Message ID: 348     Entry time: 20 Sep 2023, 02:09
Author: Jayanath Koliyadu 
Group: SPB 
Subject: Shift end 

X-ray delivery

  • 7 keV, 2.1 mJ, stable delivery

Optical laser delivery

  • None

Achievements/Observations

  • M1, M2 pre alignment for this weeks beamtime
  • Checked the beam trajectory through MKB mirrors after stripe change

Issues

  • It seems that with wider funnel for the catcher, the YAG is not reaching the X-ray beam

 

Note: At 7 keV with 100 pulses, and full beam we were at 2.2 W average power.