| ID | 
Date | 
Author | 
Group | 
Subject | 
Text | 
  |  
| 
  224  
 | 
08 Dec 2024, 02:49 | 
Jörg Hallmann | MID | Shift summary | successful measurements of elastomer, gelatine 
& bio samples
 
 
issue: | 
   |  | 
  223  
 | 
07 Dec 2024, 02:04 | 
Jörg Hallmann | MID | Shift summary | data collection of bubbles in elastomers 
(good progress)
 
 
issue: beam loss in the tunnel | 
   |  | 
  222  
 | 
06 Dec 2024, 07:49 | 
Johannes Moeller | MID | Stability Issue | And since the 4th there are some instabilities 
in the vacuum levels at M1 and M2 as well. | 
    |  | 
  221  
 | 
06 Dec 2024, 06:37 | 
Johannes Moeller | MID | Stability Issue | The jumps keep repeating very frequently 
since yesterday afternoon. The overall drift 
of the beam seems to accalerate as well. | 
    |  | 
  220  
 | 
06 Dec 2024, 02:41 | 
Jörg Hallmann | MID | Shift summary | 
 
optimization 
of the timing of the involved components 
(laser, cameras, FEL) | 
    |  | 
  219  
 | 
05 Dec 2024, 19:47 | 
Alexey Zozulya | MID | Stability Issue | Today we have observed multiple large disturbances 
to beam stability. These can be characterised 
by large jumps in the horizontal beam position, | 
    |  | 
  218  
 | 
05 Dec 2024, 15:58 | 
Jan Gruenert | PRC | Issue | additional comment to MESSAGE ID: 217
 
 
PRC was informed by MID at 8h50 
about a new appeared limiation to about 60 | 
   |  | 
  217  
 | 
05 Dec 2024, 09:18 | 
Johannes Moeller | MID | Issue | MID operation limited to 55 bunches by 
SA2_XTD1_OPTICS_PROTECTION/MDL/ATT1 because 
of inserted Si 0.5mm. Seems a bit too tight | 
   |  | 
  216  
 | 
05 Dec 2024, 07:38 | 
Jan Gruenert | PRC | Issue | Accelerator module issue
 
 
7h20: 
BKR/RC inform that there is was issue 
with the A12 Klystron filament which had | 
    |  | 
  215  
 | 
05 Dec 2024, 00:06 | 
Jörg Hallmann | MID | Shift summary | 
 
machine 
runs at 17 keV with about 1.2 mJ
 
 
 | 
   |  | 
  214  
 | 
04 Dec 2024, 15:34 | 
Jan Gruenert | PRC | Status | Beam delivery Status well after tuning 
finished (which went faster than anticipated). | 
    |  | 
  213  
 | 
04 Dec 2024, 07:12 | 
Tomas Popelar | SPB | Shift summary | X-ray delivery
 
 
19 keV, ~ 400  - 450 uJ, 1 
- 128 pulses, stable delivery | 
   |  | 
  212  
 | 
01 Dec 2024, 23:07 | 
Tokushi Sato | SPB | Shift summary | X-ray delivery
 
 
19 keV, ~450 uJ, 1 - 128 pulses, 
stable delivery | 
   |  | 
  211  
 | 
30 Nov 2024, 23:01 | 
Tokushi Sato | SPB | Shift summary | X-ray delivery
 
 
19 keV, ~550 uJ, 1 - 128 pulses, 
stable delivery | 
   |  | 
  210  
 | 
26 Nov 2024, 09:47 | 
Andreas Koch | XPD | SA1 status | Concerning 
damage of the SA1 FEL imager, Operation-2024 
eLog #206 | 
     |  | 
  209  
 | 
24 Nov 2024, 17:23 | 
Jan Gruenert | PRC | Status | Status
 
 
All beamlines in operation.
 
The attachment ATT#1 shows the beam 
delivery of this afternoon, with the pulse | 
    |  | 
  208  
 | 
24 Nov 2024, 14:09 | 
Jan Gruenert | PRC | Issue | Beckhoff communication loss SA1-EPS (again)
 
 
14h00 
Same issue as before, but now EEE cannot 
clear the problem anymore remotely. | 
    |  | 
  207  
 | 
24 Nov 2024, 13:47 | 
Jan Gruenert | PRC | Issue | Beckhoff communication loss SA1-EPS
 
 
12h19: 
BKR informs PRC about a limitation to 30 
bunches in total for the north branch. | 
   |  | 
  206  
 | 
23 Nov 2024, 15:11 | 
Jan Gruenert | PRC | Issue | Damage on YAG screen of SA1_XTD2_IMGFEL
 
 
A 
damage spot was detected during the restart 
of SA1 beam operation at 14h30. | 
      |  | 
  205  
 | 
23 Nov 2024, 10:27 | 
Jan Gruenert | PRC | Issue | SA1 Beckhoff issue
 
 
SA1 blocked 
to max. 2 bunches and SA3 limited to max 
29 bunches | 
      |   
 |