XHCrew
  XHCrew logbook, Page 19 of 65  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown
  423   29 Sep 2023, 12:34 Orkidia BilaniXHEXPInformationSQS: Transport

Transport of SQS components:

QR 44455, QR 44458 and QR 49874 from XHEXP1 to XHE1.

QR 45466 from XHE1 back to XHEXP1.

 

Coworkers: O. Bilani, M. Peter, H. Heuer

  30   28 Sep 2022, 13:44 Orkidia BilaniXHEXPInformationSQS: Support

Yevheniy sent a ticket to XO Transport, as following:

"Hi   Hall Crew, 
We would like to transport from experimental hall to XHE1 the following
components:

-> Cluster source  with QR44455 
-> The DSSC components: QR 47932,  QR 47938, QR48494, QR48493

-> The big CF300 VAT valve for the DSSC experiments with QR44459

-> The pnCCD rack with QR5802 "

 

He was supported with the Ticket, QR and the XIM.

The transport will be carried out next week.

(A big laser table can also be stored to XHE1. T.Mullins will let know by latest end of the week.)

Coworkers: Y. Ovcharenko, O. Bilani

 

  614   22 Mar 2024, 13:47 Orkidia BilaniXHEXPInformationSQS: Emergency craning

Craned for SQS the chain of the manual crane. 

This because the REMI needed to be repaired. 

The core of REMI was craned manually by Rebekka, Ares and Sergey.

They will crane it back to the chamber around 4-5 p.m.

 

Attachment 1: IMG_20240322_111619_MP.jpg
IMG_20240322_111619_MP.jpg
  86   15 Nov 2022, 12:58 Orkidia BilaniXHEXPInformationSQS: "Igel" Kammer

M. Ilchen (with Desy Transport) removed the "Igel" chamber from the exp.hall and brought it to Desy back.

 

 

  1216   12 May 2025, 07:05 Benjamin WolfGeneralInformationSQS und SXP Support

Ein Dewar mit Schlauch für SQS befüllt und ein Dewar mit Top Anschluss für SXP befüllt 

  5   14 Sep 2022, 15:07 Orkidia BilaniXHEXPInformationSQS support

The cold trap and all the contaminated components (SQS) have being placed in the small washing machine of the vacuum lab.

Coworkers: Hall Crew and Bianca D.

 

  19   19 Sep 2022, 15:26 Orkidia BilaniXHEXPInformationSQS support

Support of the SQS with:

- dismounting of coils in the big coils' frame

- Tischfuss: brought into the workshop (M. Schrage)  two times  (gefräst 0.2mm and then again 0.1mm more)

- AQS chamber, dismounted, craned and mounted/attached  to another chamber

- Tomorrow more...

 

Coworkers: T. Baumann, J. Montano, A. de Fanis, O. Bilani

Attachment 1: sqs_19Sept2022.jpg
sqs_19Sept2022.jpg
  21   21 Sep 2022, 15:47 Orkidia BilaniXHEXPInformationSQS support

SQS supported on building up and preparing for mounting the vacuum pump (see pic below).

Work on going...

Coworkers: O,Bilani, J. Montano

Attachment 1: sqs_21Sept2022.jpg
sqs_21Sept2022.jpg
  74   02 Nov 2022, 14:40 Orkidia BilaniXHEXPInformationSQS support

Discussed by the end of September with T.Mullins and D. Rivas, to remove the laser tables from the exp.hall area, in case they won't be needed anymore.

Today we supported SQS in dismountig and removing these tables (1*2 m²) from the exp.hall.

Coworkers: O.Bilani, S. Menzel, D. Rivas, J. Monotano

  535   24 Jan 2024, 13:37 Frank SiyliXHEXPInformationSQS support

Nils Rennhack unterstützt.

Leitungssätze im Podest entfernt und neu verlegt.

Coworker: Nils Rennhack, Sascha Menzel, Orkidia Bilani, Frank Siyli

Attachment 1: Image20240125060518.jpg
Image20240125060518.jpg
Attachment 2: Image20240125060521.jpg
Image20240125060521.jpg
Attachment 3: Image20240125060523.jpg
Image20240125060523.jpg
  118   16 Dec 2022, 11:51 Michael LuedekeGeneralInformationSQS start installation frame for exhaust
Attachment 1: 20221216_111621.jpg
20221216_111621.jpg
Attachment 2: 20221216_111637.jpg
20221216_111637.jpg
  1051   18 Feb 2025, 10:34 Benjamin WolfGeneralInformationSQS Transport

Die Kammer #48500 aus XHE 1 in die Halle transportiert

 

 

coworkers:O. Bilani, K. Pfeiffer, B. Wolf

Attachment 1: Image20250218103653.png
Image20250218103653.png
  139   11 Jan 2023, 17:58 Orkidia BilaniXHEXPInformationSQS Support: 19-20.01.2023

SQS requested the following support  from XHCrew:


Thursday and Friday of next week SQS expect to carry on some installation works in their hutch with expected activities:

- To make modifications to an existing frame
- To assemble a new frame
- Support with craning into the hutch of COMO source

 

  409   22 Sep 2023, 10:47 Orkidia BilaniXHEXPInformationSQS Support in XHEXP1

SQS doesn't have many space left in their assembly area. Talked/dealed with the SQS colleagues, and managed to free spaces :-).

