Entry   TS, posted by Orkidia Bilani on 29 Nov 2022, 08:06 

TS (A.Kondraschew, D. Tscherwitschka) contacted for temporarily space in the hall.

They need to place the materials which will be used during the maintanance period. Currently these are located near and under the stairs of the XHVrew Hutch.

Entry   Pulserraum: HiBEF, posted by Orkidia Bilani on 28 Nov 2022, 11:38 

C.Bähtz needs a temporary space in the hall, to place the materials (5 palltes and a 4m long frame) which be used during the buildiing up of the Pulserraum.

Delivery expected latest in January 2023.

Since no space is given without making space, he together with J.Hauser will sort out and remove from the hall parts and materials which are no longer needed there. :-)

 

 

Entry   SCS Support, posted by Orkidia Bilani on 24 Nov 2022, 10:38 

A zoom discussion with A. Reich from SCS.

SCS needs the support of the XHCrew starting from monday afternoon next week, in craning in their hutch the plates for the cleanroom. Also in building up the clean room in their hutch, our support is asked.

Further detIails will be discussed on monday in person.

Entry   Dewar gefüllt, posted by Sascha Menzel on 18 Nov 2022, 10:40 

Da P.Schmidt (TS) heute nicht vor Ort ist hat die XHCrew für Vacuum zwei Dewar mit flüssigem Stickstoff gefüllt.

Entry   SXP Support, posted by Sascha Menzel on 17 Nov 2022, 17:21 

Am 15.11 hat S.Arslan in der SXP Hutch das Mikroskop auf dem frame mittels Kran angehoben und es für einen Strahlversuch angeschlagen gelassen. Heute 17.11 hat die XHCrew mittels Kran das Mikroskop wieder in vorherige Position gebracht und befestigt. Anschläge demontiert und verräumt.

 

Coworkers: S.Menzel, M.Lüdeke, V.Vardanyan

Entry   TS Support, posted by Sascha Menzel on 17 Nov 2022, 17:18 

TS (P.Schmidt) beim füllen der Dewar QR 25579 , QR 44229 & QR 25584 unterstützt.

 

Coworkers: S.Menzel, P.Schmidt

Entry   Transport von XHE1 zur XHEXP1, posted by Sascha Menzel on 17 Nov 2022, 14:40 IMG_7021.jpgIMG_7022.jpgIMG_7023.jpg

Für HiBEF QR 47620 Montagehilfsmittel für Cryofan 100J aus dem XHE1 zur XHEXP1 transportiert und in deren Area gebracht.

Für SQS ein Rack QR 48494 und zwei Kisten mit Kabel QR 47932 & QR 47938 aus dem XHE1 zur XHEXP1 transportiert und in deren Area gebracht.

 

Coworkers: S.Menzel, M.Lüdeke

Entry   SCS Kammer verschieben, posted by Michael Luedeke on 17 Nov 2022, 14:30 IMG_20221117_092242.jpg

17.11.2022: Email von Jan Torben - SCS Kammer verschieben. Wurde heute Morgen erledigt.

Entry   Transport von SCS Teilen, posted by Sascha Menzel on 16 Nov 2022, 10:49 Image20221116140104.jpg

Die Teile für den Reinraum der in der SCS Hutch gebaut werden soll von XHPSC in die LKW Schleuse transportiert und von dort aus in die Halle gekrant. Die Teile befinden sich jetzt im SCS Bereich in der Halle.

 

Coworkers: S.Menzel, M.Lüdeke, O.Bilani, S.Arslan  

Entry   Transport from XHEXP1 to XHE1 and back: 17.11.2022, posted by Orkidia Bilani on 16 Nov 2022, 10:02 Image20221116140100.jpg

SPB/SFX: Transport of a big optical table from the exp.hall  to XHE1. Alreaday craned from XHCrew and S.Arslan and is now in the LKW Schleuse.

HiBEF: J. Hauser wants a component back in the exp.hall. (Will come back today with other parts to be stored in the XHE1, needs support with XIM). The other components would be transported in another day to XHE1).

