ID |
Date |
Author |
Location |
Severity |
Subject |
54
|
05 Oct 2022, 10:45 |
Orkidia Bilani | XHEXP | Information | Transport to XHE1: postponed for tomorrow |
Unfortunately it did not succeed, because the elevator in XHE1 is out of service.
Technische Notdienst was there, but could not solve the problem. A technician from "Lutz Aufzüge" will look it up tomorrow.
The Anhänger with the components is in XHE1, the transporter is loaded and ready for the transport tomorrow.
Coworkers: O. Bilani, S. Menzel, M.Lüdeke, and the care takers frrom TS.
|
53
|
04 Oct 2022, 15:44 |
Sascha Menzel | XHEXP | Information | SCS Support |
Das Reinraumzelt auf dem Balkon aufgestellt und Profile montiert.
Coworkers: C.Broers, M.Lüdeke, S.Menzel |
Attachment 1: IMG_6934.jpg
|
|
52
|
04 Oct 2022, 15:39 |
Sascha Menzel | XHEXP | Information | SCS Support |
Einen Metallschrank auf den Balkon von SCS transportiert, S.Arslan half mit dem Gabelstapler den Schrank auf die Brüstung zu heben.
Coworkers: S.Arslan, M.Lüdeke, S.Menzel |
Attachment 1: IMG_6933.jpg
|
|
51
|
04 Oct 2022, 14:29 |
Orkidia Bilani | XHEXP | Information | Manual red Crane |
The manual red crane (from HiBEF) was tested and it WORKS!
Nevertheless an external specialist will take care for the Inbetriebnahme/Zulassung very soon (S.Arslan will contact him).
Instruments (FXE, HiBEF, HED) happy about it |
Attachment 1: Manual_Crane.jpg
|
|
50
|
04 Oct 2022, 13:15 |
Orkidia Bilani | XHEXP | Information | Transport to XHE1: Preparation |
We prepared and brought the components, which will be transported to XHE1, into the LKW-Schleuse.
The transport will be carried out tomorrow, 05.10.2022, very early in the morning.
Coworkers: O.Bilani, S. Menzel, M. Lüdeke |
Attachment 1: Transport_Vorbereitung_1.jpg
|
|
Attachment 2: Transport_Vorbereitung_2.jpg
|
|
49
|
04 Oct 2022, 12:34 |
Sascha Menzel | XHEXP | Information | R+K Regal fuer SQS fertiggestellt |
Die letzte Aluplatte an das R+K Regal für SQS montiert und somit fertiggestellt.
Coworkers: M.Lüdeke, S.Menzel |
48
|
04 Oct 2022, 12:30 |
Sascha Menzel | XHEXP | Information | SQS Support |
XHCrew hat an das Reinraumzelt in der SQS Hutch eine Lochwand montiert.
Coworkers: M.Lüdeke, S.Menzel |
Attachment 1: IMG_6928.jpg
|
|
Attachment 2: IMG_6929.jpg
|
|
47
|
04 Oct 2022, 12:23 |
Sascha Menzel | XHEXP | Information | SXP Support |
XHCrew hat diverse Komponenten an das Momentum Mikroskop Gestell montiert.
Coworkers: M.Lüdeke, S.Menzel |
Attachment 1: IMG_6925.jpg
|
|
Attachment 2: IMG_6926.jpg
|
|
Attachment 3: IMG_6927.jpg
|
|
46
|
04 Oct 2022, 08:51 |
Orkidia Bilani | XHEXP | Information | SA1: Luftbefeuchter |
Der Luftbefeuchter auf dem Balkon (SA1) hat (akustisches) Alarm gezeigt (seit mind. gestern) .
Die Hebeanlage war kapputt. TS informiert und das Problem behoben/die Hebeanlage wieder repariert. |
Attachment 1: Image20221004091403.jpg
|
|
45
|
30 Sep 2022, 14:29 |
Sascha Menzel | XHEXP | Information | SPB/SFX Support |
N.Reimers bat die XH Crew um unterstützung, Im Gasschrank wurde eine Stickstoffflasche durch eine Heliumflasche ersetzt. P.Schmidt gab die Heliumflasche heraus und Stickstoffflasche wurde im Gaslager eingelagert.
Coworkers: N.Reimers, P.Schmidt, S.Menzel |
44
|
30 Sep 2022, 11:43 |
Sascha Menzel | General | Information | TS Support |
P.Schmidt bat um unterstützung, 1 Dewar mit flüssigen Stickstoff für H.Huijong gefüllt.
Coworkers: S.Menzel |
43
|
30 Sep 2022, 11:33 |
Sascha Menzel | XHEXP | Information | Zylinder tausch Mobiler Kran |
Hall Crew hat den Hubzylinder vom mobilen Kran durch einen neuen Zylinder ersetzt.
Der Ersatzzylinder wurde von J.Hauser zur Verfügung gestellt (er hatte einen Ersatzteil bestellt).
