Group Selection Page
HELP
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
EEE
WP78
FXE
SPB
MID
HED
SQS
SXP
Sample Environment
Operation
PSPO
XO
TS
Migrated2Zulip
OPERATION-2025
OPERATION-2024
OPERATION-2023
OPERATION-2022
OPERATION-2021
OPERATION-2020
OPERATION-2019
SASE1-2018
SASE1-2017
Experiment data
OPERATION-2025 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn
Not logged in
List
|
Message ID:
76
Entry time:
30 May 2025, 07:16
Author:
Yoonhee Kim
Group:
SPB
Subject:
Shift summary
X-ray delivery
9.3 keV, 2000 uJ pulse energy. Beam was unstable at the beginning.
Optical laser delivery
ns laser for particle illumination inside the chamber,
another ns laser to visualize the tip of capillary on top of the chamber
Achievements/Observations
Measured GV for ~ 2 hours
Issues
PSI from the first reservoir was leaking
Concentration of PSI seems low (judged by seeing camera for liquid jet delivery).
We could not see any diffraction from PSI by both AGIPD preview and OnDA (same setting with GV used)
Instrument status
AGIPD HV off.
AGIPD gate valve closed and pinned.
Attenuators set to thickest diamond.
Vacuum valves closed.
AGIPD breaks enguaged
ns Lasers off
ELOG V3.1.4-7c3fd00