Update: Stored parts in XHE1, posted by Orkidia Bilani on 19 Dec 2022, 12:42
|
The documentation for the storeed parts in the shaft building XHE1 has been updated and uploaded to Alfresco (see link below):
https://docs.xfel.eu/share/page/site/x-ray-operations/document-details?nodeRef=workspace://SpacesStore/b34eece4-1700-4d93-b546-aff1645a00f8
|
SQS start installation frame for exhaust, posted by Michael Luedeke on 16 Dec 2022, 11:51
|
|
Kranen und Transport zum XHE1, posted by Sascha Menzel on 14 Dec 2022, 14:30 6x
|
SCS Parts in der Hutch auf Paletten und Gitterbox gekrant, verzurrt und für den Transport zum XHE1 in die LKW Schleuse gebracht. SCS Parts und Palette von SPB/SFX nach Osdorf XHE1 transportiert.
Die Palette von SPB/SFX mit Hilfe von S.Arslan im XHE1 vom Anhänger gekrant.
SCS, SPB/SFX Parts eingelagert.
Coworkers: S.Menzel, M.Lüdeke, O.Bilani, S.Arslan
|
Craning for SXP, posted by Orkidia Bilani on 14 Dec 2022, 07:27
|
V. Vardanyan asked for the XHCrew support in craning in the SXP experiment hutch. Will meet him on 15.12 for further details. |
Transport XHE1->XHEXP1, posted by Sascha Menzel on 13 Dec 2022, 16:49 8x
|
HiBEF Parts QR50374, QR50375, QR50373 und QR50372 zum XHE1 transportiert und eingelagert.
Vom XHE1 SCS Parts QR44265, QR49608, QR49609 und QR49620 zur XHEXP1 transportiert und in die SCS Assembly Area gestellt.
Coworkers: S.Menzel, M.Lüdeke, H.Heuer |
HiBEF: Bellows and pipes to give away, posted by Orkidia Bilani on 09 Dec 2022, 13:32
|
HiBEF had a Gitterbox with various bellows and pipes to give away.
SQS is now the new owner. :-) Are now stored in SQS labs in the E floor. |
SQS, posted by Orkidia Bilani on 09 Dec 2022, 11:54
|
Contacted SQS (N.Rennhack) and suggested solution for three chemical kanisters "Thermal G for Julabo" located at the entrance of their hutch.
They have been removed from there, and are now located in the chemicals' storage.
Coworkers: V. Bazhenov, O. Bilani
|
HiBEF Rack , posted by Orkidia Bilani on 09 Dec 2022, 09:46
|
A rack to give away from HiBEF has found a new owner , the SQS (N.Rennhack).
|
HiBEF: Waste, posted by Orkidia Bilani on 09 Dec 2022, 09:44
|
A pallet with waste from HiBEF was removed from the hall and disposed.
|
SCS clean tent installation 8.12.2022, posted by Michael Luedeke on 09 Dec 2022, 07:55
|
The big aluminium plate is mounted
The frame of the clean tent is well moving
Some small tasks are missing and will be done next week
|
SCS Rack Room, posted by Orkidia Bilani on 08 Dec 2022, 13:12
|
The door of the SCS rack room is functional again.
The cause of the SCS rack room door jamming was a piece of cardboard that was inserted into the door latch opening by a person. That has been removed and the door is working again. |
SCS Rack Room, posted by Orkidia Bilani on 08 Dec 2022, 08:32
|
The door of the SCS Rack Room can't open, even when activation with the DACHS card shows a green light. It seems to be stucked.
S.Arslan informed via Redmine Ticket. |
SCS clean tent 7.12.2022, posted by Michael Luedeke on 08 Dec 2022, 07:51
|
Preparation top plate part 1 (drilling, cutting, mounting) |
SQS, posted by Orkidia Bilani on 07 Dec 2022, 14:07
|
Together with T.Mazza checked the COMO source, which is located in XHE1.
This will be brought back in January in XHEXP1, details will follow in due time.
|
SCS: Transport (XHE1, XHEXP1), posted by Orkidia Bilani on 07 Dec 2022, 11:16
|
Until the end of the year SCS needs back from XHE1 to XHEXP1 the components (QR 44265, QR 49608, QR 49609 and QR 49620).
Further, other components will be stored in the XHE1. Details will follow by next week.
|
HiBEF, posted by Orkidia Bilani on 07 Dec 2022, 11:09
|
HiBEF colleauges (mainly J.Hauser) are cleaning up the spaces from the materials which no longer are needed in the hall.
They are preparing a 1-2 pallets with waste.
Many components will be stored in the shaft building XHE1 (will support them wth Redmine Ticket and QR codes).
Meanwhile the "Montagehilfe für Cryofan" QR 47620 has been used and can be brought back to XHE1.
|
XHCrew Hutch, posted by Orkidia Bilani on 07 Dec 2022, 11:07
|
Under the XHallCrew office lights have been installed and are functional. |
SCS clean tent installation 6.12.2022, posted by Michael Luedeke on 07 Dec 2022, 08:15 8x
|
Installation C-Profile
Moving Chamber 1
Moving Chamber 2
Material preparation |
SCS Cleantent Day 2 22-11-30, posted by Michael Luedeke on 30 Nov 2022, 14:49
|
|
SCS Installation for Cleantent 22_11_29, posted by Michael Luedeke on 29 Nov 2022, 15:09
|
|