Dewar gefüllt, posted by Sascha Menzel on 10 Jan 2023, 14:42
|
TS bat um Unterstützung einen Dewar für S.Göde (HED) zu füllen. |
Einweisung XHWS, posted by Sascha Menzel on 10 Jan 2023, 14:41
|
Restliche Einweisung im XHWS von M.Schrage bekommen. |
Dewar gefüllt, posted by Sascha Menzel on 09 Jan 2023, 14:52
|
Dewar #44229 gefüllt. |
Einweisung XHWS, posted by Sascha Menzel on 09 Jan 2023, 11:45
|
Einweisung auf die Gerätschaften/Maschienen wie z.B. Fräse, Drehbank, Standbohrmaschinen usw. von M.Schrage bekommen.
Coworkers: M.Schrage, M.Lüdeke, S.Menzel |
HED: Update entry of 06.01.2023, posted by Orkidia Bilani on 09 Jan 2023, 11:41 
|
-> The pallet with empty Kartonkisten as well as the other one with the big empty wooden box are removed from the hall (carried out by the HED colleagues).
-> The coffee rests and dirty mugs were cleaned up (carreied out by the HED colleagues).
|
Transport zum XHE1, posted by Sascha Menzel on 09 Jan 2023, 11:41
|
Für SQS QR44457 (COMO-Setup) aus dem XHE1 zur XHEXP1 transportiert und am Reinraum abgestellt.
Coworkers: O.Bilani, M.Lüdeke, S.Menzel |
PC Einschübe, posted by Sascha Menzel on 06 Jan 2023, 12:30 
|
4 PC Einschübe für den Unterbau am Schreibtisch aus Blech geschnitten und gekanntet.
Coworkers: S.Menzel, M.Lüdeke |
HED, posted by Orkidia Bilani on 06 Jan 2023, 10:54 
|
Contacted S. Göde from HED to remove from the hall the wooden pallet with big empty boxes, currently located in front of the MID hutch. He/his colleagues will do so, and also a big wooden empty box (located next to this pallet) belongig to HED will get removed from the hall.
Also, talked to him about the coffee corner in front of the HED hutch, which is untidy and still with rest boiled coffee from the last user run and unwashed cups. He will take care of that quite soon.
|
Dewar gefüllt, posted by Sascha Menzel on 05 Jan 2023, 12:55
|
Dewar #25584 gefüllt. |
Vacuumpumpe getauscht, posted by Sascha Menzel on 05 Jan 2023, 12:51 
|
N.Rennhack SQS beim Tausch einer defekten Vacuum Pumpe (laute Geräusche) am Teststand unterstützt. |
VAC - Hera clean tent lamellen, posted by Orkidia Bilani on 04 Jan 2023, 14:42
|
Bianca (VAC) wanted some of the Hera clean tent curtains (currently in XHE1) here in campus (in order to make a Gehäuse for the dewars, sie hatte schon mit Lorenz darüber gesprochen).
Went together there and brought 15 pieces here, stored now in the VAC lab.
|
MID pump on the exp. hutch roof, posted by Orkidia Bilani on 02 Jan 2023, 09:14
|
On the roof of the MID exp. hutch one of the pumps is making strange loud noises (laut zischen). The display is off, same as the other pump close to that (which is switched off).
Contacted/called Andreas Schmidt, he assumed that, that is not good with the pump, but cannot solve the problem because he is in home office today and directed me to A.Bartmann.
Tried to reach A. Bartmann, without success (for the moment).
-----10:15----: Reached A. Bartmann, problem solved. Er hat die Stickstoffleitung ausgestellt.
|
Extension Module Gewicht ermittelt, posted by Sascha Menzel on 23 Dec 2022, 11:23
|
Das SCS GRD Extension Module-38982 QR49620 mit der Kranwage angekrant um das Gewicht zu ermitteln. 620kg |
2 Dewar gefüllt, posted by Sascha Menzel on 21 Dec 2022, 13:08
|
2 Dewar #25580 & #44229 gefüllt.
Coworkers: S.Menzel, M.Lüdeke |
SQS Frame Installation for exaust air 20.12.2022, posted by Michael Luedeke on 21 Dec 2022, 07:48    
|
|
Update: Stored parts in XHE1, posted by Orkidia Bilani on 19 Dec 2022, 12:42
|
The documentation for the storeed parts in the shaft building XHE1 has been updated and uploaded to Alfresco (see link below):
https://docs.xfel.eu/share/page/site/x-ray-operations/document-details?nodeRef=workspace://SpacesStore/b34eece4-1700-4d93-b546-aff1645a00f8
|
SQS start installation frame for exhaust, posted by Michael Luedeke on 16 Dec 2022, 11:51 
|
|
Kranen und Transport zum XHE1, posted by Sascha Menzel on 14 Dec 2022, 14:30 6x
|
SCS Parts in der Hutch auf Paletten und Gitterbox gekrant, verzurrt und für den Transport zum XHE1 in die LKW Schleuse gebracht. SCS Parts und Palette von SPB/SFX nach Osdorf XHE1 transportiert.
Die Palette von SPB/SFX mit Hilfe von S.Arslan im XHE1 vom Anhänger gekrant.
SCS, SPB/SFX Parts eingelagert.
Coworkers: S.Menzel, M.Lüdeke, O.Bilani, S.Arslan
|
Craning for SXP, posted by Orkidia Bilani on 14 Dec 2022, 07:27
|
V. Vardanyan asked for the XHCrew support in craning in the SXP experiment hutch. Will meet him on 15.12 for further details. |
Transport XHE1->XHEXP1, posted by Sascha Menzel on 13 Dec 2022, 16:49 8x
|
HiBEF Parts QR50374, QR50375, QR50373 und QR50372 zum XHE1 transportiert und eingelagert.
Vom XHE1 SCS Parts QR44265, QR49608, QR49609 und QR49620 zur XHEXP1 transportiert und in die SCS Assembly Area gestellt.
Coworkers: S.Menzel, M.Lüdeke, H.Heuer |