20
|
11 Feb 2025, 01:41 |
Tomas Popelar | SPB | Shift summary | SPB/SFX 7955 Day 4
X-ray delivery
Optical laser delivery
-
420nm used for sample excitation. timed to 1ps with water jet interaction
-
PAM set up for time points <1 ps
-
From 19:15 to 21:15 (100 uJ/cm2 data point) the feedback loops were off resulting in higher intensity fluctuations, resolved at 21:52
Achievements/Observations
-
x-ray beam de-focused to a few um for data taking
-
PP laser aligned and timed
-
PAM calibrated and used with YAG sample surviving 13% transmission
-
power titration at 100ns and fluences 13 mJ/cm2, 25 mJ/cm2, 100 mJ/cm2 and 191 mJ/cm2
-
delays 100 fs and 500 fs
-
good peak distribution at 13% transmission (None / None / None / 3200 CVD)
-
hit rate around 6%
Issues
|
15
|
08 Feb 2025, 00:00 |
Tokushi Sato | SPB | Shift summary | SPB/SFX 7955 Shift 1
**X-ray delivery**
* up to 202 pulses per train (~1.4 mJ pulse energy), 0.5 MHz.
**Optical laser delivery**
* 420nm used for sample excitation. timed to 1ps with water jet interaction
* difficult to find good filter combination for jet illumination laser and pump laser
**Achievements/Observations**
* 10.8 keV - 11.2 keV energy scan
* lysozyme geometry data set
* several runs for sample dark data set (potentially more needed)
* a few runs for 1ps pumped data set (definitely more needed)
**Issues**
* difficult end to shift (nozzle and illumination issues)
* hit rate rather low for timing program (leads to long processing times)
**To do for next shift**
* continue user data set including power titration
* start time delay sequence |
21
|
13 Feb 2025, 07:24 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
up to 352 pulses per train (~1.9 mJ pulse energy)@9.3 keV, 0.5 MHz ans 1.1 MHz. Beamdown for 40 min.
Optical laser delivery
800 nm, less than 20 fs at sample position, no issue
Achievements/Observations
X-ray beam de-focused to a few um for data taking
PP laser aligned and timed
1 hours data collection
Issues
AGIPD gain map was strange, some gain changes was observed without X-ray
Data was not migrated -> DRC was called and informed |
22
|
15 Feb 2025, 06:52 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
up to 202 pulses per train (~1.9 mJ pulse energy)@9.3 keV, 0.5 MHz
Optical laser delivery
800 nm, less than 20 fs at sample position, no issue
Achievements/Observations
X-ray beam de-focused to a few um for data taking
PP laser aligned and timed
runs for -1 ps - 1.5 ps
Very stable jet
Issues
No major issue |
23
|
16 Feb 2025, 06:46 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
up to 202 pulses per train (~1.9 mJ pulse energy)@9.3 keV, 0.5 MHz
Optical laser delivery
800 nm, less than 20 fs at sample position, no issue
Achievements/Observations
X-ray beam de-focused to a few um for data taking
PP laser aligned and timed
runs for -1 ps - 1.5 ps
Very stable jet
Issues
No major issue
|
24
|
17 Feb 2025, 06:57 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
up to 202 pulses per train (~1.9 mJ pulse energy)@9.3 keV, 0.5 MHz
Optical laser delivery
800 nm, less than 20 fs at sample position, no issue
Achievements/Observations
X-ray beam de-focused to a few um for data taking
PP laser aligned and timed
runs for -1 ps - 1.5 ps
Very stable jet
PAM was installed |
29
|
27 Feb 2025, 07:02 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
up to 202/352 pulses per train (~0.8 mJ pulse energy)@13.4 keV, 0.5/1.1 MHz
Optical laser delivery
800 nm, less than 20 fs at sample position, no issue
Achievements/Observations
X-ray beam de-focused to a few um for data taking
PP laser aligned
Fixed target measurement was finished |
30
|
28 Feb 2025, 06:57 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
up to 202/352 pulses per train (~0.8 mJ pulse energy)@13.4 keV, 0.5/1.1 MHz
Optical laser delivery
800 nm, less than 20 fs at sample position, no issue
Achievements/Observations
