Entry   SQS: Support, posted by Orkidia Bilani on 28 Sep 2022, 13:44 

Yevheniy sent a ticket to XO Transport, as following:

"Hi   Hall Crew, 
We would like to transport from experimental hall to XHE1 the following
components:

-> Cluster source  with QR44455 
-> The DSSC components: QR 47932,  QR 47938, QR48494, QR48493

-> The big CF300 VAT valve for the DSSC experiments with QR44459

-> The pnCCD rack with QR5802 "

 

He was supported with the Ticket, QR and the XIM.

The transport will be carried out next week.

(A big laser table can also be stored to XHE1. T.Mullins will let know by latest end of the week.)

Coworkers: Y. Ovcharenko, O. Bilani

 

Entry   SQS: Emergency craning , posted by Orkidia Bilani on 22 Mar 2024, 13:47 IMG_20240322_111619_MP.jpg

Craned for SQS the chain of the manual crane. 

This because the REMI needed to be repaired. 

The core of REMI was craned manually by Rebekka, Ares and Sergey.

They will crane it back to the chamber around 4-5 p.m.

 

Entry   SQS: "Igel" Kammer, posted by Orkidia Bilani on 15 Nov 2022, 12:58 

M. Ilchen (with Desy Transport) removed the "Igel" chamber from the exp.hall and brought it to Desy back.

 

 

Entry   SQS und SXP Support , posted by Benjamin Wolf on 12 May 2025, 07:05 

Ein Dewar mit Schlauch für SQS befüllt und ein Dewar mit Top Anschluss für SXP befüllt 

Entry   SQS support, posted by Orkidia Bilani on 14 Sep 2022, 15:07 

The cold trap and all the contaminated components (SQS) have being placed in the small washing machine of the vacuum lab.

Coworkers: Hall Crew and Bianca D.

 

Entry   SQS support, posted by Orkidia Bilani on 19 Sep 2022, 15:26 sqs_19Sept2022.jpg

Support of the SQS with:

- dismounting of coils in the big coils' frame

- Tischfuss: brought into the workshop (M. Schrage)  two times  (gefräst 0.2mm and then again 0.1mm more)

- AQS chamber, dismounted, craned and mounted/attached  to another chamber

- Tomorrow more...

 

Coworkers: T. Baumann, J. Montano, A. de Fanis, O. Bilani

Entry   SQS support, posted by Orkidia Bilani on 21 Sep 2022, 15:47 sqs_21Sept2022.jpg

SQS supported on building up and preparing for mounting the vacuum pump (see pic below).

Work on going...

Coworkers: O,Bilani, J. Montano

Entry   SQS support, posted by Orkidia Bilani on 02 Nov 2022, 14:40 

Discussed by the end of September with T.Mullins and D. Rivas, to remove the laser tables from the exp.hall area, in case they won't be needed anymore.

Today we supported SQS in dismountig and removing these tables (1*2 m²) from the exp.hall.

Coworkers: O.Bilani, S. Menzel, D. Rivas, J. Monotano

Entry   SQS support, posted by Frank Siyli on 24 Jan 2024, 13:37 Image20240125060518.jpgImage20240125060521.jpgImage20240125060523.jpg

Nils Rennhack unterstützt.

Leitungssätze im Podest entfernt und neu verlegt.

Coworker: Nils Rennhack, Sascha Menzel, Orkidia Bilani, Frank Siyli

Entry   SQS start installation frame for exhaust, posted by Michael Luedeke on 16 Dec 2022, 11:51 20221216_111621.jpg20221216_111637.jpg
 
Entry   SQS Transport, posted by Benjamin Wolf on 18 Feb 2025, 10:34 Image20250218103653.png

Die Kammer #48500 aus XHE 1 in die Halle transportiert

 

 

coworkers:O. Bilani, K. Pfeiffer, B. Wolf

Entry   SQS Support: 19-20.01.2023, posted by Orkidia Bilani on 11 Jan 2023, 17:58 

SQS requested the following support  from XHCrew:


Thursday and Friday of next week SQS expect to carry on some installation works in their hutch with expected activities:

- To make modifications to an existing frame
- To assemble a new frame
- Support with craning into the hutch of COMO source

 

Entry   SQS Support in XHEXP1, posted by Orkidia Bilani on 22 Sep 2023, 10:47 

SQS doesn't have many space left in their assembly area. Talked/dealed with the SQS colleagues, and managed to free spaces :-).

The parts/components will be transported to XHE1 and to Ütersen.

Sascha will do the transport to XHE1 on his shift over the weekend. The transport to Ütersen will be done next week.

 

Coworkers: O.Bilani, N. Rennhack, J. Montano, A. Igharas, S. Menzel, S. Dold

 

Entry   SQS Support in XHE1, posted by Orkidia Bilani on 27 Feb 2024, 15:43 SQS.png

Suppoerted SQS in XHE1 with disassembling parts from the cluster source and transported these components back to XHEXP1.

Co-workers: Y. Ovcharenko, A. Igharas, O. Bilani

Entry   SQS Support am 22.08.2023, posted by Sascha Menzel on 23 Aug 2023, 13:29 14x

Bei SASE3 die Seitenwände vom Laserraum zwischen SASE3 und SASE1 demontiert (geöffnet) dann zwei Schubladenschränke mit dem Hubwagen weg transportiert. Diverse Leitungen und Kühlwasserschläuche demontiert und die drei Lasertische mittels mobielen Kran aus dem Laserraum gekrant und auf Transportrollen gestellt. Die Lasertische zur SQS Area transportiert und mittels Hallenkran in Holzkisten gekrant. Die Holzkisten hatte zuvor O.Smith in die Halle transportiert. Einen Chiller aus dem Laserraum von der Wasserversorgung getrennt und aus dem Raum transportiert. Zum Schluss die Wandelemente wieder montiert und die Wand somit geschlossen.

Coworkers: S.Menzel, N.Rennhack, D.Raiser, A.Igharas und T.Mullins

Entry   SQS Support , posted by Orkidia Bilani on 01 Nov 2023, 11:07 IMG_20231030_131455_MP.jpgIMG_20231030_131503_MP.jpg

Discussed with T.Mazza on Monday, 30.10.2023, about storing temporarily in XHE1 the wooden boxes of an equipment they recevied recently. 

They should be stored until the equipment is tested and working, so that if something goes wrong, it can be shipped to the manufacturer with the original Verpackung 

If all fine, they will be disposed, most probably by the end of winter maintenance period.

 

Transport was done!

Co-workers: S.Menzel. O.Bilani, J. Montano

Entry   SQS Support , posted by Orkidia Bilani on 28 Nov 2023, 19:33 

Supported SQS with carrying the top small cabinets and placing them on the bigger ones.

Co-workers: O. Bilani,  M. Peter, A. Igharas, J. Montano

Entry   SQS Support , posted by Orkidia Bilani on 29 Nov 2023, 19:46 IMG_20231129_133338_MP.jpg

Brought Back from XHE1 into the Experiment Hall the "PAM - Chambers".

Co-workers: O. Bilani, H. Heuer

 

Entry   SQS Support , posted by Orkidia Bilani on 07 Aug 2024, 21:00 IMG_20240807_203521_HDR.jpg

Dismounted a R+K "Gestell" of SQS. Brought the R+K to the Warehouse. 

The wheels are still in the Exp.Hall, because maybe Sascha and Paul would need them soon.

Entry   SQS Support , posted by Benjamin Wolf on 23 May 2025, 08:48 

Dewar für SQS befüllt 