Coworkers: M.Lüdeke, S.Menzel |
Attachment 1: IMG_6917.jpg
|
|
41
|
30 Sep 2022, 10:52 |
Orkidia Bilani | XHEXP | Information | HiBEF: Sorting out |
HiBEF will start next week sorting out the four Gitterboxes and other things located around/infront of MID hutch:
- J.Hauser will sort out what is waste and what can be stored (long and/or short term storage)
- XHCrew offered support to speed up the action.
Coworkers: J. Hauser, O. Bilani |
40
|
30 Sep 2022, 10:47 |
Orkidia Bilani | XHEXP | Information | SCS: Transport to XHE1 |
SCS have few components to store in XHE1:
QR 44263 (SCS Test Chamber) which was placed by XHCrew inside a wooden box from SCS.
QR 49608 (fast CCD motorized 4DOF-37394) and QR 49609 (Support for mot 5 DOF Detector-37400).
A big Gestell Traverse (QR 49620) in the SCS Hutch craned onto pallets and brought into the LKW Schleuse (pic.3).
This transport will take place on 5.10.2022
Coworkers: S.Menzel, O.Bilani
|
Attachment 1: Image20220930141811.jpg
|
|
Attachment 2: IMG_6918.jpg
|
|
Attachment 3: 30Sept2022.jpg
|
|
39
|
30 Sep 2022, 10:40 |
Orkidia Bilani | XHEXP | Information | XHE1 |
XHCrew went to shaft building and took note of the series numbers of the filter units. There are still 8 pieces left and their functionality is somehow unclear.
Checked the spaces for the next week's transport.
Coworkers: S.Menzel, M.Lüdeke, O.Bilani
|
38
|
29 Sep 2022, 19:25 |
Orkidia Bilani | XHEXP | Information | Joint Cleantent |
Mr. Ch. Grüner from "Spetec" came to discuss about the build up of the joint clean tent in the Exp.Hall.
He proposed not to use R+K profiles, but their own, since the R+K profiles do not provide a good stability of the cleanroom modules.
We have most of the filter units, so we do not neccessary need to buy all of them (save money).
The instruments will inform about the last filter change (actually is a yearly procedure).
The crane position for the SCS part of the clean tent can be changed (we got confirmation from J-T.Delitz).
In case it will be granted to build the cleantent from "Spetec", we agreed to have only one expert from "Spetec" to build it up, instead of four (saving money), since the entire XHCrew (O.Bilani, S.Menzel, M.Lüdeke) will work on it.
The time scale is 2-3 weeks to complete the whole mounting and the Inbetriebnahme.
On 30.09 we will go to XHE1 to see the type of the filter units and give this information further to Mr. Ch.Grüner. |
37
|
29 Sep 2022, 16:25 |
Sascha Menzel | XHEXP | Information | SCS Support |
Hall Crew unterstützt beim Reinraumzelt Aufbau auf dem Balkon.
Coworkers: S.Menzel, C,Broers |
Attachment 1: IMG_6911.jpg
|
|
36
|
29 Sep 2022, 15:52 |
Orkidia Bilani | XHEXP | Problem | Elevator at TH2 |
Nils Rennhack called because the elevator at TH2 has stopped between the floors.
L. Kersting was immediately informed, and he is taking care to solve the problem.
|
35
|
29 Sep 2022, 12:10 |
Sascha Menzel | General | Information | TS Support |
P. Schmidt bat um unterstützung beim Dewars füllen mit flüssigen Stickstoff. 2 Dewars für Vacuum gefüllt.
Coworkers: S.Menzel |
34
|
29 Sep 2022, 10:39 |
Orkidia Bilani | XHEXP | Information | Hall Organization Meeting |
-> FXE: mentioned, as two days ago, that they will need support on 10.10 for craning of the Kappa Goniometer: Hall Crew will try to find the best solution for that and organize a meeting between FXE, HallCrew and S. Arslan.
They asked if we know when can they have He again, but we made it clear that XHCrwe doesn't have any news about that and we are not the point of contact for gases.
-> SXP: support on finishing the building up of the Frame for the Momentum Microscope (Tuesday 4.10.2022). V. Vardanyan was aksed to start mounting early in the morning and HallCrew will join for support at 10:00 am.
needs support on craning a pump (details on what and when exactly will follow).
-> PLA: must/have to drill few holes for the central pressurized air into the pillars (Säule) in the exp.hall. Since they must drill only on mondays (when there is no beam and the measurements do not get disturbed from vibrations) and 3.10 is a holyday, they asked for permission to drill on Tuesday (4.10), but not the entire day.
FXE. HED, SQS and SCS do not see a problem on that. Other Instruments still to be asked.
-> The instruments' representative were informed that from 10.10 - 15.10 only M. Lüdeke is present from XHCrew and the week after, 17.10 - 21.10 no member of XHCrew is there due to vacation/training. O.Bilani will check anyway regularly the emails and will be telefonisch erreichbar in any case and reminded the colleagues to keep the hall free from any chaos, danger and waste.
|