X-ray beam de-focused to a few um for data taking
PP laser aligned
Data collection for some samples
Issues
No major issue today
|
31
|
01 Mar 2025, 06:56 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
up to 202/352 pulses per train (~0.8 mJ pulse energy)@13.4 keV, 0.5/1.1 MHz
Optical laser delivery
800 nm, less than 20 fs at sample position, no issue
Achievements/Observations
X-ray beam de-focused to a few um for data taking
PP laser aligned
Data collection for some samples
|
33
|
02 Mar 2025, 06:56 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
up to 175 pulses per train (~1 mJ pulse energy)@13.4 keV, 0.5 MHz
Optical laser delivery
800 nm, less than 20 fs at sample position, no issue
Achievements/Observations
X-ray beam de-focused to a few um for data taking
PP laser aligned
Data collection for some samples
Issues
We could use 188 pulses, but last 13 pulses intensity was too weak, not used for measurement
|
34
|
03 Mar 2025, 07:05 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
up to 188 pulses per train (~1 mJ pulse energy)@13.4 keV, 0.5 MHz
Optical laser delivery
800 nm, less than 20 fs at sample position, no issue
Achievements/Observations
X-ray beam de-focused to a few um for data taking
PP laser aligned
Data collection for some samples |
35
|
04 Mar 2025, 07:05 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
up to 188/352 pulses per train (~1 mJ pulse energy)@13.4 keV, 0.5/1.1 MHz
Optical laser delivery
800 nm, less than 20 fs at sample position, no issue
Achievements/Observations
X-ray beam de-focused to a few um for data taking
PP laser aligned
Data collection for some samples |
39
|
27 Mar 2025, 22:57 |
Tokushi Sato | SPB | Shift end | **X-ray delivery:**
* 16 keV, ~upto 1 mJ, 160 pulses
**Optical Laser:**
* None
**Achievements / Observations:**
* Alignement
* Recorded first explosions |
46
|
09 Apr 2025, 22:46 |
Tokushi Sato | SPB | Shift summary | X-ray delivery:
20 keV, ~ 400 uJ, 128 pulses, stable delivery
Optical Laser:
1030 nm, 850 fs, stable delivery
Achievements / Observations:
20 keV beam to sample position and cameras
Rough alignment of optical setup
Issues:
Optical laser from light conversion had issue with shutter control |
47
|
10 Apr 2025, 23:17 |
Tokushi Sato | SPB | Shift summary | X-ray delivery:
20 keV, ~ 400 uJ, 128 pulses, stable delivery
Optical Laser:
1030 nm, 850 fs, stable delivery
Achievements / Observations:
Rough timing alignment of optical laser setup
Took some initial data
Issues:
No major issue to report |
48
|
11 Apr 2025, 23:14 |
Tokushi Sato | SPB | Shift summary | X-ray delivery:
20 keV, ~ 400 uJ, 246 pulses, stable delivery
Optical Laser:
1030 nm, 850 fs, stable delivery
Achievements / Observations:
Spatial and temporal alignment of optical laser setup
Data collection |
49
|
12 Apr 2025, 23:15 |
Tokushi Sato | SPB | Shift summary | X-ray delivery:
20 keV, ~ 500 uJ, 246 pulses, stable delivery
Optical Laser:
1030 nm, 850 fs, stable delivery
Achievements / Observations:
Lots of data collection
Issues:
Shimadzu camera for Schlieren imaging had issue with shutter, mechanically broken. |
50
|
13 Apr 2025, 22:55 |
Tokushi Sato | SPB | Shift summary | Staff: PV, TS, JK, FK, + users
X-ray delivery:
20 keV, ~ 300-400 uJ, 250 pulses, stable delivery
Optical Laser:
1030 nm, 850 fs, stable delivery
Achievements / Observations:
Lots of data collection
Issues:
No major issue today |
52
|
14 Apr 2025, 23:08 |
Tokushi Sato | SPB | Shift summary | X-ray delivery:
20 keV, 250-400 uJ, 250 pulses, stable delivery
Optical Laser:
1030 nm, 850 fs, stable delivery
Achievements / Observations:
Lots of data collection
Issues:
No major issue today |
56
|
25 Apr 2025, 06:48 |
Tokushi Sato | SPB | Shift summary | X-ray delivery:
10 keV, ~ 850 uJ, 128 pulses, tuning was needed for 1 hour
Optical Laser:
No PP-laser for this week
Achievements / Observations:
Finalized alignment of crystals
Issues:
No major issue today. |
|