Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 19 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Location Severity Subject Text Attachments
  237   16 May 2017, 14:55 Hugo Silva SantosGeneralInformationCAS On-Call Duty Planning (Until 11/06) Dear All,   
  236   16 May 2017, 13:50 NEREA JARDONXTD9InformationMotion loopDear all,
Due to local test needed in Rack
1.18 for the Motion loop, it  will be interrupted
  
  235   15 May 2017, 22:17 Thomas MichelatGeneralInformationOCD CAS Dear all,
The OCD number for tonight (15/05)
for the CAS group is 98053.
  
  234   15 May 2017, 11:32 NEREA JARDONGeneralInformationOCD AE GroupDear all,

The OCD AE numbers for the following
  
  233   15 May 2017, 11:02 Tobias HaasGeneralInformationStatus and plans after 09:00 meeting in BKR Issues observed
by PCT over the weekend (from H. Sinn entry
  
  232   12 May 2017, 15:58 Valerii BondarGeneralInformationCAS OCD from today to MondayDear all,
CAS phone numbers for OCD:
Friday: Alessandro (98054),
  
  231   12 May 2017, 15:37 NEREA JARDONGeneralInformationOCD AE GroupDear all,
The OCD numbers for this weekend
and today will be:
  
  230   12 May 2017, 13:59 Harald SinnGeneralInformationV0 open!V0 is open now!
Janni opened this morning at 11:00
the V0 valve towards the accelerator vacuum.
 IMG_4609.jpg 
  229   12 May 2017, 13:33 Tobias HaasGeneralInformationStatus and plans after SASE1 Readiness MeetingFocus of meeting is on SASE1 Instruments,
Laser and Detectors
SPB (B. Weinhausen)
 AttendanceS1R120517.pdf 
  228   12 May 2017, 13:19 Alessandro SilenziGeneralInformationNew Deployment of Karabo for the SASE1 control machines.

    

       
            
  
  227   12 May 2017, 12:26 Monica ArestéGeneralInformationUpdate of Instrument component priority list Find attached the Instrument Component
priority list discussed this morning.
Regards,
 170512_Instrument_Components-Priority-list.xlsx 
  226   12 May 2017, 09:23 NEREA JARDONXTD9InformationMotion loopDear all,
Due to local test needed in Rack
1.18 for the Motion loop, the loop will be
  
  225   12 May 2017, 08:21 Harald SinnGeneralInformationRestart vacuum loop now We are in the BRK and corrected the
vacuum interlock condition.
We will restart the SA1 vacuum loop
  
  224   11 May 2017, 19:12 Jan GrünertGeneralInformationWP74 OCD contactsPlan of WP74 OCD contacts for May.
Assignments are subject to change.
Initially availability is 10h-18h
 WP74-OCD-5-2017.xlsx 
  223   11 May 2017, 18:26 Harald SinnXTD10InformationXTD10 not open on Monday Dear all, 
contrary to the rumor that I spread
last Tuesday in the PBS meeting, the magnet
  
  222   11 May 2017, 16:41 NEREA JARDONGeneralInformationMotion loopDear all,
I will update the Motion loop to
include the mc2 motors, it will be running
  
  221   11 May 2017, 15:08 Alessandro SilenziGeneralInformationNew Deployment of Karabo for the SASE1 control machines.


   
        
            
  
  220   11 May 2017, 12:43 Alessandro SilenziGeneralInformationNew Deployment of Karabo for the SASE1 control machines.I will ramp down the system and bring it
back up during the lunch break after installing
the 
 download.sh 
  219   10 May 2017, 18:52 Gero FluckeGeneralInformationCAS OCDCAS on call service for the night:
Gero Flucke: 9-8053
 
  
  218   10 May 2017, 13:07 Jan GrünertXTD2Problemkarabo Beckhoff link not reestablished for SASE1 tunnel VAC loop

    

       
            
  