ID |
Date |
Author |
Location |
Severity |
Subject |
24
|
26 Sep 2022, 15:23 |
Sascha Menzel | XHEXP | Information | SQS Support |
Granitsteine (wo der 1D XUV spectrometer drauf steht) mittels Hutch-Kran versetzt.
Coworkers: Th.Baumann, O.Bilani, M.Lüdeke, S.Menzel |
23
|
22 Sep 2022, 19:44 |
Orkidia Bilani | XHEXP | Information | SQS Support |
SQS support:
-> Completed the building up of the vacuum pump and mounted it in the beamline (pic.a and b).
-> Craned and mounted (attached) the 1D XUV spectrometer (from Uppsala) into the beamline (pic.c and d).
Coworkers: O,Bilani, Th. Baumann, J. Montano
|
22
|
22 Sep 2022, 17:14 |
Sascha Menzel | General | Information | Hall Crew Techniker Fortbildung Fraesen |
Vom 19.09.2022 bis 23.09.2022
Hall Crew Techniker zur Fortbildung (Fräsen) beim bfw (Berufsfortbildungswerk) siehe Bilder und Video.
Coworkers: S.Menzel, M.Lüdeke |
21
|
21 Sep 2022, 15:47 |
Orkidia Bilani | XHEXP | Information | SQS support |
SQS supported on building up and preparing for mounting the vacuum pump (see pic below).
Work on going...
Coworkers: O,Bilani, J. Montano |
20
|
20 Sep 2022, 14:52 |
Orkidia Bilani | XHEXP | Information | Gas cabinets: TüV |
Tobias Bartsch wird bis ende nächste Woche die Gasschränke in SA1 and SA3 prüfen (die TüVs sind fällig). |
19
|
19 Sep 2022, 15:26 |
Orkidia Bilani | XHEXP | Information | SQS support |
Support of the SQS with:
- dismounting of coils in the big coils' frame
- Tischfuss: brought into the workshop (M. Schrage) two times (gefräst 0.2mm and then again 0.1mm more)
- AQS chamber, dismounted, craned and mounted/attached to another chamber
- Tomorrow more...
Coworkers: T. Baumann, J. Montano, A. de Fanis, O. Bilani |
18
|
16 Sep 2022, 17:41 |
Sascha Menzel | General | Information | Transport zum XHE1 |
13:00 -> Die für den Transport vorbereitete Box mit HED Part aus der LKW Scheuse zum XHE1 gebracht und eingelagert.
Coworkers: S.Menzel, M.Lüdeke |
16
|
16 Sep 2022, 15:50 |
Sascha Menzel | XHEXP | Information | SCS bei Vacuum Problem unterstuezt |
SCS bat um Unterstüzung beim beheben einer defekten Vacuum-Leitung. Der Anschluß war defekt (Leitung abgerissen), die Hall Crew hat einen neuen Anschluß aus dem Vacuum-Lab. besorgt und die Leitung instand gesetzt und wieder angeschlossen.
Mitarbeiter: S.Menzel, M.Lüdeke, J.T.Delitz |
15
|
16 Sep 2022, 11:27 |
Sascha Menzel | XHEXP | Information | Messpunkte am Hallenboden überklebt. |
Die Messpunkte am Hallenboden dür den Transport von Kammern mit Luftkissen (Newport) gereinigt und neu überklebt.
Coworkers: M.Lüdeke, S.Menzel |
14
|
16 Sep 2022, 11:13 |
Sascha Menzel | XHEXP | Information | Bei MID Area Platz fuer Vaccum geschaffen |
Nach Absprache von Orkidia Bilani mit Andreas Schmidt, wurde Platz für die neuen Stellplätze der Pumpen (Vacuum) durch aufrücken geschaffen.
Coworkers: O.Bilani, M.Lüdeke, S.Menzel |
13
|
15 Sep 2022, 15:42 |
Orkidia Bilani | XHEXP | Information | HED big flange in XHEXP1 |
10:30 -> Discussion between Andreas Schmidt und O.Bilani about a box containing a flange from HED (long term storage).
Decided to store it in XHE1 (QR:44463 )
The Hall Crew will take care about the transport into XHE1 (for the current status, see entry of S.Menzel) |
12
|
15 Sep 2022, 15:35 |
Orkidia Bilani | XHEXP | Information | Pallet of the "MID AGIPD Stainless Steel Cover" |
12:45 -> Meeting Gabriele Ansaldi and O.Bilani about the pallet containing "MID AGIPD Stainless Steel Cover" (QR: 37702) located in the XHEXP1.
Together we decided to bring it in the Warehouse (short term storage) and O.Bilani will provide Gabriele the updated status.
Already brought by Hall Crew in the Warhouse and Stefan Quast updated it in XIM. |
11
|
15 Sep 2022, 14:43 |
Sascha Menzel | XHEXP | Information | Transport zum XHE1 vorbereitet (MID) |
Einen Flansch von MID in einer Kunstoffbox verpackt, mit QR:44463 versehen und für den Transport am 16.09.2022 zum XHE1 in die LKW Schleuse gestellt.
Coworkers: S.Menzel, M.Lüdeke |
10
|
15 Sep 2022, 14:39 |
Sascha Menzel | XHEXP | Information | Transport von XHEXP1 zum Warehouse für MID |
Hall Crew hat diese Holzkiste von MID mit Schrauben verschlossen und von der Halle ins Warehouse gebracht.
Already updated in XIM by Stefan Quast.
Coworkers: O. Bilani, S.Menzel, M.Lüdeke, G. Ansaldi |
9
|
15 Sep 2022, 12:35 |
Sascha Menzel | XHEXP | Information | R+K Regal fuer SQS montiert |
Das zweite R+K Regal für SQS weiter montiert.
Coworkers: S.Menzel, M.Lüdeke |
8
|
15 Sep 2022, 11:32 |
Orkidia Bilani | XHEXP | Information | Hall Organization Meeting |
All instruments present, except for SPB/SFX.
SCS needs the Hall Crew support for today late afternoon and tomorrow.
SQS asked for Hall Crew support for the comming two weeks.
Waste topic from SXP still pending.
A.Schmidt has a vaccum part to store in XHE1, and another box with a component inside can also be stored in XHE1 (for this still to talk with G. Ansaldi).
S.Menzel and M. Lüdeke will be from 19.09-23.09 on a training outside XFEL.
|
7
|
14 Sep 2022, 16:03 |
Sascha Menzel | XHEXP | Information | R+K Regal fuer SQS montiert |
Angefangen fuer SQS das zweite R+K Regal zu montieren.
Coworkers: S.Menzel, M.Lüdeke |
6
|
14 Sep 2022, 15:52 |
Sascha Menzel | XHEXP | Information | SXP unterstuetzt: "Frame of the Momentum Microscope" |
Vom 05.09.2022 - 08.09.2022
Frame of the Momentum Microscope aus R+K Profile für SXP montiert.
Coworkers: S.Menzel, V.Vardanyan |
5
|
14 Sep 2022, 15:07 |
Orkidia Bilani | XHEXP | Information | SQS support |
The cold trap and all the contaminated components (SQS) have being placed in the small washing machine of the vacuum lab.
Coworkers: Hall Crew and Bianca D.
|
4
|
14 Sep 2022, 11:09 |
Orkidia Bilani | XHEXP | Information | Transport of Helmholtz Coils (SQS) to XHE1 |
The two Helmholtz coils have been transported into the shaftbuliding: XHE1.
Coworkers: Orkidia Bilani, Sascha Menzel
|