SQS start installation frame for exhaust, posted by Michael Luedeke on 16 Dec 2022, 11:51 
|
|
Update: Stored parts in XHE1, posted by Orkidia Bilani on 19 Dec 2022, 12:42
|
The documentation for the storeed parts in the shaft building XHE1 has been updated and uploaded to Alfresco (see link below):
https://docs.xfel.eu/share/page/site/x-ray-operations/document-details?nodeRef=workspace://SpacesStore/b34eece4-1700-4d93-b546-aff1645a00f8
|
SQS Frame Installation for exaust air 20.12.2022, posted by Michael Luedeke on 21 Dec 2022, 07:48    
|
|
2 Dewar gefüllt, posted by Sascha Menzel on 21 Dec 2022, 13:08
|
2 Dewar #25580 & #44229 gefüllt.
Coworkers: S.Menzel, M.Lüdeke |
Extension Module Gewicht ermittelt, posted by Sascha Menzel on 23 Dec 2022, 11:23
|
Das SCS GRD Extension Module-38982 QR49620 mit der Kranwage angekrant um das Gewicht zu ermitteln. 620kg |
MID pump on the exp. hutch roof, posted by Orkidia Bilani on 02 Jan 2023, 09:14
|
On the roof of the MID exp. hutch one of the pumps is making strange loud noises (laut zischen). The display is off, same as the other pump close to that (which is switched off).
Contacted/called Andreas Schmidt, he assumed that, that is not good with the pump, but cannot solve the problem because he is in home office today and directed me to A.Bartmann.
Tried to reach A. Bartmann, without success (for the moment).
-----10:15----: Reached A. Bartmann, problem solved. Er hat die Stickstoffleitung ausgestellt.
|
VAC - Hera clean tent lamellen, posted by Orkidia Bilani on 04 Jan 2023, 14:42
|
Bianca (VAC) wanted some of the Hera clean tent curtains (currently in XHE1) here in campus (in order to make a Gehäuse for the dewars, sie hatte schon mit Lorenz darüber gesprochen).
Went together there and brought 15 pieces here, stored now in the VAC lab.
|
Vacuumpumpe getauscht, posted by Sascha Menzel on 05 Jan 2023, 12:51 
|
N.Rennhack SQS beim Tausch einer defekten Vacuum Pumpe (laute Geräusche) am Teststand unterstützt. |
Dewar gefüllt, posted by Sascha Menzel on 05 Jan 2023, 12:55
|
Dewar #25584 gefüllt. |
HED, posted by Orkidia Bilani on 06 Jan 2023, 10:54 
|
Contacted S. Göde from HED to remove from the hall the wooden pallet with big empty boxes, currently located in front of the MID hutch. He/his colleagues will do so, and also a big wooden empty box (located next to this pallet) belongig to HED will get removed from the hall.
Also, talked to him about the coffee corner in front of the HED hutch, which is untidy and still with rest boiled coffee from the last user run and unwashed cups. He will take care of that quite soon.
|
PC Einschübe, posted by Sascha Menzel on 06 Jan 2023, 12:30 
|
4 PC Einschübe für den Unterbau am Schreibtisch aus Blech geschnitten und gekanntet.
Coworkers: S.Menzel, M.Lüdeke |
Transport zum XHE1, posted by Sascha Menzel on 09 Jan 2023, 11:41
|
Für SQS QR44457 (COMO-Setup) aus dem XHE1 zur XHEXP1 transportiert und am Reinraum abgestellt.
Coworkers: O.Bilani, M.Lüdeke, S.Menzel |
HED: Update entry of 06.01.2023, posted by Orkidia Bilani on 09 Jan 2023, 11:41 
|
-> The pallet with empty Kartonkisten as well as the other one with the big empty wooden box are removed from the hall (carried out by the HED colleagues).
-> The coffee rests and dirty mugs were cleaned up (carreied out by the HED colleagues).
|
Einweisung XHWS, posted by Sascha Menzel on 09 Jan 2023, 11:45
|
Einweisung auf die Gerätschaften/Maschienen wie z.B. Fräse, Drehbank, Standbohrmaschinen usw. von M.Schrage bekommen.
Coworkers: M.Schrage, M.Lüdeke, S.Menzel |
Dewar gefüllt, posted by Sascha Menzel on 09 Jan 2023, 14:52
|
Dewar #44229 gefüllt. |
Einweisung XHWS, posted by Sascha Menzel on 10 Jan 2023, 14:41
|
Restliche Einweisung im XHWS von M.Schrage bekommen. |
Dewar gefüllt, posted by Sascha Menzel on 10 Jan 2023, 14:42
|
TS bat um Unterstützung einen Dewar für S.Göde (HED) zu füllen. |
PC´s montiert, posted by Sascha Menzel on 10 Jan 2023, 14:50  
|
4 PC´s mit den angefertigten Einschüben unter den Schreibtischen der XO/HallCrew Hütte montiert. |
Pulser Komponente gekrant, posted by Sascha Menzel on 11 Jan 2023, 13:17 6x
|
Die Komponenten für den Pulser von der LKW Schleuse in die Halle/XHEXP1 gekrant und den Steiger aus der Halle in die LKW Schleuse gekrant.
Coworkers: S.Arslan, S.Menzel |
Lights in the Experiment Hall, posted by Orkidia Bilani on 11 Jan 2023, 17:53
|
Lights in the experiment hall needed to be exchanged, and in the SA1 and SA2, three of them were not working.
Torsten Schön was informed already last year, and in the RedMine he replied today following:
"The first row, between northern outer wall and SASE3 has been exchanged with the new lights for testing. The new lights are accepted and ordered. Delivery time 6 weeks at least." |