| ID | Date | Author | Group | Subject | Text |  |  | 349 | 20 Sep 2023, 19:42 | Peter Zalden | FXE | Issue | Connerning the phase shifter adjustment after undulator gap scan via karabo:
 
 At 19:30 FXE tested the scan change
 |  |  | 348 | 20 Sep 2023, 02:09 | Jayanath Koliyadu | SPB | Shift end | X-ray delivery 
 
 7 keV, 2.1 mJ, stable delivery
 
 
 Optical
 laser delivery
 |  |  | 347 | 19 Sep 2023, 18:58 | Jan Gruenert | PRC | SA1 status | Concerning SASE1: 
 Please note that for this week
 the "remote power limit" was set
 |  |  | 346 | 18 Sep 2023, 19:14 | Yifeng Jiang | FXE | Issue | We found that the x-ray pulse energy
 dropped a lot when we changed the undulator
 from 5.5 keV to 5.45 keV. We called BKR to
 |    |  | 345 | 15 Sep 2023, 14:54 | Chan Kim | SPB | Issue | Vacuum issue at XTD2 tunnel which might be triggered by SA1_XTD2_ATT Arm5 (1.2mm
 thick CVD diamond)
 |    |  | 344 | 14 Sep 2023, 23:03 | Tokushi Sato | SPB | Shift summary | X-ray delivery 
 
 1.1 mj, 564 kHz, 93 pulses,
 stable delivery
 
 
 Optical
 |  |  | 343 | 14 Sep 2023, 16:49 | Thomas Baumann |  | Summary: Night 13th and Day 14th | The late shift on the 13th fixed remaining problems with the DLD and the calibration
 pipeline.
 |  |  | 342 | 14 Sep 2023, 00:05 | Tokushi Sato | SPB | Shift summary | X-ray delivery 
 
 1.1 mj, 564 kHz, 93 pulses,
 stable delivery
 
 
 Optical
 |  |  | 341 | 13 Sep 2023, 02:18 | Tokushi Sato | SPB | Shift summary | X-ray delivery 
 
 0.5 mj, improved to 1.1
 mj xray energy in the evening
 
 
 Optical
 |  |  | 340 | 09 Sep 2023, 15:03 | Naresh Kujala | PRC | Status | Info from Machine RC (Lars): 
 ----------------------------------------------------------------------------------------------------------------------------------------
 
 Author: Froehlich
 |  |  | 339 | 09 Sep 2023, 11:36 | Naresh Kujala | PRC | Status | - Due to the failure of the cryo cold compressor. The machine is down.
 
 - Next update 9 pm today
 |  |  | 338 | 09 Sep 2023, 07:54 | Naresh Kujala | PRC | Status | Info from MRC (Lars) 
 -----------------------------------------------------------------------------
 
 The cryo crew reports that the
 |  |  | 337 | 09 Sep 2023, 07:00 | Erik Brambrink | HED | Shift summary | Data taken from 11 to cryo failure
 Beam
 conditions stable
 Timing scan
 for different energy
 Operation
 |  |  | 336 | 08 Sep 2023, 06:22 | Erik Brambrink | HED | Shift summary | Improved the alignment procedure:
 
 Using
 the pin to make sure of the spatial overlap
 SAXS
 signal is used to make sure the pin is well
 |  |  | 335 | 07 Sep 2023, 23:46 | Andreas Scherz | SCS | Shift summary | Shift summary 07.09.2023 
 Achievements:
 1. found t0   on LSCO x=0.15
 |  |  | 334 | 07 Sep 2023, 07:24 | Justine Schlappa, Guiseppe Mercurio | SCS | Shift summary, September 7 after nightshift | Achievements: - Optimized hRIXS settings for OK
 edge at 145 deg scattering angle, resolution
 |  |  | 333 | 06 Sep 2023, 23:33 | Ben, Andreas | SCS | Shift Summary | Achievements 
 
 Determined temporal overlap
 between the X-ray and laser
 measured
 |  |  | 332 | 06 Sep 2023, 06:35 | Giuseppe Mercurio | SCS | Giuseppe, Justine | achievements: 
 - we found optimum hRIXS settings
 for 1020 eV but moving the detector arm
 |  |  | 331 | 05 Sep 2023, 22:33 | Oliver Humphries | HED | Shift summary | Received the beam from day shift,
 aligned to beam stop (low signal due to 4m
 air scatter, only 700uJ upstream)
 
 ZYLA5
 |  |  | 330 | 29 Aug 2023, 03:14 | Wonhyuk Jo | MID | Shift summary | Shift summary for 29th of Aug. 
 - Conducted Time-resolved Bragg
 CDI experiment using 3rd harmonic pump laser.
 |  |  |