The parts/components will be transported to XHE1 and to Ütersen.

Sascha will do the transport to XHE1 on his shift over the weekend. The transport to Ütersen will be done next week.

 

Coworkers: O.Bilani, N. Rennhack, J. Montano, A. Igharas, S. Menzel, S. Dold

 

  573   27 Feb 2024, 15:43 Orkidia BilaniXHEXPInformationSQS Support in XHE1

Suppoerted SQS in XHE1 with disassembling parts from the cluster source and transported these components back to XHEXP1.

Co-workers: Y. Ovcharenko, A. Igharas, O. Bilani

Attachment 1: SQS.png
SQS.png
  381   23 Aug 2023, 13:29 Sascha MenzelXHEXPInformationSQS Support am 22.08.2023

Bei SASE3 die Seitenwände vom Laserraum zwischen SASE3 und SASE1 demontiert (geöffnet) dann zwei Schubladenschränke mit dem Hubwagen weg transportiert. Diverse Leitungen und Kühlwasserschläuche demontiert und die drei Lasertische mittels mobielen Kran aus dem Laserraum gekrant und auf Transportrollen gestellt. Die Lasertische zur SQS Area transportiert und mittels Hallenkran in Holzkisten gekrant. Die Holzkisten hatte zuvor O.Smith in die Halle transportiert. Einen Chiller aus dem Laserraum von der Wasserversorgung getrennt und aus dem Raum transportiert. Zum Schluss die Wandelemente wieder montiert und die Wand somit geschlossen.

Coworkers: S.Menzel, N.Rennhack, D.Raiser, A.Igharas und T.Mullins

Attachment 1: Image20230823124712.jpg
Image20230823124712.jpg
Attachment 2: Image20230823124715.jpg
Image20230823124715.jpg
Attachment 3: Image20230823124717.jpg
Image20230823124717.jpg
Attachment 4: Image20230823124720.jpg
Image20230823124720.jpg
Attachment 5: Image20230823124722.jpg
Image20230823124722.jpg
Attachment 6: Image20230823124726.jpg
Image20230823124726.jpg
Attachment 7: Image20230823124729.jpg
Image20230823124729.jpg
Attachment 8: Image20230823124731.jpg
Image20230823124731.jpg
Attachment 9: Image20230823124736.jpg
Image20230823124736.jpg
Attachment 10: Image20230823124740.jpg
Image20230823124740.jpg
Attachment 11: Image20230823124742.jpg
Image20230823124742.jpg
Attachment 12: Image20230823124747.jpg
Image20230823124747.jpg
Attachment 13: Image20230823124749.jpg
Image20230823124749.jpg
Attachment 14: IMG_7084.jpg
IMG_7084.jpg
  456   01 Nov 2023, 11:07 Orkidia BilaniXHEXPInformationSQS Support

Discussed with T.Mazza on Monday, 30.10.2023, about storing temporarily in XHE1 the wooden boxes of an equipment they recevied recently. 

They should be stored until the equipment is tested and working, so that if something goes wrong, it can be shipped to the manufacturer with the original Verpackung 

If all fine, they will be disposed, most probably by the end of winter maintenance period.

 

Transport was done!

Co-workers: S.Menzel. O.Bilani, J. Montano

Attachment 1: IMG_20231030_131455_MP.jpg
IMG_20231030_131455_MP.jpg
Attachment 2: IMG_20231030_131503_MP.jpg
IMG_20231030_131503_MP.jpg
  480   28 Nov 2023, 19:33 Orkidia BilaniXHEXPInformationSQS Support

Supported SQS with carrying the top small cabinets and placing them on the bigger ones.

Co-workers: O. Bilani,  M. Peter, A. Igharas, J. Montano

  481   29 Nov 2023, 19:46 Orkidia BilaniXHEXPInformationSQS Support

Brought Back from XHE1 into the Experiment Hall the "PAM - Chambers".

Co-workers: O. Bilani, H. Heuer

 

Attachment 1: IMG_20231129_133338_MP.jpg
IMG_20231129_133338_MP.jpg
  760   07 Aug 2024, 21:00 Orkidia BilaniXHEXPInformationSQS Support

Dismounted a R+K "Gestell" of SQS. Brought the R+K to the Warehouse. 

The wheels are still in the Exp.Hall, because maybe Sascha and Paul would need them soon.

Attachment 1: IMG_20240807_203521_HDR.jpg
IMG_20240807_203521_HDR.jpg