 

 

 

Entry   Planungsgespraech Beleuchtung XHCrew Gitter, posted by Sascha Menzel on 15 Nov 2022, 15:13 

Mit O.Engelmann (TS) um 14:00 Uhr an der XHCrew Hütte getroffen und über die Installation der Beleuchtung und Steckdosen im Gitter gesprochen. Es werden 4 Leuchten und eine Steckdosenleiste am 24.11 von IMD installiert

 

Coworkers: O.Bilani, M.Lüdeke, S.Menzel, O.Engelmann

Entry   Planungsgespraech Reinraumzelt SCS Hutch, posted by Sascha Menzel on 15 Nov 2022, 14:59 

Das Reinraumzelt in der SCS Hutch soll (Plan) in KW 47 aufgebaut werden, dazu müssen alle Teile/Materialien zusammengepackt werden. Die XHCrew organisiert den Transport der Teile die in XHPSC liegen in die Halle und unterstüzt S.Arslan dabei. A.Reich & C.Broers besorgen den Rest der in XHWS eingelagert ist. A.Reich wird sich um einen Erlaubnisschein für Heiß- und Schweißarbeiten kümmern.

 

Coworkers: S.Menzel, M.Lüdeke

Entry   R+K Regal demontiert, posted by Sascha Menzel on 15 Nov 2022, 14:58 

R+K Regal zwecks Änderung demontiert.

 

Coworkers: S.Menzel

Entry   SQS: "Igel" Kammer, posted by Orkidia Bilani on 15 Nov 2022, 12:58 

M. Ilchen (with Desy Transport) removed the "Igel" chamber from the exp.hall and brought it to Desy back.

 

 

Entry   SCS Support, posted by Sascha Menzel on 14 Nov 2022, 11:41 

Eine Kammer auf Luftkissen an den mobilen Kompressor angeschlossen und diese in der SCS Hutch verschoben.

 

Coworkers: O.Bilani, S.Menzel

Entry   Verlaengerungskabel fuer Reinigungsmaschine, posted by Sascha Menzel on 14 Nov 2022, 09:53 Image20221114100035.jpgImage20221114104652.jpg

Das Verlängerungskabel zum laden der Reinigungsmaschine ist für die Halle nicht zulässig, da es nicht aus Silikon besteht. Fa. Karo (S.Franke) wurde darüber informiert und die Hall Crew hat ein Silikonkabel organisiert und es gegen das nicht zulässige ausgetauscht.

 

Coworkers: O.Bilani, S.Menzel

Entry   SQS: Transport from XHE1 to XHEXP1, posted by Orkidia Bilani on 11 Nov 2022, 15:19 

Y. Ovcharenko wrote a Redmine Ticket to XO Transport:

The DSSC components: QR 47932,  QR 47938, QR48494 should be brought back to XHEXP1. Already booked the transporter for Thursday 17.11.2022.

Entry   R+K Rahmen von SCS demontiert, posted by Sascha Menzel on 11 Nov 2022, 11:35 Image20221111113654.jpgImage20221111113658.jpgImage20221111113701.jpg

2 R+K Rahmen mit R+K Profilen im SCS Bereich demontiert und die Profile ins XHWS gebracht.

 

Coworkers: O.Bilani, S.Menzel, M.Lüdeke

Entry   Hall Organization Meeting, posted by Orkidia Bilani on 11 Nov 2022, 07:36 

Hall Organization Meeting on 10.11.2022:

- Only SPP/SFX and SCS were present.

- FXE didn't have time, but reported via email.

- SCS, JT.Delitz wanted support with the dismounting of a clean tent frame which was laying in their assembly area; Also support is needed for building up a cleantent in the SCS hutch.

- SPB/SFX, T. Dietze: support on removing a big optical table, which is taking space in their assembly area. A crane and a forklifter are needed, so XHCrew will coordinate this with S.Arslan. Nadja will write to us about details.

 

Entry   2 R+K Regale demontiert , posted by Sascha Menzel on 10 Nov 2022, 14:59 Image20221110150415.jpg

Das alte Laser-Board Regal und ein Regal aus der Hutch von SQS demontiert, die Profile werden im XHWS eingelagert.

 

Coworkers: M.Lüdeke, S.Menzel 