34 Alessandro SilenziGeneralInformationLink to the redmin list of Tasks.https://in.xfel.eu/redmine/projects/control-support/issues
Short Instructions:
- Add your task
  
  68   10 Mar 2017, 11:18 Tobias HaasXHEXPInformationInstrument Component Priority List update after SASE1 Readiness Meeting   170310_Instrument_Components-Priority-list.xlsx 
  67   10 Mar 2017, 11:15 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness Meeting   Components-Priority-list.xlsx 
  66   08 Mar 2017, 18:26 Alessandro SilenziGeneralInformationKarabo Deployment Documentation linkUrl to the readthedocs documentation:
  
  65   08 Mar 2017, 16:18 Andreas KochXTD2InformationKarabo testingHere the link to the detailed list of issues:
https://docs.xfel.eu/share/page/site/xfelwp74/document-details?nodeRef=workspace://SpacesStore/1733b825-e62e-47af-abba-fdef1ff9485d
  
  64   08 Mar 2017, 16:08 Andreas KochXTD2ProblemKarabo testingEnd switch testing: the in-position end
switch stopped devices working, also stopped
gateway connection. Stroke of motor is not
  
  63   08 Mar 2017, 13:11 NEREA JARDONXTD9InformationInterlock tests DPSThe interlock test in XTD9-DPS has been
done. The Vacuum PLC is again available for
Karaboo.
  
  62   07 Mar 2017, 11:09 Andreas KochXTD2InformationKarabo testing on WednesdayAs discussed with Wajid, I am availalbe
tomorrow Wednesday the whole day to continue
testing Karabo, motion loop. Wajid checked
  
  61   07 Mar 2017, 10:21 NEREA JARDONXTD9InformationXTD9-DPSDear all,
Tomorrow morning, 08th of March at
09.30h. I will be in the tunnel doing interlock
  
  60   06 Mar 2017, 18:14 Andreas KochXTD2InformationPop-In II-45 Karabo test






Normal
0
  
  59   03 Mar 2017, 16:46 Tobias HaasGeneralInformationMinutes of weekly SASE1 Readiness Meeting Here is the link to the minutes Minutes   
  58   03 Mar 2017, 16:40 Tobias HaasGeneralInformationUpdate of Component Priority list after weekly meeting   170303_Components-Priority-list.xlsx 
ELOG V3.1.4-7c3fd00