24 Nov 2024, 14:09 |
Jan Gruenert | PRC | Issue | Beckhoff communication loss SA1-EPS (again)
14h00
Same issue as before, but now EEE cannot
clear the problem anymore remotely. |
|
207
|
24 Nov 2024, 13:47 |
Jan Gruenert | PRC | Issue | Beckhoff communication loss SA1-EPS
12h19:
BKR informs PRC about a limitation to 30
bunches in total for the north branch. |
|
206
|
23 Nov 2024, 15:11 |
Jan Gruenert | PRC | Issue | Damage on YAG screen of SA1_XTD2_IMGFEL
A
damage spot was detected during the restart
of SA1 beam operation at 14h30. |
|
205
|
23 Nov 2024, 10:27 |
Jan Gruenert | PRC | Issue | SA1 Beckhoff issue
SA1 blocked
to max. 2 bunches and SA3 limited to max
29 bunches |
|
204
|
23 Nov 2024, 10:23 |
Jan Gruenert | PRC | Issue | Broken Radiation Interlock
Beam
was down for all beamlines due to a broken
radiation interlock in the SPB/SFX experimental |
|
203
|
23 Nov 2024, 07:09 |
Raphael de Wijn | SPB | Shift end | End of in-house
8496
X-ray |
|
202
|
23 Nov 2024, 00:48 |
Jan Gruenert | PRC | Issue | Broken Bridges
Around 21h20 the
XPD group notices that several karabo-to-DOOCS
bridges are broken. |
|
201
|
23 Nov 2024, 00:36 |
Jan Gruenert | PRC | Issue | 20h16: beam down in all beamlines due
to a gun problem
20h50: x-ray beams are back |
|
200
|
15 Nov 2024, 10:50 |
Frederik Wolff-Fabris | PRC | Issue | SA2 cell#5 undulator segment moved at ~09:45AM
Fri to 25mm without aparent reason and
undulator experts need a ZZ to exchange power |
|
199
|
12 Nov 2024, 10:07 |
Frederik Wolff-Fabris | PRC | Issue |
- While FEL IMG with YAG screen was
inserted in SA1, EPS/MPS was not limited
to the expected 2 bunches, but to 30 |
|
198
|
04 Nov 2024, 15:07 |
Frederik Wolff-Fabris | XO | SA2 status | Dear MID colleagues, Svitozar (PRC), Bolko
and Shan (RCs),
This morning we faced the situation |
|
197
|
03 Nov 2024, 00:00 |
Raphael de Wijn | SPB | Shift summary | X-ray delivery
12.5 keV,
~1.6 mJ |
|
196
|
31 Oct 2024, 02:43 |
Ulrike Boesenberg | MID | Shift summary | 12.389keV, HXRSS, 1-400+ bunches, 450uJ
Seeding alignment
Beamline
alignment (Mirror + foccussing)
Measured |
|
195
|
28 Oct 2024, 09:58 |
Peter Zalden | FXE | SA1 status | This is to report some findings during
operation that should be looked into (mostly
to avoid in the future, because both negatively |
|
194
|
25 Oct 2024, 05:51 |
Chan Kim | SPB | Shift summary | X-ray delivery
12.4 keV, ~1.4 mJ
|
|
193
|
24 Oct 2024, 06:51 |
Chan Kim | SPB | Shift summary | X-ray
delivery
12.4 keV, ~1.4 mJ
Achievements/Observations |
|
192
|
07 Oct 2024, 16:34 |
Naresh Kujala | PRC | Status | Desy Laser group has fixed the issue about
the laser Synchronization.
https://ttfinfo.desy.de/XFELelog/show.jsp?dir=/2024/41/07.10_M&pos=2024-10-07T14:51:12 |
|
191
|
07 Oct 2024, 15:15 |
Naresh Kujala | PRC | Issue | 14:40hr
FXE and HED reported the laser
synchronization issue. Informed to Machine |
|
190
|
01 Oct 2024, 02:39 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
6 keV, ~2.8 mJ, continuous
beam drift in both direction |
|
189
|
30 Sep 2024, 01:50 |
Jörg Hallmann | MID | Shift summary | 01:49
|
|
|