  XHCrew logbook, Page 21 of 69  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Location Severity Subjectdown
  1224   21 May 2025, 10:06 Benjamin WolfXHEXPInformationSXP Support

Einen Halter für die LN 2 Transferleitungen gebaut und montiert. Anschließend die Leitungen daran aufgehängt und fixiert.

 

 

Coworker: S Menzel, B. Wolf

Attachment 1: Image20250521100736.jpg
Image20250521100736.jpg
  1226   22 May 2025, 13:10 Benjamin WolfXHEXPInformationSXP Support

R und K Profile zugeschnitten, Material zusammen gestellt und die Teile vormontiert zur Optimierung des Halters für die Transferleitungen.

 

Coworker: S.Menzel, B.Wolf

  1227   22 May 2025, 19:29 Kai-Erik PfeifferXHEXPInformationSXP Support

Die vorbereiteten Teile in der SXP Hutch montiert.

Attachment 1: Image20250523104225.jpg
Image20250523104225.jpg
  1235   28 May 2025, 12:02 Sascha MenzelXHEXPInformationSXP Support

Die vom J.Moore bestellten Halter an den LN2 Halterahmen montiert.

Attachment 1: Image20250528115542.jpg
Image20250528115542.jpg
  1288   08 Jul 2025, 09:26 Sascha MenzelXHEXPInformationSXP Support

Einen Laser-Tisch in der SXP Exp.Hutch auf Schwerlastrollen mit zwei Hochhubwagen gestellt, zwei R+K Profile vom Reinraum demontiert und alles mit den mobilen Kran gesichert. Den Laser-Tisch an die neue Position verschoben und abgestellt.

Coworkers: K.Pfeiffer, D.Jaacks, B.Wolf, S.Menzel

Attachment 1: Image20250708092249.jpg
Image20250708092249.jpg
Attachment 2: Image20250708092252.jpg
Image20250708092252.jpg
Attachment 3: Image20250708092254.jpg
Image20250708092254.jpg
Attachment 4: Image20250708092257.jpg
Image20250708092257.jpg
Attachment 5: Image20250708092959.jpg
Image20250708092959.jpg
  1311   29 Jul 2025, 14:19 Kai-Erik PfeifferXHEXPInformationSXP Support

An zehn Edelstahlrahmen mit Netzen Löcher gebohrt, je vier Halter mit Griffen montiert und auf die Lasertische in der SXP Hutch gelegt.

 

Coworkers:

D. Jaacks, K. Pfeiffer

Attachment 1: Image20250729142126.jpg
Image20250729142126.jpg
Attachment 2: Image20250729142129.jpg
Image20250729142129.jpg
  1360   09 Sep 2025, 17:05 Sascha MenzelXHEXPInformationSXP Support

Löcher gebohrt und Griffhalter an zwei Laserbord-Deckel angebracht und jeweils zwei Senklöcher an eine von 8 Gleitschienen gebohrt.

Coworkers: K.Pfeiffer, B.Wolf, D.Jaacks und S.Menzel

Attachment 1: Image20250909170413.jpg
Image20250909170413.jpg
Attachment 2: Image20250909170417.jpg
Image20250909170417.jpg
Attachment 3: Image20250909170210.jpg
Image20250909170210.jpg
Attachment 4: Image20250909170408.jpg
Image20250909170408.jpg
  1287   07 Jul 2025, 13:18 Kai-Erik PfeifferXHEXPInformationSXP Monitorhalter

Die andere Seite im SXP Kontrollraum mit Hiltischiene, neuen Monitoren und Haltern aufgerüstet.

 

Coworkers:

D. Jaacks, B. Wolf, K. Pfeiffer

Attachment 1: Image20250707131745_1.jpg
Image20250707131745_1.jpg
Attachment 2: Image20250707131749.jpg
Image20250707131749.jpg
  353   04 Jul 2023, 14:46 Sascha MenzelXHEXPInformationSXP Area aufgeräumt

Die Bodenbeläge ( Pappe & Filz ) aus der SXP Area sowie vom Podest aufgenommen und entsorgt.

