  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 5 of 30  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown Text Attachments
  42   10 Feb 2017, 15:07 Tobias HaasGeneralInformationUpdated Components List Added Diagnostic Screen for SPB and
changed PRIO for DPS - XGM - DPS in XTD9
to high as discussed during the S1R meeting
 Componets-XTD2-9-new.xlsx 
  44   10 Feb 2017, 16:34 Tobias HaasGeneralInformationUpdated Components List   Components-XTD2-9.xlsx 
  50   17 Feb 2017, 12:40 Thomas TschentscherGeneralInformationUpdated Component status listSee the updated component status list for
XTD2 and XTD9 tunnels. As discussed at the
SASE1 readiness mtg this morning. Yellow
 170217_Components-XTD2-9.xlsx 
  39   09 Feb 2017, 13:57 Tobias HaasGeneralInformationUpdate of installation list for tomorrow's S1R Meeting Please check if correct. I mark all
newly done things in yellow!
 Componets-XTD2-9.xlsx 
  88   24 Mar 2017, 15:24 Tobias HaasGeneralInformationUpdate of component priority list after weekly meeting   170324-Tunnel-Components-Priority-list.xlsx 
  54   24 Feb 2017, 16:33 Tobias HaasGeneralInformationUpdate of component list after weekly meeting   240217_Components-XTD2-9.xlsx 
  90   31 Mar 2017, 15:00 Tobias HaasGeneralInformationUpdate of component list after weekly meeting   170331-Tunnel-Components-Priority-list.xlsx 
  67   10 Mar 2017, 11:15 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness Meeting   Components-Priority-list.xlsx 
  70   10 Mar 2017, 12:53 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness MeetingNote that due to a bug in the elog the
name appeared wrongly in my previous message.
In general: Avoid underscores in the file
 170310-Tunnel-Components-Priority-list.xlsx 
  252   19 May 2017, 12:46 Monica ArestéGeneralInformationUpdate of Instrument component priority list






Normal
0
 170519_Instrument_Components-Priority-list.xlsx 
  227   12 May 2017, 12:26 Monica ArestéGeneralInformationUpdate of Instrument component priority list Find attached the Instrument Component
priority list discussed this morning.
Regards,
 170512_Instrument_Components-Priority-list.xlsx 
  9   09 Nov 2016, 15:36 Tobias HaasGeneralInformationUpdate of Component listI have included the status columns provided
by Alessandro and Sandor in the component
list. Please find it in the usual location
 elog.tiff 
  58   03 Mar 2017, 16:40 Tobias HaasGeneralInformationUpdate of Component Priority list after weekly meeting   170303_Components-Priority-list.xlsx 
  37   03 Feb 2017, 08:48 Jan GrünertXTD2InformationUpdate WP74 cabling status (w5)Information posted on behalf of Torben
Falk (WP74 cabling)
W
  
  446   11 Jan 2018, 11:04 Bruno FernandesGeneralInformationUpdate Timing Firmware/Doocs ServerDear all,

an update of the Timing boards
firmware and doocs server is require. This
  
  449   12 Jan 2018, 14:34 Bruno FernandesGeneralInformationUpdate Timing Firmware/Doocs ServerDear all,

with the exception of one board,
all boards in SASE1, SASE3, FXE, SPB and
  
  182   27 Apr 2017, 09:34 Tobias FreyermuthXTD2InformationUpdate MOV loopHi all,
 
in order to integrate the CRL in
  
  101   04 Apr 2017, 18:49 Alessandro SilenziGeneralInformationUPDATE on Temperature sensors for EPS loopHere are the updated values for the temperature
sensors inn the EPS loop.
Now Thermocouples work!
  
  289   12 Jun 2017, 13:21 Monica ArestéGeneralInformationTunnel's schedule updatedLast information is that tomorrow Fire
brigade will come to inspect the tunnels,
therefore all tunnels will
  
  288   12 Jun 2017, 11:17 Monica ArestéGeneralInformationTunnel's schedule






Normal
0
  