Joint Cleantent, posted by Orkidia Bilani on 29 Sep 2022, 19:25
|
Mr. Ch. Grüner from "Spetec" came to discuss about the build up of the joint clean tent in the Exp.Hall.
He proposed not to use R+K profiles, but their own, since the R+K profiles do not provide a good stability of the cleanroom modules.
We have most of the filter units, so we do not neccessary need to buy all of them (save money). |
SCS Support, posted by Sascha Menzel on 29 Sep 2022, 16:25
|
Hall Crew unterstützt beim Reinraumzelt Aufbau auf dem Balkon.
Coworkers: S.Menzel, C,Broers |
Elevator at TH2, posted by Orkidia Bilani on 29 Sep 2022, 15:52
|
Nils Rennhack called because the elevator at TH2 has stopped between the floors.
L. Kersting was immediately informed, and he is taking care to solve the problem.
|
TS Support, posted by Sascha Menzel on 29 Sep 2022, 12:10
|
P. Schmidt bat um unterstützung beim Dewars füllen mit flüssigen Stickstoff. 2 Dewars für Vacuum gefüllt.
Coworkers: S.Menzel |
Hall Organization Meeting, posted by Orkidia Bilani on 29 Sep 2022, 10:39
|
-> FXE: mentioned, as two days ago, that they will need support on 10.10 for craning of the Kappa Goniometer: Hall Crew will try to find the
best solution for that and organize a meeting between FXE, HallCrew and S. Arslan.
They asked if we know when can they have He again, but we made |
SCS Support, posted by Sascha Menzel on 28 Sep 2022, 18:54
|
Transport von R+K Lieferung (diverse Profile) aus dem Warehouse in die Halle (XHEXP1 Balkon) und Paletten / Verpackung entsorgt.
Coworkers: M.Lüdeke, C.Broers |
R+K Regal fuer SQS weiter komplettiert, posted by Sascha Menzel on 28 Sep 2022, 18:52
|
Seitenteil und Deckel für das R+K Regal (SQS) montiert.
Coworkers: M.Lüdeke, S.Menzel |
Regal fuer die Hall Crew Huette fertig gestellt, posted by Sascha Menzel on 28 Sep 2022, 18:48
|
Rückwand vom Regal für die Hall Crew Hütte befestiegt und das Regal in der Hütte aufgestellt..
Coworkers: S.Menzel, M.Lüdeke |
SQS: Support, posted by Orkidia Bilani on 28 Sep 2022, 13:44
|
Yevheniy sent a ticket to XO Transport, as following:
"Hi Hall Crew, |
FXE Support, posted by Orkidia Bilani on 27 Sep 2022, 20:15
|
FXE (P.Frankenberger, M.Knoll) needs our support on craning Kappa Goniometer (ca.180kg) and attaching it into the beamline. Since the space is
quite limited, one would need a special crane (the manual one that HiBEF has left to HallCrew to be used by all instruments when needed, which unfortunately,
due to a leak problem, is out of service; the talk between S.Arslan and T. Toncian is still pending). |
SQS: Transport to XHE1, posted by Orkidia Bilani on 27 Sep 2022, 17:32
|
SQS asks for support to transport from Experimental Hall to XHE1 the following components:
-> Cluster source with QR44455 |
2 Dewars gefuellt, posted by Sascha Menzel on 27 Sep 2022, 16:46
|
Am 26.09.2022 um 09:00 Uhr -> (TS Peter Schmidt bat um Unterstützung) 2 Dewars mit Flüssigstickstoff für Vasilii gefüllt.
Coworkers: S.Menzel |
Regal für Hall Crew Huette angepasst, posted by Sascha Menzel on 27 Sep 2022, 16:37
|
Ein Holzregal was in die Hall Crew Hütte soll, mittels einer Stichsäge ausgesägt damit es wegen dem Kabelkanal ganz an die Wand passt.
Coworkers: S.Menzel, M.Lüdeke |
Aluminiumplatten für das SQS Regal montiert, posted by Sascha Menzel on 27 Sep 2022, 16:33
|
Aluminiumplatten an das R+K Regal für SQS montiert.
Coworkers: S.Menzel, M.Lüdeke |
SQS Support, posted by Sascha Menzel on 26 Sep 2022, 15:23
|
Granitsteine (wo der 1D XUV spectrometer drauf steht) mittels Hutch-Kran versetzt.
Coworkers: Th.Baumann, O.Bilani, M.Lüdeke, S.Menzel |
SQS Support, posted by Orkidia Bilani on 22 Sep 2022, 19:44
|
SQS support:
-> Completed the building up of the vacuum pump and mounted it in the beamline (pic.a and b).
-> Craned and mounted (attached) the 1D XUV spectrometer (from Uppsala) into the beamline (pic.c and d). |
Hall Crew Techniker Fortbildung Fraesen , posted by Sascha Menzel on 22 Sep 2022, 17:14 11x
|
Vom 19.09.2022 bis 23.09.2022
Hall Crew Techniker zur Fortbildung (Fräsen) beim bfw (Berufsfortbildungswerk) siehe Bilder und Video.
Coworkers: S.Menzel, M.Lüdeke |
SQS support, posted by Orkidia Bilani on 21 Sep 2022, 15:47
|
SQS supported on building up and preparing for mounting the vacuum pump (see pic below).
Work on going...
Coworkers: O,Bilani, J. Montano |
Gas cabinets: TüV, posted by Orkidia Bilani on 20 Sep 2022, 14:52
|
Tobias Bartsch wird bis ende nächste Woche die Gasschränke in SA1 and SA3 prüfen (die TüVs sind fällig). |
SQS support, posted by Orkidia Bilani on 19 Sep 2022, 15:26
|
Support of the SQS with:
- dismounting of coils in the big coils' frame
- Tischfuss: brought into the workshop (M. Schrage) two times (gefräst 0.2mm and then again 0.1mm more) |