Coworkers: O.Bilani, S.Menzel

Attachment 1: Image20230705104700.jpg
Image20230705104700.jpg
  408   22 Sep 2023, 10:45 Orkidia BilaniXHEXPInformationSQS: Transport to XHEXP1

Brought back from XHE1 to the experiment hall following parts for SQS:

QR48494 Rack
QR48493 Rack
QR47932 Kabel
QR47938 Kabel

Coworkers: S. Menzel, O. Bilani

  28   27 Sep 2022, 17:32 Orkidia BilaniXHEXPInformationSQS: Transport to XHE1

SQS asks for support to transport from Experimental Hall to XHE1 the following components:

-> Cluster source  with QR44455
-> The DSSC components: QR 47932,  QR 47938

Yevheniy will clairify, if  the racks with QR 47938 and  QR47932 (part of DSSC), have to be transported to XHE1 or not.

Coworkers: O.Bilani, Y. Ovcharenko

  401   21 Sep 2023, 08:40 Orkidia BilaniXHEXPInformationSQS: Transport to XHE1

Transport of two granite blocks (QR 51494 and QR 514945) of SQS from XHEXP1 to XHE1.

 

Coworkers: S. Menzel, M. Peter, O. Bilani

Attachment 1: QR51494_51495.jpg
QR51494_51495.jpg
  83   11 Nov 2022, 15:19 Orkidia BilaniXHEXPInformationSQS: Transport from XHE1 to XHEXP1

Y. Ovcharenko wrote a Redmine Ticket to XO Transport:

The DSSC components: QR 47932,  QR 47938, QR48494 should be brought back to XHEXP1. Already booked the transporter for Thursday 17.11.2022.

  423   29 Sep 2023, 12:34 Orkidia BilaniXHEXPInformationSQS: Transport

Transport of SQS components:

QR 44455, QR 44458 and QR 49874 from XHEXP1 to XHE1.

QR 45466 from XHE1 back to XHEXP1.

 

Coworkers: O. Bilani, M. Peter, H. Heuer

  30   28 Sep 2022, 13:44 Orkidia BilaniXHEXPInformationSQS: Support

Yevheniy sent a ticket to XO Transport, as following:

"Hi   Hall Crew, 
We would like to transport from experimental hall to XHE1 the following
components:

-> Cluster source  with QR44455 
-> The DSSC components: QR 47932,  QR 47938, QR48494, QR48493

-> The big CF300 VAT valve for the DSSC experiments with QR44459

-> The pnCCD rack with QR5802 "

 

He was supported with the Ticket, QR and the XIM.

The transport will be carried out next week.

(A big laser table can also be stored to XHE1. T.Mullins will let know by latest end of the week.)

Coworkers: Y. Ovcharenko, O. Bilani

 

  614   22 Mar 2024, 13:47 Orkidia BilaniXHEXPInformationSQS: Emergency craning

Craned for SQS the chain of the manual crane. 

This because the REMI needed to be repaired. 

The core of REMI was craned manually by Rebekka, Ares and Sergey.

They will crane it back to the chamber around 4-5 p.m.

 

Attachment 1: IMG_20240322_111619_MP.jpg
IMG_20240322_111619_MP.jpg
  86   15 Nov 2022, 12:58 Orkidia BilaniXHEXPInformationSQS: "Igel" Kammer

M. Ilchen (with Desy Transport) removed the "Igel" chamber from the exp.hall and brought it to Desy back.

 

 

  1216   12 May 2025, 07:05 Benjamin WolfGeneralInformationSQS und SXP Support

Ein Dewar mit Schlauch für SQS befüllt und ein Dewar mit Top Anschluss für SXP befüllt 

  5   14 Sep 2022, 15:07 Orkidia BilaniXHEXPInformationSQS support

The cold trap and all the contaminated components (SQS) have being placed in the small washing machine of the vacuum lab.

Coworkers: Hall Crew and Bianca D.

 

  19   19 Sep 2022, 15:26 Orkidia BilaniXHEXPInformationSQS support

Support of the SQS with:

- dismounting of coils in the big coils' frame

- Tischfuss: brought into the workshop (M. Schrage)  two times  (gefräst 0.2mm and then again 0.1mm more)

- AQS chamber, dismounted, craned and mounted/attached  to another chamber

- Tomorrow more...

 

Coworkers: T. Baumann, J. Montano, A. de Fanis, O. Bilani

Attachment 1: sqs_19Sept2022.jpg
sqs_19Sept2022.jpg