74
|
02 Nov 2022, 14:40 |
Orkidia Bilani | XHEXP | Information | SQS support | Discussed by the end of September with
T.Mullins and D. Rivas, to remove the laser
tables from the exp.hall area, in case they |
|
535
|
24 Jan 2024, 13:37 |
Frank Siyli | XHEXP | Information | SQS support | Nils Rennhack unterstützt.
Leitungssätze im Podest entfernt
und neu verlegt. |
  |
118
|
16 Dec 2022, 11:51 |
Michael Luedeke | General | Information | SQS start installation frame for exhaust | |
 |
1051
|
18 Feb 2025, 10:34 |
Benjamin Wolf | General | Information | SQS Transport | Die Kammer #48500 aus XHE 1 in die Halle
transportiert
|
|
139
|
11 Jan 2023, 17:58 |
Orkidia Bilani | XHEXP | Information | SQS Support: 19-20.01.2023 | SQS
requested the following support from
XHCrew: |
|
409
|
22 Sep 2023, 10:47 |
Orkidia Bilani | XHEXP | Information | SQS Support in XHEXP1 | SQS doesn't have many space left in
their assembly area. Talked/dealed with the
SQS colleagues, and managed to free spaces |
|
573
|
27 Feb 2024, 15:43 |
Orkidia Bilani | XHEXP | Information | SQS Support in XHE1 | Suppoerted SQS in XHE1 with disassembling
parts from the cluster source and transported
these components back to XHEXP1. |
|
381
|
23 Aug 2023, 13:29 |
Sascha Menzel | XHEXP | Information | SQS Support am 22.08.2023 | Bei SASE3 die Seitenwände vom Laserraum
zwischen SASE3 und SASE1 demontiert (geöffnet)
dann zwei Schubladenschränke mit dem |
14x |
456
|
01 Nov 2023, 11:07 |
Orkidia Bilani | XHEXP | Information | SQS Support | Discussed with T.Mazza on Monday, 30.10.2023,
about storing temporarily in XHE1 the wooden
boxes of an equipment they recevied recently. |
 |
480
|
28 Nov 2023, 19:33 |
Orkidia Bilani | XHEXP | Information | SQS Support | Supported SQS with carrying the top small
cabinets and placing them on the bigger ones.
Co-workers: O. Bilani, M. |
|
481
|
29 Nov 2023, 19:46 |
Orkidia Bilani | XHEXP | Information | SQS Support | Brought Back from XHE1 into the Experiment
Hall the "PAM - Chambers".
Co-workers: O. Bilani, H. Heuer |
|
760
|
07 Aug 2024, 21:00 |
Orkidia Bilani | XHEXP | Information | SQS Support | Dismounted a R+K "Gestell" of
SQS. Brought the R+K to the Warehouse.
The wheels are still in the Exp.Hall, |
|
23
|
22 Sep 2022, 19:44 |
Orkidia Bilani | XHEXP | Information | SQS Support | SQS support:
-> Completed the building up
of the vacuum pump and mounted it in the |
    |
24
|
26 Sep 2022, 15:23 |
Sascha Menzel | XHEXP | Information | SQS Support | Granitsteine (wo der
1D XUV spectrometer drauf steht)
mittels Hutch-Kran versetzt. |
|
48
|
04 Oct 2022, 12:30 |
Sascha Menzel | XHEXP | Information | SQS Support | XHCrew hat an das Reinraumzelt in der SQS
Hutch eine Lochwand montiert.
|
 |
171
|
07 Feb 2023, 13:10 |
Sascha Menzel | General | Information | SQS Support | Für N.Rennhack (SQS) zwei Ausschnitte
in einen Schaltschrank mit einer Stichsäge
ausgeschnitten. |
 |
236
|
24 Mar 2023, 15:49 |
Sascha Menzel | General | Information | SQS Support | Im SQS Labor E0.508 am Aufbau für
die Hochdruckpumpen die Kühlwasserleitungen
durch Schläuche ersetzt. |
 |
240
|
25 Mar 2023, 20:23 |
Sascha Menzel | General | Information | SQS Support | Einen Halter zum befestigen von Schnellkupplung
für Kühlwasserschläuche konstruiert
und zusammen gebaut. Den Halter mit den Schnellkupplungen |
   |
262
|
05 Apr 2023, 18:14 |
Orkidia Bilani | XHEXP | Information | SQS Support | Went with Yevheniy and Sergei to XHE1.
They dismount and took some controllers and
cables from the COMO setup. |
|
268
|
18 Apr 2023, 19:02 |
Sascha Menzel | XHEXP | Information | SQS Support | Für SQS eine Kammer mittels Hallenkran
auf ein Gestell gekrant.
|
|