  OPERATION-2024 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn, Page 8 of 10  Not logged in ELOG logo
ID Date Author Group Subjectdown Text Attachments
  190   01 Oct 2024, 02:39 Tokushi SatoSPBShift summaryX-ray delivery

    6 keV, ~2.8 mJ, continuous
beam drift in both direction
  
  193   24 Oct 2024, 06:51 Chan KimSPBShift summaryX-ray
delivery

12.4 keV, ~1.4 mJ

Achievements/Observations
  
  194   25 Oct 2024, 05:51 Chan KimSPBShift summaryX-ray delivery

12.4 keV, ~1.4 mJ

 
  
  196   31 Oct 2024, 02:43 Ulrike BoesenbergMIDShift summary12.389keV, HXRSS, 1-400+ bunches, 450uJ


Seeding alignment
Beamline
alignment (Mirror + foccussing)
Measured
  
  197   03 Nov 2024, 00:00 Raphael de WijnSPBShift summaryX-ray delivery

12.5 keV,
~1.6 mJ
  
  71   31 Mar 2024, 23:20 Adam RoundSPBShift endX-ray delivery


12.72 keV, 10Hz, ~1.4 mJ/pulse,
some beam drift in the horizontal direction
  
  76   08 Apr 2024, 06:37 Marcin SikorskiSPBShift endIn-house/commissioning beam time summary
night 5

X-ray delivery:
  
  163   12 Sep 2024, 23:48 Adam RoundSPBShift endX-ray delivery

8.951
keV, 1.6 mJ
  
  165   13 Sep 2024, 23:17 Adam RoundSPBShift endOn Shift: TS,
FT, CK, AR, PS

X-ray
  
  128   22 Jul 2024, 15:27 Antje TrappXROSASE3 end of shift summarythis morning, ZZ was done together with
Sylvia Huynh (EEE) to solve softmono pre-mirror
motor issue https://redmine.xfel.eu/issues/177392
  
  129   22 Jul 2024, 15:20 Antje TrappXROSASE2 end of shift summaryBeam is now aligned back to HED for hand-over
to Naresh (see picture)

points achieved:
 HED_beam__2024-07-22_15-19-15.png 
  81   11 Apr 2024, 21:54 Antje TrappXROSASE1 MIRROR MOTORS CALIBRATEDDear all,

we calibrated the mirror vertical
motors to their geometrically neutral.
 XRO_optics-setpoints_2024-04-11_22-05-08.png 
  85   20 Apr 2024, 23:58 Jan GruenertPRCSA2 status20.4.2024 / 22h51:
DOC informed PRC that the SASE2 topic
broker had to be restarted.
  
  198   04 Nov 2024, 15:07 Frederik Wolff-FabrisXOSA2 statusDear MID colleagues, Svitozar (PRC), Bolko
and Shan (RCs),
This morning we faced the situation
  
  4   31 Jan 2024, 11:24 Frederik Wolff-FabrisPRCSA1 statusA ZZ is taking place today, 31.01 at
11:30, in XTD9 to verify and fix the M3 Pop-in
screen which is currently blocking the
  
  39   28 Feb 2024, 08:57 Peter ZaldenFXESA1 status5.61 keV setpoint in SA1 was confirmed
to correspond to 5.660 keV (+/- 0.003 keV),
see attached.
 2024-02-28-081608_626485769_exflqr51474.png 
  172   21 Sep 2024, 09:50 Peter ZaldenFXESA1 statusThe xray beam drifted significantly on
wednesday and thursday (18. and 19.) but
then was not drifting on friday (20.), see
 2024-09-21-094858_073864177_exflqr51474.png 
  195   28 Oct 2024, 09:58 Peter ZaldenFXESA1 statusThis is to report some findings during
operation that should be looked into (mostly
to avoid in the future, because both negatively
 2024-10-28-095823_156722903_exflqr37199.png2024-10-28-100227_584317851_exflqr37199.pngScreenshot_2024-11-08_093316.png 
  80   10 Apr 2024, 17:03 Kelin TascaXROM3 calibration- M3 TX moved to 0 in steps of 1 mm and
beam on FXE Pop-In corrected with M3 RY (+)
and M2 RY
 SA1_M1_calibration.odsM3_at_nominal_2024-04-10_21-16-39.pngM3_calibrated_2024-04-10_21-20-34.png 
  157   30 Aug 2024, 13:02 Antje TrappXROM1 Rz damaged - DO NOT MOVE!!!What has happened:
During euler motion calibration of
M1, we were driving the vertical motors by
 6x 