R+K Regal demontiert, posted by Sascha Menzel on 15 Nov 2022, 14:58
|
R+K Regal zwecks Änderung demontiert.
Coworkers: S.Menzel |
Planungsgespraech Beleuchtung XHCrew Gitter, posted by Sascha Menzel on 15 Nov 2022, 15:13
|
Mit O.Engelmann (TS) um 14:00 Uhr an der XHCrew Hütte getroffen und über die Installation der Beleuchtung und Steckdosen im Gitter gesprochen. Es werden 4 Leuchten und eine Steckdosenleiste am 24.11 von IMD installiert
Coworkers: O.Bilani, M.Lüdeke, S.Menzel, O.Engelmann |
Transport from XHEXP1 to XHE1 and back: 17.11.2022, posted by Orkidia Bilani on 16 Nov 2022, 10:02
|
SPB/SFX: Transport of a big optical table from the exp.hall to XHE1. Alreaday craned from XHCrew and S.Arslan and is now in the LKW Schleuse.
HiBEF: J. Hauser wants a component back in the exp.hall. (Will come back today with other parts to be stored in the XHE1, needs support with XIM). The other components would be transported in another day to XHE1).
|
Transport von SCS Teilen, posted by Sascha Menzel on 16 Nov 2022, 10:49
|
Die Teile für den Reinraum der in der SCS Hutch gebaut werden soll von XHPSC in die LKW Schleuse transportiert und von dort aus in die Halle gekrant. Die Teile befinden sich jetzt im SCS Bereich in der Halle.
Coworkers: S.Menzel, M.Lüdeke, O.Bilani, S.Arslan |
SCS Kammer verschieben, posted by Michael Luedeke on 17 Nov 2022, 14:30
|
17.11.2022: Email von Jan Torben - SCS Kammer verschieben. Wurde heute Morgen erledigt. |
SXP Support, posted by Sascha Menzel on 17 Nov 2022, 17:21
|
Am 15.11 hat S.Arslan in der SXP Hutch das Mikroskop auf dem frame mittels Kran angehoben und es für einen Strahlversuch angeschlagen gelassen. Heute 17.11 hat die XHCrew mittels Kran das Mikroskop wieder in vorherige Position gebracht und befestigt. Anschläge demontiert und verräumt.
Coworkers: S.Menzel, M.Lüdeke, V.Vardanyan |
SCS Support, posted by Orkidia Bilani on 24 Nov 2022, 10:38
|
A zoom discussion with A. Reich from SCS.
SCS needs the support of the XHCrew starting from monday afternoon next week, in craning in their hutch the plates for the cleanroom. Also in building up the clean room in their hutch, our support is asked.
Further detIails will be discussed on monday in person. |
Pulserraum: HiBEF, posted by Orkidia Bilani on 28 Nov 2022, 11:38
|
C.Bähtz needs a temporary space in the hall, to place the materials (5 palltes and a 4m long frame) which be used during the buildiing up of the Pulserraum.
Delivery expected latest in January 2023.
Since no space is given without making space, he together with J.Hauser will sort out and remove from the hall parts and materials which are no longer needed there. :-)
|
TS, posted by Orkidia Bilani on 29 Nov 2022, 08:06
|
TS (A.Kondraschew, D. Tscherwitschka) contacted for temporarily space in the hall.
They need to place the materials which will be used during the maintanance period. Currently these are located near and under the stairs of the XHVrew Hutch. |
XHCrew Hutch, posted by Orkidia Bilani on 07 Dec 2022, 11:07
|
Under the XHallCrew office lights have been installed and are functional. |
HiBEF, posted by Orkidia Bilani on 07 Dec 2022, 11:09
|
HiBEF colleauges (mainly J.Hauser) are cleaning up the spaces from the materials which no longer are needed in the hall.
They are preparing a 1-2 pallets with waste.
Many components will be stored in the shaft building XHE1 (will support them wth Redmine Ticket and QR codes).
Meanwhile the "Montagehilfe für Cryofan" QR 47620 has been used and can be brought back to XHE1.
|
SCS: Transport (XHE1, XHEXP1), posted by Orkidia Bilani on 07 Dec 2022, 11:16
|
Until the end of the year SCS needs back from XHE1 to XHEXP1 the components (QR 44265, QR 49608, QR 49609 and QR 49620).
Further, other components will be stored in the XHE1. Details will follow by next week.
|
SQS, posted by Orkidia Bilani on 07 Dec 2022, 14:07
|
Together with T.Mazza checked the COMO source, which is located in XHE1.
This will be brought back in January in XHEXP1, details will follow in due time.
|
SCS Rack Room, posted by Orkidia Bilani on 08 Dec 2022, 08:32
|
The door of the SCS Rack Room can't open, even when activation with the DACHS card shows a green light. It seems to be stucked.
S.Arslan informed via Redmine Ticket. |
SCS Rack Room, posted by Orkidia Bilani on 08 Dec 2022, 13:12
|
The door of the SCS rack room is functional again.
The cause of the SCS rack room door jamming was a piece of cardboard that was inserted into the door latch opening by a person. That has been removed and the door is working again. |
HiBEF: Waste, posted by Orkidia Bilani on 09 Dec 2022, 09:44
|
A pallet with waste from HiBEF was removed from the hall and disposed.
|
HiBEF Rack , posted by Orkidia Bilani on 09 Dec 2022, 09:46
|
A rack to give away from HiBEF has found a new owner , the SQS (N.Rennhack).
|
SQS, posted by Orkidia Bilani on 09 Dec 2022, 11:54 
|
Contacted SQS (N.Rennhack) and suggested solution for three chemical kanisters "Thermal G for Julabo" located at the entrance of their hutch.
They have been removed from there, and are now located in the chemicals' storage.
Coworkers: V. Bazhenov, O. Bilani
|
HiBEF: Bellows and pipes to give away, posted by Orkidia Bilani on 09 Dec 2022, 13:32
|
HiBEF had a Gitterbox with various bellows and pipes to give away.
SQS is now the new owner. :-) Are now stored in SQS labs in the E floor. |
Craning for SXP, posted by Orkidia Bilani on 14 Dec 2022, 07:27
|
V. Vardanyan asked for the XHCrew support in craning in the SXP experiment hutch. Will meet him on 15.12 for further details. |