XHE1, posted by Orkidia Bilani on 30 Sep 2022, 10:40
|
XHCrew went to shaft building and took note of the series numbers of the filter units. There are still 8 pieces left and their functionality is somehow
unclear.
Checked the spaces for the next week's transport. |
SCS: Transport to XHE1, posted by Orkidia Bilani on 30 Sep 2022, 10:47  
|
SCS have few components to store in XHE1:
QR 44263 (SCS Test Chamber) which was placed by XHCrew inside a wooden box from SCS.
QR 49608 (fast CCD motorized 4DOF-37394) and QR 49609 (Support for mot 5 DOF Detector-37400). |
HiBEF: Sorting out, posted by Orkidia Bilani on 30 Sep 2022, 10:52
|
HiBEF will start next week sorting out the four Gitterboxes and other things located around/infront of MID hutch:
- J.Hauser will sort out what is waste and what can be stored (long and/or short term storage)
- XHCrew offered support to speed up the action. |
Zylinder tausch Mobiler Kran, posted by Sascha Menzel on 30 Sep 2022, 11:33
|
Hall Crew hat den Hubzylinder vom mobilen Kran durch einen neuen Zylinder ersetzt.
Der Ersatzzylinder wurde von J.Hauser zur Verfügung gestellt (er hatte einen Ersatzteil bestellt).
|
SPB/SFX Support, posted by Sascha Menzel on 30 Sep 2022, 14:29
|
N.Reimers bat die XH Crew um unterstützung, Im Gasschrank wurde eine Stickstoffflasche durch eine Heliumflasche ersetzt. P.Schmidt gab die Heliumflasche
heraus und Stickstoffflasche wurde im Gaslager eingelagert.
|
SA1: Luftbefeuchter, posted by Orkidia Bilani on 04 Oct 2022, 08:51
|
Der Luftbefeuchter auf dem Balkon (SA1) hat (akustisches) Alarm gezeigt (seit mind. gestern) .
Die Hebeanlage war kapputt. TS informiert und das Problem behoben/die Hebeanlage wieder repariert. |
SXP Support, posted by Sascha Menzel on 04 Oct 2022, 12:23  
|
XHCrew hat diverse Komponenten an das Momentum Mikroskop Gestell montiert.
Coworkers: M.Lüdeke, S.Menzel |
SQS Support, posted by Sascha Menzel on 04 Oct 2022, 12:30 
|
XHCrew hat an das Reinraumzelt in der SQS Hutch eine Lochwand montiert.
Coworkers: M.Lüdeke, S.Menzel |
R+K Regal fuer SQS fertiggestellt, posted by Sascha Menzel on 04 Oct 2022, 12:34
|
Die letzte Aluplatte an das R+K Regal für SQS montiert und somit fertiggestellt.
Coworkers: M.Lüdeke, S.Menzel |
Transport to XHE1: Preparation, posted by Orkidia Bilani on 04 Oct 2022, 13:15 
|
We prepared and brought the components, which will be transported to XHE1, into the LKW-Schleuse.
The transport will be carried out tomorrow, 05.10.2022, very early in the morning.
|
Manual red Crane, posted by Orkidia Bilani on 04 Oct 2022, 14:29
|
The manual red crane (from HiBEF) was tested and it WORKS!
Nevertheless an external specialist will take care for the Inbetriebnahme/Zulassung very soon (S.Arslan will contact him).
Instruments (FXE, HiBEF, HED) happy about it |
SCS Support, posted by Sascha Menzel on 04 Oct 2022, 15:39
|
Einen Metallschrank auf den Balkon von SCS transportiert, S.Arslan half mit dem Gabelstapler den Schrank auf die Brüstung zu heben.
Coworkers: S.Arslan, M.Lüdeke, S.Menzel |
SCS Support, posted by Sascha Menzel on 04 Oct 2022, 15:44
|
Das Reinraumzelt auf dem Balkon aufgestellt und Profile montiert.
Coworkers: C.Broers, M.Lüdeke, S.Menzel |
Transport to XHE1: postponed for tomorrow, posted by Orkidia Bilani on 05 Oct 2022, 10:45
|
Unfortunately it did not succeed, because the elevator in XHE1 is out of service.
Technische Notdienst was there, but could not solve the problem. A technician from "Lutz Aufzüge" will look it up tomorrow.
The Anhänger with the components is in XHE1, the transporter is loaded and ready for the transport tomorrow. |
Hall Crew from 10.10 - 23.10.2022, posted by Orkidia Bilani on 07 Oct 2022, 11:04
|
Next week, 10.10 - 14.10.2022 only one Hall Crew member, M.Lüdeke, will be here. S.Menzel will be on vacation.
On 17.10 - 23.10.2022 Hall Crew is not there. M.Lüdeke and S.Menzel will attend a training
O.Bilani will the whole two weeks on vacation, but always verfügbar. |
SCS Support, posted by Sascha Menzel on 25 Oct 2022, 15:10 
|
Zwei Filtereinheiten auf den Balkon gebracht und auf das neue Reinraumzelt siehe Bilder gehoben.
Coworkers: S.Menzel, M.Lüdeke, C.Broers |
Weissklima Technik at SA2, posted by Orkidia Bilani on 27 Oct 2022, 07:54
|
An acustic warning singal was triggered at the Weissklima Technik unit (QR 30755) at SA2- On the display: Nicht dringende Störung.
Acustic signal has been muted, TS will check.
|
SCS Support, posted by Orkidia Bilani on 28 Oct 2022, 10:58
|
Supported J.Schlappa, SCS, with the transport of a big dewar to their exp.hutch. |
SCS Support, posted by Sascha Menzel on 01 Nov 2022, 11:45
|
J.T.Delitz beim Transport von einer flüssig Helium Kanne von der Halle zum Dewar Lager unterstützt.
Coworkers: J.T.Delitz, S.Menzel |
Schwerlastrollen an das R+K Regal für SQS montiert, posted by Sascha Menzel on 02 Nov 2022, 10:03
|
Das R+K Regal angekrant und 4 Schwerlastrollen montiert.
Coworkers: O.Bilani, S.Menzel |