Entry   Acceptance test IMAGERS (FRIDAY 07-04-2017), posted by wajid ehsan on 07 Apr 2017, 19:13 
 
SA1_XTD2_IMGPII45:
 
1) MOTOR/SCREEN(DONE)
2)
Check operation of range of movement, defined by end switches (DONE) 
3) Check repeatability (DONE)
4)
Entry   KARABO 2.1.13, posted by wajid ehsan on 08 Aug 2017, 13:10 
As previously announced we will deploy KARABO 2.1.13 in tunnel under topic SA1. The system will go down in 10 mins. I will announce it
again as soon the system is up again.

Regards,
Entry   KARABO 2.1.13, posted by wajid ehsan on 08 Aug 2017, 15:25 
The system is up and running.

Regards,

Wajid 
Entry   Karabo K-Mono-scenes, posted by Wolfgang Freund on 07 Jul 2017, 08:24 
I am working this morning on following projects:

SA1_KMONO_SYSTEM
SA1_XTD2_KMONO
Entry   K-Mono control, posted by Wolfgang Freund on 10 Jul 2017, 14:35 
During the first K-Mono test with Karabo on Friday the first goniometer THETA1 (Elmo controller) moved beyond the CW limit switch and stopped  at
the CCW switch. So the goniometer was trapped between both switches with a movement range of a few degrees. Movement of encoder and motor were opposite.
This behaviour is not understood and under investigation.
Entry   Motion Loop is up, posted by Valerii Bondar on 27 Apr 2017, 17:41 
Dear all, 
motion loop is up and all Karabo devices in it are running.
Thank you.
Entry   CAS OCD from today to Monday, posted by Valerii Bondar on 12 May 2017, 15:58 
Dear all,
CAS phone numbers for OCD:
Friday: Alessandro (98054),
Entry   SASE3 E.21 and E.22 electrical power distribution, posted by Torsten Schoen on 13 Apr 2018, 09:05 
changes according to the racklist on the electrical power distribution cabinets for rackrooms E.21 and E.22 are done. Power supply should be stable now.
Please note that there will be emergency power off tests prior to the final acceptance test of SASE3 electrical installations around mid of May. You will
be notified about the exact time and date.
Entry   SPB emergency power off tests, posted by Torsten Schoen on 17 Apr 2018, 14:23 
Dear all,

 the emergency power off test has been successfully performed in SPB.

Nobody can instantly cut the power to non hazardous racks (see racklist.xlsx managed by Ulf Brueggmann) by pushing the emergency off button anymore.
Entry   Wiring status, posted by Torben Falk on 16 Mar 2017, 13:34 
Wiring status SASE 1:
Wiring progress:

    Internal wiring of the XGM in XTD 9 is done.
    Vacuum part wiring of the XGM in XTD 9 is done (ready for local Beckhoff
Entry   Start of Logbook, posted by Tobias Haas on 26 Oct 2016, 13:55 
Dear Colleagues,
in the future we would like to use this mechanism to record and exchange information that concerns the work done within the context of this task
force. Please use this generously. We shall also put a link to the minutes after each weekly meeting.
Entry   Minutes of last week's meeting, posted by Tobias Haas on 26 Oct 2016, 14:26 
 http://tinyurl.com/gvvv392
Entry   Update of Component list, posted by Tobias Haas on 09 Nov 2016, 15:36 elog.tiff
I have included the status columns provided by Alessandro and Sandor in the component list. Please find it in the usual location here: http://tinyurl.com/zn7otsa
Entry   Mandate for the Extension of the Vacuum Controls Commissioning Task Force, posted by Tobias Haas on 11 Nov 2016, 15:43 
The Vacuum Controls Commissioning Task Force initially helped to get the vacuum components extending from the gate valve at 2678 m to the gate valve
at 2730 m in XTD2. This comprised the valves and pumps and the associated vacuum interlock logic. The necessary components were all installed and locally
tested. As the next step the PLC firmware for the control of these devices was generated including the interlock logic. Finally the system was connected
Entry   STATUS UPDATE: XTD2 Differential Pumping Modules running under interlock control, posted by Tobias Haas on 24 Jan 2017, 08:17 
 Post on behalf of Raul Villanueva:
As we just finished the exhaustive testing and final adjustments of local
Entry   Karabo Names in Vacuum component list, posted by Tobias Haas on 24 Jan 2017, 08:21 
Post on behalf of Harald Sinn:
 for the non-vacuum part of WP73 we have the following situation: 
Entry   Karabo Names in Vacuum component list, posted by Tobias Haas on 24 Jan 2017, 08:23 
 Post on behalf of Alessandro Silenzi:
 
Entry   XGM at XTD2 / issue with in-vacuum-resistor, posted by Tobias Haas on 26 Jan 2017, 17:02 
Post on behalf of Jan Grünert:

 
Entry   Software Report, posted by Tobias Haas on 27 Jan 2017, 09:25 
Post on behalf of S. Brockhauser
 Since I am in Grenoble and visiting ESRF, I will not be able to give you the report in person.
Entry   Installation List Update, posted by Tobias Haas on 02 Feb 2017, 16:56 Components-XTD2-9.xlsx
 Updates as of 2 Feb 16:30